13. Price Schedule.xlsx
XLSX spreadsheet 22 KB Posted
- Solicitation number
- FA252121R0005
About this file
This document contains a price schedule and statement of work for a federal contract solicitation to provide fire protection, emergency management, and emergency medical services at Cape Canaveral Space Force Station in Florida. The incumbent contractor will provide continuous fire protection, emergency management, and emergency medical services on a 24/7 basis over a five year base period and one six-month extension option. Services include fully staffing three fire stations, providing emergency management and medical services, and reimbursing fuel costs. Pricing is established at $36,000 per year for the base and four option years, and $18,000 for the six-month extension. The total evaluated price is $198,000. The solicitation was issued by the Department of the Air Force Space Command to obtain these services on a follow-on acquisition to contract FA252120R0036.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule - Summary
| CLIN | CONTRACT YEAR | DESCRIPTION | AMOUNT | |
| 0001 | Phase In/ Base Period | Provide Phase-In Period for the new contractor of the Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS), FL. | ||
| PoP EST:1 Aug 21 - 30 Sep 21 | $ - 0 | |||
| 1001-1005 | First Option Year | Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS), FL. | ||
| PoP EST:1 Oct 21 - 30 Sep 22 | $ 36,000.00 | |||
| 2001-2005 | Second Option Year | Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS), FL. | ||
| PoP EST:1 Oct 22 - 30 Sep 23 | $ 36,000.00 | |||
| 3001-3005 | Third Option Year | Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS), FL. | ||
| PoP EST:1 Oct 23 - 30 Sep 24 | $ 36,000.00 | |||
| 4001-4005 | Fourth Option Year | Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS), FL. | ||
| PoP EST:1 Oct 24 - 30 Sep 25 | $ 36,000.00 | |||
| 5001-5005 | Fifth Option Year | Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS), FL. | ||
| PoP EST:1 Oct 25 - 30 Sep 26 | $ 36,000.00 | |||
| 6001-6005 | Six Month Extention | Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS), FL. | ||
| PoP EST: 1 Oct 26 - 1 Apr 27 | $ 18,000.00 |
Total Evaluated Price (TEP) $ 198,000.00
PoP = Period of Performance
Phase-in Base Period
| ITEM | SCOPE OF WORK DESCRIPTION | |||
| Unit costs are all inclusive to include labor, material, equipment, transportation, profit, overhead, all and any direct and/or indirect costs etc., that is, any cost that can be associated with the scope of the line item is to be include in the unit cost. | UNIT | EST QUANT | UNIT | |
| COST | TOTAL | |||
| 0001 | Phase-in/Base Period Provide Phase-In Period for the new contractor of the Fire Protection, Emergency Management and Emergency Medical Services (FEMS) IV contract for Cape Canaveral Space Force Station (CCSFS) in accordance with Statement of Work para 4.1 and the Offeror's proposal. | |||
| Months | 2 | $ - 0 |
Project Total $0.00
Option Year One
| ITEM | SCOPE OF WORK DESCRIPTION | |||
| Unit costs are all inclusive to include labor, material, equipment, transportation, profit, overhead, all and any direct and/or indirect costs etc., that is, any cost that can be associated with the scope of the line item is to be include in the unit cost. | Period of Performance | UNIT | EST QUANT | UNIT |
| COST | TOTAL | |||
| 1001 | Fire Protection (Main & Station #2) Provide Fire Protection Services to fully staff the Main Fire Station Bldg. 50012 and Fire Station #2 Bldg. 70535 at Cape Canaveral Space Force Station (CCSFS) FL. | |||
| 1 Oct 21 - 30 Sep 22 | Months | 12 | $ - 0 | |
| 1002 | Emergency Management Provide Emergency Management Services at Cape Canaveral Space Force Station (CCAFS), FL. | |||
| 1 Oct 21 - 30 Sep 22 | Months | 12 | $ - 0 | |
| 1003 | Emergency Medical Services Provide Emergency Medical Services at Cape Canaveral Space Force Station (CCAFS), FL. | |||
| 1 Oct 21 - 30 Sep 22 | Months | 12 | $ - 0 | |
