Exhibits 15-15E A-E Const IDIQ Pricing.pdf

PDF 474 KB Posted

Attached to
DRAFT RFP - Repairs, Operations, Maintenance, and Engineering (ROME) Services - DRAFT RFP Federal contract opportunity
Solicitation number
80GSFC22R0011-DRFP
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This is a draft Request for Proposal for Repairs, Operations, Maintenance, and Engineering (ROME) services to be provided at Goddard Space Flight Center in Greenbelt, Maryland and Wallops Flight Facility in Wallops Island, Virginia. The contractor shall provide facilities support services including facilities operations and maintenance, architect-engineering services, construction services, and facilities information resources services. Facilities cover office buildings, technical facilities, laboratories, launch facilities, an airfield, and warehouses. Utilities supported include electrical power, water, wastewater, storm water, steam, chilled water, gas, fire alarm, and utility control systems. Custodial services are excluded. The RFP seeks these ROME services to support facilities operations and maintenance for NASA facilities at the specified locations.

View the file

Other files for this federal contract opportunity

Other files attached to DRAFT RFP - Repairs, Operations, Maintenance, and Engineering (ROME) Services - DRAFT RFP, newest first.
File Type Posted
ROME E-Library Documents.zip ZIP file
Exhibit 14 ROME Past Perf Questionaire.pdf PDF
Enclosure 3 ROME RTO3 Navy OM IR.pdf PDF
Attachment C1 - GB List of IAGP.pdf PDF
Attachment C2 - Wallops List of IAGP.pdf PDF
Attachment H IT Security Management Plan.pdf PDF
Attachment K Safety and Health Plan.pdf PDF
Attachment N Wage Determinations Building.pdf PDF
N.2 Davis Bacon Wage Determination VA 20220007.txt TXT text file
Appendix 17 Snow Removal Area 100 GB.pdf PDF
Appendix 20 Snow Maps WFF.pdf PDF
Appendix 13 - ROME Position Qualifications.pdf PDF
Appendix 9-SUBMITTAL REGISTER.pdf PDF
Appendix 11 - Application Systems List (Admin and OT).pdf PDF
Appendix 15 Snow Removal Roads Parking GB.pdf PDF
Appendix 19 Snow Removal Area 300 and 400 GB.pdf PDF
80GSFC22R0011 Cover Letter.pdf PDF
Enclosure 1 ROME RTO1 Greenbelt OM IR.pdf PDF
Enclosure 2 ROME RTO2 WFF OM IR.pdf PDF
Enclosure 4 ROME QA Surveillance Plan.pdf PDF
Enclosure 5 IT Security Management Plan Template.pdf PDF
Attachment I OCI Avoidance Plan Outline.pdf PDF
Attachment L ROME FINANCIAL REPORTING 533.pdf PDF
Attachment M Collective Bargaining Agreement.pdf PDF
M.2 WD CBA 2022-134 Virginia.pdf PDF
Attachment O Wage Determinations SCA.pdf PDF
Appendix 8 - RESERVED.pdf PDF
Appendix 16 Snow Removal Sidewalks GB.pdf PDF
Appendix 4 - List of Facilities final.pdf PDF
80GSFC22R0011 SF33 ROME DRFP.pdf PDF
Appendix 4 - List of Facilities.pdf PDF
Appendix 7 - Navy SCSC Assets.pdf PDF
Attachment D DD254-ROME.pdf PDF
Attachment F Quality Control Plan.pdf PDF
Attachment J Contract Historical Data.pdf PDF
O.2 Wage Determination SCA VA 2015-4327.txt TXT text file
Appendix 12 As-Built.pdf PDF
Appendix 10 - ROME Specifications.pdf PDF
Appendix 1 - ROME SRD -2021 .pdf PDF
Appendix 14 Snow and Ice Removal GB.pdf PDF
Appendix 18 Snow Removal Area 200 GB.pdf PDF
80GSFC22R0011 ROME DRFP.pdf PDF
Exhibits 1-13A ROME COST.pdf PDF
Attachment A - ROME Contract SOW.pdf PDF
Attachment B IDIQ Cost-Fixed Price Rate Matrix All IDIQ Contract.pdf PDF
Attachment C - List of IAGP.pdf PDF
Attachment D DD254.pdf PDF
Attachment E A-E Const IDIQ Pricing.pdf PDF
Attachment G IT Security Applicable Documents List.pdf PDF
M.1 WD CBA 2022-99 Maryland.pdf PDF
Show all 50

DRAFT RFP - Repairs, Operations, Maintenance, and Engineering (ROME) Services - DRAFT RFP has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) ARCHITECT AND ENGINEERING (A-E) SERVICES Minimum qualifications for the disciplines specified below are set forth in Appendix 13.

Offerors shall propose loaded (incl. burden, G&A, overhead and profit) hourly rates for the following skill disiplines.

