Attachment 10d - DPAS Implementation Schedule.pdf

PDF 137 KB Posted

Attached to
Instrumentation Range Support Program Federal contract opportunity
Solicitation number
FA2521-20-R-0006
Issued by
Department of the Air Force Space Command

About this file

This document outlines an implementation schedule for the Instrumentation Range Support Program (IRSP) contract. Key details include:

  • The schedule spans 363 days from January 1, 2021 to May 24, 2022. It details 28 tasks related to modifying the contract, designating the contractor as a CICP, completing inventory, validating data, and achieving full operating capability in the DPAS system. Successful completion of preceding tasks is often listed as a dependency for following tasks.

  • The solicitation was reposted on beta.SAM.gov as FA2521-20-R-0006 after originally being posted on FBO.gov as FA2521-18-R-0024. The opportunity is for the Instrumentation Range Support Program III contract managed by the Department of the Air Force Space Command. The attachment provides additional context regarding documents associated with the solicitation but does not specify products/services required under the contract.

View the file

Other files for this federal contract opportunity

Other files attached to Instrumentation Range Support Program, newest first.
File Type Posted
Whats New-Bidders Library V13.pdf PDF
Amend 2_Solicitation FA252120R00060002.pdf PDF
Amend 2_Attachment Section L.pdf PDF
Amend 2_Attachment L-11 TEP Cost Workbook.xlsx XLSX spreadsheet
RFP Question and Response List Nov 25 2019.pdf PDF
Amend 1_Attachment L-08 Performance Eval Questionnaire SYSTEM ERROR FIXED.pdf PDF
IRSP III RFP Question and Response List REVISED.pdf PDF
Attachment L-03 IRSP Phase Out Plan Final_Redacted.pdf PDF
Attachment 2 GFE List.xlsx XLSX spreadsheet
Attachment L-05 Sample System Mod Final.pdf PDF
Attachment 6 - RESERVED Labor Rate_Fee Rate Listings.pdf PDF
Amend 1_Attachment 7 - Supported Range System List.pdf PDF
Whats New-Bidders Library V12.pdf PDF
Attachment L-02 Question Template.pdf PDF
Attachment 10-a 1-CICP Imp Guide v2_7_3_FINAL.docx DOCX document
Attachment 11 - FY 19 CFO Report Template.xlsx XLSX spreadsheet
Amend 1_Attachment L-01 Historical Info.pdf PDF
Attachment L-06 Eng and Obs Sample Final.pdf PDF
Attachment 10c - GFE Data Sheet.xlsx XLSX spreadsheet
Attachment L-07 Logistics Sample Final.pdf PDF
Attachment 3 GFM List.xlsx XLSX spreadsheet
Attachment 4 DD254.pdf PDF
Attachment 8 - Range Resource List.pdf PDF
Amend 1_Attachment 4 DD254.pdf PDF
Attachment L-09 PEQ Cover Letter.pdf PDF
Attachment Section M.pdf PDF
Attachment L-12 Compliance Matrix.pdf PDF
Amend 1_IRSP SOW .pdf PDF
Attachment 1 IRSP SOW.pdf PDF
Attachment L-11 TEP Cost Workbook 25 OCT 19.xlsx XLSX spreadsheet
Amend 1_Attachment L-11 TEP Cost Workbook.xlsx XLSX spreadsheet
IRSP III RFP Question and Response List.pdf PDF
Attachment 9 IRSP SBPCD.pdf PDF
Attachment 10e - 1-Imp Guide_Appendix_C.pdf PDF
Attachment L-01 Historical Info.pdf PDF
Attachment L-04 Overhaul Work Specification Final.pdf PDF
Attachment L-08 Performance Eval Questionnaire.pdf PDF
Attachment L-10 Sample Consent Letter.pdf PDF
Attachment Section L.pdf PDF
Exhibit IRSP CDRL Portfolio A-M.pdf PDF
Amend 1_Attachment Section L.pdf PDF
Amend 1_Attachment L-07 Logistics Sample Final.pdf PDF
Attachment 10a1 1-CICP Imp Guide v2_7-3 App_E.xlsx XLSX spreadsheet
Amend 1_Solicitation FA252120R00060001.pdf PDF
Amend 1_Attachment L-08 Performance Eval Questionnaire.pdf PDF
Attachment 7 - Supported Range System List .pdf PDF
Attachment 10b - 1-PMO Imp Guide v2_7_3_FINAL.docx DOCX document
Solicitation - FA2521-20-R-0006.pdf PDF
Attachment 5 CONOPS.pdf PDF
Show all 49