| 1004 | Fire Protection (3rd Fire station) Provide Fire Protection Services to fully man the third fire station Bldg. 85010 at Cape Canaveral Air Force Station (CCSFS), FL. | |||
| 1 Oct 21 - 30 Sep 22 | Months | 12 | $ - 0 | |
| 1005 | Fuel Cost The contractor shall provide fuel required in the performance of this contract in accordance with the Statement of Work paragraph 6.2. Reimbursement will be on a cost reimbursement basis exclusive of profit or fee. | |||
| 1 Oct 21 - 30 Sep 22 | Months | 12 | $ 3,000.00 | $ 36,000.00 |
Project Total $36,000.00
Option Year Two
| ITEM | SCOPE OF WORK DESCRIPTION | ||||||
| Unit costs are all inclusive to include labor, material, equipment, transportation, profit, overhead, all and any direct and/or indirect costs etc., that is, any cost that can be associated with the scope of the line item is to be include in the unit cost. | Period of | ||||||
| Performance | UNIT | EST QUANT | UNIT | ||||
| COST | TOTAL | ||||||
| 2001 | Fire Protection (Main & Station #2) Provide Fire Protection Services to fully staff the Main Fire Station Bldg 50012 and Fire Station #2 Bldg 70535 at Cape Canaveral Space Force Station (CCSFS) FL. | 1 Oct 22 - 30 Sep 23 | Months | 12 | $ - 0 | ||
| 2002 | Emergency Management Provide Emergency Management Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 22 - 30 Sep 23 | Months | 12 | $ - 0 | ||
| 2003 | Emergency Medical Services Provide Emergency Medical Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 22 - 30 Sep 23 | Months | 12 | $ - 0 | ||
| 2004 | Fire Protection (3rd Fire station) Provide Fire Protection Services to fully man the third fire station Bldg 85010 at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 22 - 30 Sep 23 | Months | 12 | $ - 0 | ||
| 2005 | Fuel Cost The contractor shall provide fuel required in the performance of this contract in accordance with the Statement of Work paragraph 6.2. Reimbursement will be on a cost reimbursement basis exclusive of profit or fee. | 1 Oct 22 - 30 Sep 23 | Months | 12 | $ 3,000.00 | $ 36,000.00 |
Project Total $36,000.00
Option Year Three
| ITEM | SCOPE OF WORK DESCRIPTION | ||||||
| Unit costs are all inclusive to include labor, material, equipment, transportation, profit, overhead, all and any direct and/or indirect costs etc., that is, any cost that can be associated with the scope of the line item is to be include in the unit cost. | Period of | ||||||
| Performance | UNIT | EST QUANT | UNIT | ||||
| COST | TOTAL | ||||||
| 3001 | Fire Protection (Main & Station #2) Provide Fire Protection Services to fully staff the Main Fire Station Bldg 50012 and Fire Station #2 Bldg 70535 at Cape Canaveral Space Force Station (CCSFS) FL. | 1 Oct 23 - 30 Sep 24 | Months | 12 | $ - 0 | ||
| 3002 | Emergency Management Provide Emergency Management Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 23 - 30 Sep 24 | Months | 12 | $ - 0 | ||
| 3003 | Emergency Medical Services Provide Emergency Medical Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 23 - 30 Sep 24 | Months | 12 | $ - 0 | ||
| 3004 | Fire Protection (3rd Fire station) Provide Fire Protection Services to fully man the third fire station Bldg 85010 at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 23 - 30 Sep 24 | Months | 12 | $ - 0 | ||
| 3005 | Fuel Cost The contractor shall provide fuel required in the performance of this contract in accordance with the Statement of Work paragraph 6.2. Reimbursement will be on a cost reimbursement basis exclusive of profit or fee. | 1 Oct 23 - 30 Sep 24 | Months | 12 | $ 3,000.00 | $ 36,000.00 |
Project Total $36,000.00
Option Year Four
| ITEM | SCOPE OF WORK DESCRIPTION | ||||||
| Unit costs are all inclusive to include labor, material, equipment, transportation, profit, overhead, all and any direct and/or indirect costs etc., that is, any cost that can be associated with the scope of the line item is to be include in the unit cost. | Period of | ||||||
| Performance | UNIT | EST QUANT | UNIT | ||||
| COST | TOTAL | ||||||