Contract Year 1 Proposed Annual IDIQ Loaded Estimated Est. Annual

Discipline Hourly Rate ($/hr) Hours A-E Price Senior Architect X 1,000 = -$ Architect X 700 = -$ Senior Civil Engineer X 500 = -$ Civil Engineer X 500 = -$ Senior Mechanical Engineer X 2,000 = -$ Mechanical Engineer X 1,000 = -$ Senior Electrical Engineer X 1,500 = -$ Electrical Engineer X 1,000 = -$ Senior Structural Engineer X 500 = -$ Structural Engineer X 500 = -$ Fire Protec ion Engineer X 1,000 = -$ Environmental Engineer X 500 = -$ Estimator X 1,000 = -$ Specification Writer X 300 = -$ CADD/BIM Technician X 500 = -$ Project Manager X 1,000 = -$ Interior Designer X 500 = -$ Scheduler X 1,000 = -$ Planner X 1,000 = -$ Sr. Systems Analyst X 300 = -$ Sr. Programmer Analyst X 300 = -$ Certified Surveyor X 200 = -$ GIS Technician X 200 = -$

TOTAL ESTIMATED FOR CONTRACT YEAR 1 -$

Specialty A-E Subcontractor Mark-up (%) % X $200,000 = $

TOTAL Year 1 A-E Services (sum of hourly costs and specialty fee) #VALUE!

(b) CONSTRUCTION SERVICES

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Minimum Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 1,000,000$ = -$ >$100K X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Full Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 200,000$ = -$ $100K to $1M X 800,000$ = -$ >$1M X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

EXHIBIT 15 ROME IDIQ A-E & Construction Prices - Year 1

Offerors shall propose a Specialty Subcontractor Fee percentage below to be applied to specialty subcontractor quotes for A-E Services as described in the Statement of Work.

Offerors shall propose Construction Management Coefficients below to be applied to the actual construction cost as described in he Statement of Work.

IDIQ

Construction/Design-Build Coefficient Estimated Design-Bid-Build Construction Only Construction/ Annual Annual

Design-Build Estimated Construction Project Value Coefficient Construction Price

$0 to $100K X 700,000$ = -$ $100K to $1M X 7,000,000$ = -$ >$1M X 4,000,000$ = -$

TOTAL WITH CONSTRUCTION-ONLY COEFFICIENT 11,700,000$ -$

Annual TOTAL Construction (incl. D-B Minimum, D-B Full, and D-B-B Construction only) $ -

Pre-Priced Construction

Estimated Annual LABEL Unit Price ($) Unit Quantity Price

A-1 Remove Vinyl Composition Tile – remove ile and adhesive. SF X 10,000 = -$ A-2 Furnish & Install (F/I) VCT – includes subfloor prepara ion when required. SF X 10,000 = -$

A-3 Flash Patch Floor – entails application of leveling grout and final cleaning for new VCT or carpet. Assumes project size of 400 sf or larger, otherwise produc ivity adjustment. SF X 2,000 = -$

A-4 Remove Carpet – remove carpet and adhesive. SF X 30,000 = -$

A-5 F/I Carpet Floor Tile SF X 30,000 = -$

A-6

R mo e nd R nst replacement only. Light furniture relocation included. Heavy equipment and furniture to be relocated by others. SF X 2,000 = -$

A-7 Remove Cove Base. LF X 1,000 = -$

A-8 F/I Cove Base. LF X 1,000 = -$

A-9 Demo CMU Wall – not cut-out demo. No toothing. Assumes full wall sec ions at least 10’ long. Includes dust protec ion. CY X 50 = -$

A-10 Demo Stud Wall – includes saw cutting if necessary. SF X 5,000 = -$

A-11 Stud/Drywall Partition – includes constructing stud wall, drywall, taping, spackling, and finishing; excludes insulation. SF X 5,000 = -$

A-12 Skim Coat Patch Drywall – assumes entire wall needs refinishing. Includes applying Durabond and Lafarge compound skim coats. SF X 3,000 = -$

A-13 Prepare and Paint Walls – includes repairing any minor imperfections, sanding, and painting with 1 coat primer and 2 coats latex. SF X 25,000 = -$

A-14 F/I 1/4" drywall over existing wall - includes adhesive or mechanical fasteners and preparation for pain ing. SF X 25,000 = -$

A-15 F/I Room Signs – includes Hermes #723-087 frame with header and 3-lines. Only room number tag is included. EA X 50 = -$

A-16

Wall Penetrations up to 4" in diameter – used for conduit or pipe wall penetrations through masonry or partition walls. Core drilling through concrete not included. Fire caulk not included. EA X 20 = -$

A-17 Fire Caulk Penetration up to 4" in diameter – fire caulk only. Does not include special fire penetra ion assemblies. EA X 20 = -$

A-18 Demo Door and Frame – as part of wall demo or part of door replacement. EA X 50 = -$

A-19 F/I Wood Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 30 = -$

A-20 F/I Wood Door & Frame (6’x7’) – no cut-out or jamb work included. No finishing included. Not fire rated. Not an egress door. EA X 10 = -$

A-21 F/I Red Oak Door & Frame (3’x7’) – installed door with frame and hardware. EA X 10 = -$

