A4 SXHT 16-1037 Rpr Str and Prk Var PAFB SOW 053025_Redacted.pdf

PDF 986 KB Posted

Attached to
SXHT 16-1037 Repair Streets & Parking Various PSFB Federal contract opportunity
Solicitation number
FA252125B0010
Issued by
Department of the Air Force Space Command

About this file

This Project Statement of Work (SOW) details a construction contract for repairing streets and parking areas at Patrick Space Force Base (PSFB) in Florida. The project involves demolishing and reconstructing portions of Challenger Street and Falcon Avenue, including road base replacement, repaving, installing concrete curbing, drainage structures, traffic control devices, and road centerlines, all in compliance with MUTCD standards. The work scope requires complete demolition and removal of existing surfaces, proper debris disposal, grading for positive drainage, and installing new infrastructure according to FDOT, ASTM, and military specifications.

Key contract requirements include providing a Project Manager, implementing a comprehensive Quality Control Plan, submitting a Site Safety Plan, and ensuring environmental protection. The project has a 90-calendar-day performance period, is set aside exclusively for small businesses, and has an estimated value between $500,000 and $1,000,000. The solicitation (FA252125B0010) is issued by the Department of the Air Force Space Command, with critical dates including a site visit on 31 July, questions due by 5 August, and bids due on 21 August 2025. Funding availability is contingent on appropriated funds, and the contract will be awarded as a Firm-Fixed-Price construction contract.

View the file

Other files for this federal contract opportunity

Other files attached to SXHT 16-1037 Repair Streets & Parking Various PSFB, newest first.
File Type Posted
FA252125B0010_Abstract of Offers.pdf PDF
Solicitation Amendment FA252125B00100003 SF 30.pdf PDF
Solicitation Amendment - FA252125B00100003.pdf PDF
A1 SXHT 16-1037 Rpr Strts and Prkng SPECS FNL REV 080725.pdf PDF
Solicitation Amendment - FA252125B00100002.pdf PDF
Solicitation Amendment FA252125B00100002 SF 30.pdf PDF
SXHT 161037 Qustns and Answrs 1 080625 REV.pdf PDF
Solicitation Amendment FA252125B00100001 SF 30.pdf PDF
SXHT 161037 Qustns and Answrs 1 080625.pdf PDF
Solicitation Amendment - FA252125B00100001.pdf PDF
Site Visit Sign in Sheet.pdf PDF
A12 Badge Request 45 SFS Form V14.pdf PDF
A8 SXHT 16-1037_Liquidated Damages 2025.pdf PDF
A9 Energy Management and Control Systems Standards.pdf PDF
A11 Small Business Self Performance Worksheet.pdf PDF
Solicitation - FA252125B0010.pdf PDF
A10 QUESTION AND ANSWER FORM.docx DOCX document
A14 SXHT 16-1037 CECC Form 3052.xlsx XLSX spreadsheet
A1 SXHT 16-1037 Rpr Strts and Prkng SPECS.pdf PDF
A5 SXHT 16-1037 GPP Certification.pdf PDF
A6 SXHT 16-1037 Haz Waste.pdf PDF
A7 SXHT 16-1037 ODS.pdf PDF
A12 Badge Request 45 SFS Form V14.pdf PDF
A2 SXHT 16-1037-G-001 071525 REV Drwngs.pdf PDF
A3 SXHT 16-1037- Submittal Register 062525.xlsx XLSX spreadsheet
A13 DBA Wage Determination_4Jul2025.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT STATEMENT OF WORK REV1

TITLE: Construct Project “Repair Streets & Parking, Various PAFB”

PROJECT NUMBER: SXHT 16-1037

DATE: 28 May 2025

REVISION: 01

2. Applicable Documents: The work shall conform to the most recent issue of the following standards and publications. The following shall be considered a partial list, and the contractor is responsible for identifying and complying with all applicable standards, regulations, and codes.

a. The Manual of Uniform Traffic Control Devices

b. FDOT Design Manual

c. Air Force Instructions (AFIs)

d. Military Standards (MIL-STD)

e. Military Specifications (MIL-Spec)

f. SDDCTEA 55-17 and other pamphlets

g. PSFB Installation Facilities Standards

h. Asphalt Institute Design Standards

i. The Portland Cement Association Design Standards

j. ASTM Standards

k. SXHT 13-1037 “Maintain Streets and Parking,” Challenger Street Design

l. SXHT 13-1231 “Repair Stormwater Piping NS, PAFB,”/2012 SES SW SYS Study Report

3. Requirements

• Project Management: The contractor shall provide a designated Project Manager who will serve as the primary point of contact and be responsible for all aspects of the project, from initial planning to final acceptance.

• Quality Engineer: The contractor shall implement a comprehensive Quality Control Plan (QCP) to ensure that all work meets or exceeds the specified requirements and standards. The QCP shall include procedures for inspection, testing, and documentation.

• Safety: The contractor shall adhere to all applicable safety regulations and maintain a safe work environment. A Site Safety Plan (SSP) shall be submitted to 45 CES/CEN for approval prior to the start of work. This plan shall include measures for traffic control, worker safety, and protection of the environment.

• Environmental Protection: The contractor shall implement appropriate measures to protect the environment during all phases of the project. This includes preventing soil erosion, controlling dust, managing stormwater runoff, and properly disposing of all waste materials. Compliance with PSFB environmental regulations is mandatory.

• Construction Management/Inspection: Provide oversight and inspection of the work to ensure compliance with the SOW and all applicable standards.

PROJECT STATEMENT OF WORK REV1

TITLE: Construct Project “Repair Streets & Parking, Various PAFB”

PROJECT NUMBER: SXHT 16-1037

DATE: 28 May 2025

REVISION: 01

3.1 Project Schedule and Milestones

• Period of Performance 90 calendar days