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IRSP-INF

Tasker Number

Task Name Duration Start Finish Predecessors

Instrumentation Range Support Program (IRSP), 363 days Fri 1/1/21 Tue 5/24/22

Implementation Starting Date 0 days Fri 1/1/21 Fri 1/1/21

Contract has been modified to include the CFO report CDRL

0 days Fri 1/1/21 Fri 1/1/21 2826

Contract has been modified to include the CICP Language for PWS

0 days Fri 1/1/21 Fri 1/1/21 2826

3 Contractor has been designated as a CICP 30 days Fri 1/1/21 Thu 2/11/21

2827, 2828

Program has requested and received the RIC/DoDAACs (EB, ED and FQ series) required

90 days Fri 2/12/21

Thu 6/17/21

5a CICP has modified its IT system to send and receive DLMS transactions

1 day Fri 1/1/21 Fri 1/1/21 2828

5b CICP has a completed and signed interface control agreement (ICA) with DAAS to interface with DPAS

90 days Fri 6/18/21

Thu 10/21/21

5c CICP has completed DLMS transaction testing with DAAS and DPAS

60 days Fri 10/22/21

Thu 1/13/22

2831, 2832

6 Data cleansing activities have been completed 240 days Fri 1/1/21 Thu 12/2/21

The appropriate valuation methodology been determined for all stock numbers

60 days Fri 1/1/21 Thu 3/25/21

7a If using the deemed cost methodology, Memorandum for the Record (MFRs) have been completed to document the methodology

180 days Fri 3/26/21

Thu 12/2/21

CICP has completed a 100% inventory of assets listed on the contract within the last 90 days

90 days Tue 6/1/21

Mon 10/4/21

9 Program office has determined its’ DPAS users 90 days Fri 1/1/21 Thu 5/6/21

FA2521-19-R-A007

(REF FA2521-18-R-0024)

RFP Attachment 10d

IRSP-INF

Program has determined which GFM-A process responsibilities it will delegate to their CICP

90 days Fri 1/1/21 Thu 5/6/21

11 CICP has determined its’ DPAS users 90 days Fri 1/1/21 Thu 5/6/21

DPAS users from the program and CICP have completed the required training to perform their roles in DPAS

30 days Fri 5/7/21 Thu 6/17/21

28382840

DPAS users from the program and CICP submitted their paperwork for DPAS accounts

30 days Fri 5/7/21 Thu 6/17/21

2838, 2840

Program/CICP completed the DPAS data conversion spreadsheet

60 days Wed 9/1/21

Tue 11/23/21

DPAS data conversion spreadsheet pass validation 10 days Wed 11/24/21

Tue 12/7/21

DPAS loads data in pre-production environment 10 days Wed 12/8/21

Tue 12/21/21

The initial data load been validated for accuracy in DPAS pre-production environment

30 days Wed 12/22/21

Tue 2/1/22

DPAS moves data to DPAS production environment

10 days Wed 2/2/22

Tue 2/15/22

Financial thresholds have been set for inventory adjustments, disposal and condemnation requests by the PMO in DPAS

30 days Wed 2/16/22

Tue 3/29/22

CICP transmits beginning balances to DPAS 10 days Wed 3/30/22

Tue 4/12/22

Beginning balances have been validated for accuracy in DPAS

30 days Wed 4/13/22

Tue 5/24/22

Stock number valuations have been validated for accuracy in DPAS

30 days Wed 4/13/22

Tue 5/24/22

19 IRSP - Go-Live Date 0 days Tue 5/24/22

Tue 5/24/22

2850, 2851

IRSP-INF