A-22 F/I Metal Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 20 = -$

A-23 Paint Door and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 50 = -$

A-24 Paint Door and Half-Leaf and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 5 = -$

A-25 Remove and Replace Ceiling Tile – includes 2’x2’ tile and 2’x4’ tile. SF X 30,000 = -$ A-26 Demo Suspended Ceiling – removal of ceiling grid, suspension system and tiles. SF X 10,000 = -$

A-27 F/I Ceiling Grid and Tile – includes support attachments, suspension system, grid and tiles (2’x2’ or 2’x4’). SF X 10,000 = -$

A-28 F/I Handicapped Door Opener - per Construction Specifications requirements -includes push buttons door opening device, and provision of electrical power. EA X 5 = -$

E-1

F/I Light Swit h inc uding wiring, conduit ( n luding fit ings, conn ctors, hang , offsets, bends, etc.), box, wall plate, and wall plate identifica ion label. Includes up to 50 LF of wiring and conduit. EA X 50 = -$

E-2

F/I Receptacle – includes wiring, conduit (including fittings, connectors, hangers, offsets, bends, etc.), box, wall plate, and wall plate identifica ion label. Includes up to 50 LF of wiring and conduit (to panelboard). Update panelboard schedule. EA X 50 = -$

E-3 F/I Wire/Conduit for Lighting and Receptacle Circuits (25 LF) – includes wire and conduit (including fittings, hangers, offsets, etc). Wire and conduit size - 3#12, ¾" EMT. EA X 100 = -$

E-4 Remove Existing Lights – includes he removal of interior 2’ x 4’ fluorescent fixtures, wiring, and conduit back to nearest JB (10 LF). EA X 100 = -$

E-5

F/I New lights. Provide 2’ x 4’, 7200 lumens LED recessed fixture (Lithonia catalog # 2GTL4 72L EZ1 LP40 or equal). fixture supports, wire and conduit (including fittings, hangers, offsets, bends, etc.). Includes up to 6 LF of MC cable for connection to nearest junc ion box. Update panelboard schedule. Includes work up to 15 feet in height. EA X 50 = -$

E-6

F/I New lights. Provide 2’ x 4’, 5000 lumens LED recessed fixture (Lithonia catalog # 2AVL4 50L MDR EZ1 LP40 or equal). Includes up to 6 LF of MC cable for connection to nearest junc ion box. Update panelboard schedule. Includes work up to 15 feet in height. EA X 50 = -$

E-7

F/I Ceiling Mounted Motion Sensors (Lighting Control) – includes motion sensor (WattStopper W500A or equal), power pack, and all required wire and conduit. Includes up to 10 LF of power wiring/conduit and up to 50 LF of control wiring (from power pack to sensor). EA X 20 = -$

E-8 F/I 700 Wiremold – includes wiremold (10 LF), box, wall plate, connector, and fittings. EA X 30 = -$

E-9 F/I New Receptacle or Switch using Wiremold – includes wire, and wall plate identification label. EA X 20 = -$

E-10 F/I Power/LAN Floor Box – entails a complete installation including core drill floor penetration, conduit, drilling, anchors, water control, etc. EA X 20 = -$

E-11 Remove Power/LAN Floor Box – entails a complete removal of box, conduit, wire and patching the floor. EA X 20 = -$

E-12 Remove Receptacle – entails complete removal back to nearest junction box. Not to exceed 10’. Trace circuit. EA X 50 = -$

E-13 Remove Wiremold (700) (per 10’) – includes demo of wire and receptacles. EA X 50 = -$ E-14 Demo Wire/Conduit (per 10’) – includes hangers and straps. EA X 300 = -$

E-15 Remove Circuit Breakers 20-90A 1P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 100 = -$

E-16 Remove Circuit Breakers 20-100A 2P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-17 Remove Circuit Breakers 20-100A 3P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-18 Remove Underfloor Quads (30’ liquidtight) – includes removal of conduit and wire from power source and relabeling. EA X 20 = -$

E-19 Remove/Blank-off Telephone Floor Stacks – includes removal of conduit and wire to nearest J-box. Blank off wi h floor inserts. EA X 20 = -$

E-20

F/I Underfloor Quads (30’ liquidtight) – includes circuit breaker, ¾" sealtite, #12 wire from power source to underfloor location. Includes KO’s, connectors, terms, boxes, covers, receptacles. Does not include lock out/tag out or R&R panel cover. EA X 25 = -$

E-21 Demo Wall Switch – includes removal of conduit/wire back to J-box and wall patching. EA X 100 = -$

F-1 Demo Sprinkler Head – includes removal of head, pipe hangers and replace ceiling tile. EA X 100 = -$

F-2 Update Sprinkler Head – involves replacement with a new head at the same location.