| 4001 | Fire Protection (Main & Station #2) Provide Fire Protection Services to fully staff the Main Fire Station Bldg 50012 and Fire Station #2 Bldg 70535 at Cape Canaveral Space Force Station (CCSFS) FL. | 1 Oct 24 - 30 Sep 25 | Months | 12 | $ - 0 | ||
| 4002 | Emergency Management Provide Emergency Management Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 24 - 30 Sep 25 | Months | 12 | $ - 0 | ||
| 4003 | Emergency Medical Services Provide Emergency Medical Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 24 - 30 Sep 25 | Months | 12 | $ - 0 | ||
| 4004 | Fire Protection (3rd Fire station) Provide Fire Protection Services to fully man the third fire station Bldg 85010 at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 24 - 30 Sep 25 | Months | 12 | $ - 0 | ||
| 4005 | Fuel Cost The contractor shall provide fuel required in the performance of this contract in accordance with the Statement of Work paragraph 6.2. Reimbursement will be on a cost reimbursement basis exclusive of profit or fee. | 1 Oct 24 - 30 Sep 25 | Months | 12 | $ 3,000.00 | $ 36,000.00 |
Project Total $36,000.00
Option Year Five
| ITEM | SCOPE OF WORK DESCRIPTION | ||||||
| Unit costs are all inclusive to include labor, material, equipment, transportation, profit, overhead, all and any direct and/or indirect costs etc., that is, any cost that can be associated with the scope of the line item is to be include in the unit cost. | Period of | ||||||
| Performance | UNIT | EST QUANT | UNIT | ||||
| COST | TOTAL | ||||||
| 5001 | Fire Protection (Main & Station #2) Provide Fire Protection Services to fully staff the Main Fire Station Bldg 50012 and Fire Station #2 Bldg 70535 at Cape Canaveral Space Force Station (CCSFS) FL. | 1 Oct 25 - 30 Sep 26 | Months | 12 | $ - 0 | ||
| 5002 | Emergency Management Provide Emergency Management Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 25 - 30 Sep 26 | Months | 12 | $ - 0 | ||
| 5003 | Emergency Medical Services Provide Emergency Medical Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 25 - 30 Sep 26 | Months | 12 | $ - 0 | ||
| 5004 | Fire Protection (3rd Fire station) Provide Fire Protection Services to fully man the third fire station Bldg 85010 at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 25 - 30 Sep 26 | Months | 12 | $ - 0 | ||
| 5005 | Fuel Cost The contractor shall provide fuel required in the performance of this contract in accordance with the Statement of Work paragraph 6.2. Reimbursement will be on a cost reimbursement basis exclusive of profit or fee. | 1 Oct 25 - 30 Sep 26 | Months | 12 | $ 3,000.00 | $ 36,000.00 |
Project Total $36,000.00
6 Mo. Extension
| ITEM | SCOPE OF WORK DESCRIPTION | ||||||
| Unit costs are all inclusive to include labor, material, equipment, transportation, profit, overhead, all and any direct and/or indirect costs etc., that is, any cost that can be associated with the scope of the line item is to be include in the unit cost. | Period of | ||||||
| Performance | UNIT | EST QUANT | UNIT | ||||
| COST | TOTAL | ||||||
| 6001 | Fire Protection (Main & Station #2) Provide Fire Protection Services to fully staff the Main Fire Station Bldg 50012 and Fire Station #2 Bldg 70535 at Cape Canaveral Space Force Station (CCSFS) FL. | 1 Oct 26 - 1 Apr 27 | Months | 6 | $ - 0 | ||
| 6002 | Emergency Management Provide Emergency Management Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 26 - 1 Apr 27 | Months | 6 | $ - 0 | ||
| 6003 | Emergency Medical Services Provide Emergency Medical Services at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 26 - 1 Apr 27 | Months | 6 | $ - 0 | ||
| 6004 | Fire Protection (3rd Fire station) Provide Fire Protection Services to fully man the third fire station Bldg 85010 at Cape Canaveral Space Force Station (CCSFS), FL. | 1 Oct 26 - 1 Apr 27 | Months | 6 | $ - 0 | ||
| 6005 | Fuel Cost The contractor shall provide fuel required in the performance of this contract in accordance with the Statement of Work paragraph 6.2. Reimbursement will be on a cost reimbursement basis exclusive of profit or fee. | 1 Oct 26 - 1 Apr 27 | Months | 6 | $ 3,000.00 | $ 18,000.00 |
Project Total $18,000.00