Includes pipe modifications, escutcheons, ceiling tile. EA X 100 = -$

F-3

Relocate Sprinkler Head – includes piping, anchoring, hangers, escutcheons, ceiling tile. Maximum distance is 5' -0" in one direction (left, right, straight, or down) from the original location of the sprinkler head elbow down turn. EA X 100 = -$

F-4 Demo Smoke Detector – includes removal of conduit/wire back to J-box. EA X 40 = -$ F-5 Demo Motion Sensor – includes removal of conduit/wire back to j-box. EA X 20 = -$ F-6 Update Smoke Detector, wiring included as necessary EA X 100 = -$

F-7 F/I Emergency Exit Sign, not including wiring EA X 20 = -$

F-8 F/I Emergency Light, not including wiring EA X 20 = -$

M-1 Demo Metal Pipe up to 2" diameter – includes removal of hangers and capping of pipe. Bare non-insulated pipe only. LF X 650 = -$

M-2 Remove and Reinstall Ceiling Diffusers – includes disconnection, removal, storage, and reinstallation of diffusers. Up to 15’ height in its same location. EA X 100 = -$

M-3 Relocate Ceiling Diffusers – same scope as item M-2 but reinstallation at a different location, and includes up to 5’ of flex duct. EA X 50 = -$

M-4 F/I 24"x24" Ceiling Diffusers – includes up to 5’ flex duct. Balancing not included. EA X 100 = -$ M-5 Relocate thermostat, furnish up to 25' of wire, no conduit required. EA X 10 = -$ M-6 TAB, Ultra sonic water flow measurement , up to 3 loca ions. EA X 10 = -$

M-7 TAB, Flow reading of hydronic systems with existing PT port, up to 5 coils and/or pumps. Includes resoration of disturbed insulation. EA X 10 = -$

M-8 TAB, Air flow of up to 10 diffusers. EA X 10 = -$

TOTAL ESTIMATED PRE-PRICED ITEMS FOR CONTRACT YEAR 1 -$

TOTAL A-E & Construction IDIQ CONTRACT YEAR 1 -$

Offerors shall propose loaded (incl. burden, G&A, overhead and profit) hourly rates for the following skill disiplines.

Contract Year 1 Proposed Annual IDIQ Loaded Estimated Est. Annual

Discipline Hourly Rate ($/hr) Hours A-E Price Senior Architect X 1,000 = -$ Architect X 700 = -$ Senior Civil Engineer X 500 = -$ Civil Engineer X 500 = -$ Senior Mechanical Engineer X 2,000 = -$ Mechanical Engineer X 1,000 = -$ Senior Electrical Engineer X 1,500 = -$ Electrical Engineer X 1,000 = -$ Senior Structural Engineer X 500 = -$ Structural Engineer X 500 = -$ Fire Protection Engineer X 1,000 = -$ Environmental Engineer X 500 = -$ Estimator X 1,000 = -$ Specification Writer X 300 = -$ CADD/BIM Technician X 500 = -$ Project Manager X 1,000 = -$ Interior Designer X 500 = -$ Scheduler X 1,000 = -$ Planner X 1,000 = -$ Sr. Systems Analyst X 300 = -$ Sr. Programmer Analyst X 300 = -$ Certified Surveyor X 200 = -$ GIS Technician X 200 = -$

TOTAL ESTIMATED FOR CONTRACT YEAR -$

Specialty A-E Subcontractor Mark-up (%) % X $200,000 = $

TOTAL Year 2 A-E Services (sum of hourly costs and specialty fee) #VALUE!

(b) CONSTRUCTION SERVICES

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Minimum Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 1,000,000$ = -$ >$100K X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Full Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 200,000$ = -$ $100K to $1M X 800,000$ = -$ >$1M X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

EXHIBIT 15A ROME IDIQ A-E & Construction Prices - Year 2

Offerors shall propose a Specialty Subcontractor Fee percentage below to be applied to specialty subcontractor quotes for A-E Services as described in the Statement of Work.

Offerors shall propose Construction Management Coefficients below to be applied to the actual construction cost as described in the Statement of Work.

Design-Bid-Build Construction Only Construction/ Annual Annual

Design-Build Estimated Construction Project Value Coefficient Construction Price

$0 to $100K X 700,000$ = -$ $100K to $1M X 7,000,000$ = -$ >$1M X 4,000,000$ = -$

TOTAL WITH CONSTRUCTION-ONLY COEFFICIENT 11,700,000$ -$

Annual TOTAL Construction (incl. D-B Minimum, D-B Full, and D-B-B Construction only) $ -

Pre-Priced Construction

Estimated Annual LABEL Unit Price ($) Unit Quantity Price

A-1 Remove Vinyl Composition Tile – remove tile and adhesive. SF X 10,000 = -$ A-2 Furnish & Install (F/I) VCT – includes subfloor preparation when required. SF X 10,000 = -$

A-3 Flash Patch Floor – entails application of leveling grout and final cleaning for new VCT or carpet.

Assumes project size of 400 sf or larger, otherwise productivity adjustment. SF X 2,000 = -$

A-4 Remove Carpet – remove carpet and adhesive. SF X 30,000 = -$

A-5 F/I Carpet Floor Tile. SF X 30,000 = -$

A-6 Remove and Reinstall Raised Access Floor Panels – entails one-time removal and replacement only.

Light furniture relocation included. Heavy equipment and furniture to be relocated by others. SF X 2,000 = -$

A-7 Remove Cove Base. LF X 1,000 = -$

A-8 F/I Cove Base. LF X 1,000 = -$

A-9 Demo CMU Wall – not cut-out demo. No toothing. Assumes full wall sections at least 10’ long. Includes dust protection. CY X 50 = -$

A-10 Demo Stud Wall – includes saw cutting if necessary. SF X 5,000 = -$

A-11 Stud/Drywall Partition – includes constructing stud wall, drywall, taping, spackling, and finishing;

excludes insulation. SF X 5,000 = -$

A-12 Skim Coat Patch Drywall – assumes entire wall needs refinishing. Includes applying Durabond and Lafarge compound skim coats. SF X 3,000 = -$

A-13 Prepare and Paint Walls – includes repairing any minor imperfections, sanding, and painting with 1 coat primer and 2 coats latex. SF X 25,000 = -$

A-14 F/I 1/4" drywall over existing wall - includes adhesive or mechanical fasteners and preparation for painting. SF X 25,000 = -$

A-15 F/I Room Signs – includes Hermes #723-087 frame with header and 3-lines. Only room number tag is included. EA X 50 = -$

A-16 Wall Penetrations up to 4" in diameter – used for conduit or pipe wall penetrations through masonry or partition walls. Core drilling through concrete not included. Fire caulk not included. EA X 20 = -$

A-17 Fire Caulk Penetration up to 4" in diameter – fire caulk only. Does not include special fire penetration assemblies. EA X 20 = -$

A-18 Demo Door and Frame – as part of wall demo or part of door replacement. EA X 50 = -$ A-19 F/I Wood Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 30 = -$

A-20 F/I Wood Door & Frame (6’x7’) – no cut-out or jamb work included. No finishing included. Not fire rated.

Not an egress door. EA X 10 = -$

A-21 F/I Red Oak Door & Frame (3’x7’) – installed door with frame and hardware. EA X 10 = -$ A-22 F/I Metal Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 20 = -$ A-23 Paint Door and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 50 = -$

A-24 Paint Door and Half-Leaf and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 5 = -$

A-25 Remove and Replace Ceiling Tile – includes 2’x2’ tile and 2’x4’ tile. SF X 30,000 = -$ A-26 Demo Suspended Ceiling – removal of ceiling grid, suspension system and tiles. SF X 10,000 = -$

A-27 F/I Ceiling Grid and Tile – includes support attachments, suspension system, grid and tiles (2’x2’ or 2’x4’). SF X 10,000 = -$

A-28 F/I Handicapped Door Opener - per Construction Specifications requirements - includes push buttons, door opening device, and provision of electrical power. EA X 5 = -$

E-1 F/I Light Switch – including wiring, conduit (including fittings, connectors, hangers, offsets, bends, etc.), box, wall plate, and wall plate identification label. Includes up to 50 LF of wiring and conduit. EA X 50 = -$

E-2

F/I Receptacle – includes wiring, conduit (including fittings, connectors, hangers, offsets, bends, etc.), box, wall plate, and wall plate identification label. Includes up to 50 LF of wiring and conduit (to panelboard). Update panelboard schedule. EA X 50 = -$

E-3 F/I Wire/Conduit for Lighting and Receptacle Circuits (25 LF) – includes wire and conduit (including fittings, hangers, offsets, etc). Wire and conduit size - 3#12, ¾" EMT. EA X 100 = -$

E-4 Remove Existing Lights – includes the removal of interior 2’ x 4’ fluorescent fixtures, wiring, and conduit back to nearest JB (10 LF). EA X 100 = -$

E-5

F/I New lights. Provide 2’ x 4’, 7200 lumens LED recessed fixture (Lithonia catalog # 2GTL4 72L EZ1 LP40 or equal). fixture supports, wire and conduit (including fittings, hangers, offsets, bends, etc.).

Includes up to 6 LF of MC cable for connection to nearest junction box. Update panelboard schedule.

Includes work up to 15 feet in height. EA X 50 = -$

E-6

F/I New lights. Provide 2’ x 4’, 5000 lumens LED recessed fixture (Lithonia catalog # 2AVL4 50L MDR EZ1 LP40 or equal). Includes up to 6 LF of MC cable for connection to nearest junction box. Update panelboard schedule. Includes work up to 15 feet in height. EA X 50 = -$

E-7

F/I Ceiling Mounted Motion Sensors (Lighting Control) – includes motion sensor (WattStopper W500A or equal), power pack, and all required wire and conduit. Includes up to 10 LF of power wiring/conduit and up to 50 LF of control wiring (from power pack to sensor). EA X 20 = -$

E-8 F/I 700 Wiremold – includes wiremold (10 LF), box, wall plate, connector, and fittings. EA X 30 = -$ E-9 F/I New Receptacle or Switch using Wiremold – includes wire, and wall plate identification label. EA X 20 = -$

E-10 F/I Power/LAN Floor Box – entails a complete installation including core drill floor penetration, conduit, drilling, anchors, water control, etc. EA X 20 = -$

E-11 Remove Power/LAN Floor Box – entails a complete removal of box, conduit, wire and patching the floor. EA X 20 = -$

E-12 Remove Receptacle – entails complete removal back to nearest junction box. Not to exceed 10’. Trace circuit. EA X 50 = -$

E-13 Remove Wiremold (700) (per 10’) – includes demo of wire and receptacles. EA X 50 = -$ E-14 Demo Wire/Conduit (per 10’) – includes hangers and straps. EA X 300 = -$

E-15 Remove Circuit Breakers 20-90A 1P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 100 = -$

E-16 Remove Circuit Breakers 20-100A 2P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-17 Remove Circuit Breakers 20-100A 3P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-18 Remove Underfloor Quads (30’ liquidtight) – includes removal of conduit and wire from power source and relabeling. EA X 20 = -$

E-19 Remove/Blank-off Telephone Floor Stacks – includes removal of conduit and wire to nearest J-box.

Blank off with floor inserts. EA X 20 = -$

E-20

F/I Underfloor Quads (30’ liquidtight) – includes circuit breaker, ¾" sealtite, #12 wire from power source to underfloor location. Includes KO’s, connectors, terms, boxes, covers, receptacles. Does not include lock out/tag out or R&R panel cover. EA X 25 = -$

E-21 Demo Wall Switch – includes removal of conduit/wire back to J-box and wall patching. EA X 100 = -$ F-1 Demo Sprinkler Head – includes removal of head, pipe hangers and replace ceiling tile. EA X 100 = -$

F-2 Update Sprinkler Head – involves replacement with a new head at the same location. Includes pipe modifications, escutcheons, ceiling tile. EA X 100 = -$

F-3

Relocate Sprinkler Head – includes piping, anchoring, hangers, escutcheons, ceiling tile. Maximum distance is 5' -0" in one direction (left, right, straight, or down) from the original location of the sprinkler head elbow down turn. EA X 100 = -$

F-4 Demo Smoke Detector – includes removal of conduit/wire back to J-box. EA X 40 = -$ F-5 Demo Motion Sensor – includes removal of conduit/wire back to j-box. EA X 20 = -$ F-6 Update Smoke Detector, wiring included as necessary EA X 100 = -$

F-7 F/I Emergency Exit Sign, not including wiring EA X 20 = -$

F-8 F/I Emergency Light, not including wiring EA X 20 = -$

M-1 Demo Metal Pipe up to 2" diameter – includes removal of hangers and capping of pipe. Bare non-insulated pipe only. LF X 650 = -$

M-2 Remove and Reinstall Ceiling Diffusers – includes disconnection, removal, storage, and reinstallation of diffusers. Up to 15’ height in its same location. EA X 100 = -$

M-3 Relocate Ceiling Diffusers – same scope as item M-2 but reinstallation at a different location, and includes up to 5’ of flex duct. EA X 50 = -$

M-4 F/I 24"x24" Ceiling Diffusers – includes up to 5’ flex duct. Balancing not included. EA X 100 = -$ M-5 Relocate thermostat, furnish up to 25' of wire, no conduit required. EA X 10 = -$ M-6 TAB, Ultra sonic water flow measurement , up to 3 locations. EA X 10 = -$

M-7 TAB, Flow reading of hydronic systems with existing PT port, up to 5 coils and/or pumps. Includes resoration of disturbed insulation. EA X 10 = -$

M-8 TAB, Air flow of up to 10 diffusers. EA X 10 = -$

TOTAL ESTIMATED PRE-PRICED ITEMS FOR CONTRACT YEAR 2 -$

TOTAL A-E & Construction IDIQ CONTRACT YEAR 2 -$

Offerors shall propose loaded (incl. burden, G&A, overhead and profit) hourly rates for the following skill disiplines.

Contract Year 1 Proposed Annual IDIQ Loaded Estimated Est. Annual

Discipline Hourly Rate ($/hr) Hours A-E Price Senior Architect X 1,000 = -$ Architect X 700 = -$ Senior Civil Engineer X 500 = -$ Civil Engineer X 500 = -$ Senior Mechanical Engineer X 2,000 = -$ Mechanical Engineer X 1,000 = -$ Senior Electrical Engineer X 1,500 = -$ Electrical Engineer X 1,000 = -$ Senior Structural Engineer X 500 = -$ Structural Engineer X 500 = -$ Fire Protection Engineer X 1,000 = -$ Environmental Engineer X 500 = -$ Estimator X 1,000 = -$ Specification Writer X 300 = -$ CADD/BIM Technician X 500 = -$ Project Manager X 1,000 = -$ Interior Designer X 500 = -$ Scheduler X 1,000 = -$ Planner X 1,000 = -$ Sr. Systems Analyst X 300 = -$ Sr. Programmer Analyst X 300 = -$ Certified Surveyor X 200 = -$ GIS Technician X 200 = -$

TOTAL ESTIMATED FOR CONTRACT YEAR 1 -$

Specialty A-E Subcontractor Mark-up (%) % X $200,000 = $

TOTAL Year 3 A-E Services (sum of hourly costs and specialty fee) #VALUE!

(b) CONSTRUCTION SERVICES

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Minimum Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 1,000,000$ = -$ >$100K X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Full Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 200,000$ = -$ $100K to $1M X 800,000$ = -$ >$1M X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

EXHIBIT 15B ROME IDIQ A-E & Construction Prices - Year 3

Offerors shall propose a Specialty Subcontractor Fee percentage below to be applied to specialty subcontractor quotes for A-E Services as described in the Statement of Work.

Offerors shall propose Construction Management Coefficients below to be applied to the actual construction cost as described in the Statement of Work.

Design-Bid-Build Construction Only Construction/ Annual Annual

Design-Build Estimated Construction Project Value Coefficient Construction Price

$0 to $100K X 700,000$ = -$ $100K to $1M X 7,000,000$ = -$ >$1M X 4,000,000$ = -$

TOTAL WITH CONSTRUCTION-ONLY COEFFICIENT 11,700,000$ -$

Annual TOTAL Construction (incl. D-B Minimum, D-B Full, and D-B-B Construction only) $ -

Pre-Priced Construction

Estimated Annual LABEL Unit Price ($/hr) Unit Quantity Price

A-1 Remove Vinyl Composition Tile – remove tile and adhesive. SF X 10,000 = -$ A-2 Furnish & Install (F/I) VCT – includes subfloor preparation when required. SF X 10,000 = -$

A-3 Flash Patch Floor – entails application of leveling grout and final cleaning for new VCT or carpet.

Assumes project size of 400 sf or larger, otherwise productivity adjustment. SF X 2,000 = -$

A-4 Remove Carpet – remove carpet and adhesive. SF X 30,000 = -$

A-5 F/I Carpet Floor Tile. SF X 30,000 = -$

A-6 Remove and Reinstall Raised Access Floor Panels – entails one-time removal and replacement only. Light furniture relocation included. Heavy equipment and furniture to be relocated by others. SF X 2,000 = -$

A-7 Remove Cove Base. LF X 1,000 = -$

A-8 F/I Cove Base. LF X 1,000 = -$

A-9 Demo CMU Wall – not cut-out demo. No toothing. Assumes full wall sections at least 10’ long. Includes dust protection. CY X 50 = -$

A-10 Demo Stud Wall – includes saw cutting if necessary. SF X 5,000 = -$

A-11 Stud/Drywall Partition – includes constructing stud wall, drywall, taping, spackling, and finishing;

excludes insulation. SF X 5,000 = -$

A-12 Skim Coat Patch Drywall – assumes entire wall needs refinishing. Includes applying Durabond and Lafarge compound skim coats. SF X 3,000 = -$

A-13 Prepare and Paint Walls – includes repairing any minor imperfections, sanding, and painting with 1 coat primer and 2 coats latex. SF X 25,000 = -$

A-14 F/I 1/4" drywall over existing wall - includes adhesive or mechanical fasteners and preparation for painting. SF X 25,000 = -$

A-15 F/I Room Signs – includes Hermes #723-087 frame with header and 3-lines. Only room number tag is included. EA X 50 = -$

A-16 Wall Penetrations up to 4" in diameter – used for conduit or pipe wall penetrations through masonry or partition walls. Core drilling through concrete not included. Fire caulk not included. EA X 20 = -$

A-17 Fire Caulk Penetration up to 4" in diameter – fire caulk only. Does not include special fire penetration assemblies. EA X 20 = -$

A-18 Demo Door and Frame – as part of wall demo or part of door replacement. EA X 50 = -$ A-19 F/I Wood Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 30 = -$

A-20 F/I Wood Door & Frame (6’x7’) – no cut-out or jamb work included. No finishing included. Not fire rated. Not an egress door. EA X 10 = -$

A-21 F/I Red Oak Door & Frame (3’x7’) – installed door with frame and hardware. EA X 10 = -$ A-22 F/I Metal Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 20 = -$ A-23 Paint Door and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 50 = -$

A-24 Paint Door and Half-Leaf and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 5 = -$

A-25 Remove and Replace Ceiling Tile – includes 2’x2’ tile and 2’x4’ tile. SF X 30,000 = -$ A-26 Demo Suspended Ceiling – removal of ceiling grid, suspension system and tiles. SF X 10,000 = -$

A-27 F/I Ceiling Grid and Tile – includes support attachments, suspension system, grid and tiles (2’x2’ or 2’x4’). SF X 10,000 = -$

A-28 F/I Handicapped Door Opener - per Construction Specifications requirements - includes push buttons, door opening device, and provision of electrical power. EA X 5 = -$

E-1 F/I Light Switch – including wiring, conduit (including fittings, connectors, hangers, offsets, bends, etc.), box, wall plate, and wall plate identification label. Includes up to 50 LF of wiring and conduit. EA X 50 = -$

E-2

F/I Receptacle – includes wiring, conduit (including fittings, connectors, hangers, offsets, bends, etc.), box, wall plate, and wall plate identification label. Includes up to 50 LF of wiring and conduit (to panelboard). Update panelboard schedule. EA X 50 = -$

E-3 F/I Wire/Conduit for Lighting and Receptacle Circuits (25 LF) – includes wire and conduit (including fittings, hangers, offsets, etc). Wire and conduit size - 3#12, ¾" EMT. EA X 100 = -$

E-4 Remove Existing Lights – includes the removal of interior 2’ x 4’ fluorescent fixtures, wiring, and conduit back to nearest JB (10 LF). EA X 100 = -$

E-5

F/I New lights. Provide 2’ x 4’, 7200 lumens LED recessed fixture (Lithonia catalog # 2GTL4 72L EZ1 LP40 or equal). fixture supports, wire and conduit (including fittings, hangers, offsets, bends, etc.).

Includes up to 6 LF of MC cable for connection to nearest junction box. Update panelboard schedule.

Includes work up to 15 feet in height. EA X 50 = -$

E-6

F/I New lights. Provide 2’ x 4’, 5000 lumens LED recessed fixture (Lithonia catalog # 2AVL4 50L MDR EZ1 LP40 or equal). Includes up to 6 LF of MC cable for connection to nearest junction box.

Update panelboard schedule. Includes work up to 15 feet in height. EA X 50 = -$

W500A or equal), power pack, and all required wire and conduit. Includes up to 10 LF of power wiring/conduit and up to 50 LF of control wiring (from power pack to sensor). EA X 20 = -$

E-8 F/I 700 Wiremold – includes wiremold (10 LF), box, wall plate, connector, and fittings. EA X 30 = -$ E-9 F/I New Receptacle or Switch using Wiremold – includes wire, and wall plate identification label. EA X 20 = -$

E-10 F/I Power/LAN Floor Box – entails a complete installation including core drill floor penetration, conduit, drilling, anchors, water control, etc. EA X 20 = -$

E-11 Remove Power/LAN Floor Box – entails a complete removal of box, conduit, wire and patching the floor. EA X 20 = -$

E-12 Remove Receptacle – entails complete removal back to nearest junction box. Not to exceed 10’. Trace circuit. EA X 50 = -$

E-13 Remove Wiremold (700) (per 10’) – includes demo of wire and receptacles. EA X 50 = -$ E-14 Demo Wire/Conduit (per 10’) – includes hangers and straps. EA X 300 = -$

E-15 Remove Circuit Breakers 20-90A 1P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 100 = -$

E-16 Remove Circuit Breakers 20-100A 2P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-17 Remove Circuit Breakers 20-100A 3P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-18 Remove Underfloor Quads (30’ liquidtight) – includes removal of conduit and wire from power source and relabeling. EA X 20 = -$

E-19 Remove/Blank-off Telephone Floor Stacks – includes removal of conduit and wire to nearest J-box.

Blank off with floor inserts. EA X 20 = -$

E-20

F/I Underfloor Quads (30’ liquidtight) – includes circuit breaker, ¾" sealtite, #12 wire from power source to underfloor location. Includes KO’s, connectors, terms, boxes, covers, receptacles. Does not include lock out/tag out or R&R panel cover. EA X 25 = -$

E-21 Demo Wall Switch – includes removal of conduit/wire back to J-box and wall patching. EA X 100 = -$ F-1 Demo Sprinkler Head – includes removal of head, pipe hangers and replace ceiling tile. EA X 100 = -$

F-2 Update Sprinkler Head – involves replacement with a new head at the same location. Includes pipe modifications, escutcheons, ceiling tile. EA X 100 = -$

F-3

Relocate Sprinkler Head – includes piping, anchoring, hangers, escutcheons, ceiling tile. Maximum distance is 5' -0" in one direction (left, right, straight, or down) from the original location of the sprinkler head elbow down turn. EA X 100 = -$

F-4 Demo Smoke Detector – includes removal of conduit/wire back to J-box. EA X 40 = -$ F-5 Demo Motion Sensor – includes removal of conduit/wire back to j-box. EA X 20 = -$ F-6 Update Smoke Detector, wiring included as necessary EA X 100 = -$

F-7 F/I Emergency Exit Sign, not including wiring EA X 20 = -$

F-8 F/I Emergency Light, not including wiring EA X 20 = -$

M-1 Demo Metal Pipe up to 2" diameter – includes removal of hangers and capping of pipe. Bare non-insulated pipe only. LF X 650 = -$

M-2 Remove and Reinstall Ceiling Diffusers – includes disconnection, removal, storage, and reinstallation of diffusers. Up to 15’ height in its same location. EA X 100 = -$

M-3 Relocate Ceiling Diffusers – same scope as item M-2 but reinstallation at a different location, and includes up to 5’ of flex duct. EA X 50 = -$

M-4 F/I 24"x24" Ceiling Diffusers – includes up to 5’ flex duct. Balancing not included. EA X 100 = -$ M-5 Relocate thermostat, furnish up to 25' of wire, no conduit required. EA X 10 = -$ M-6 TAB, Ultra sonic water flow measurement , up to 3 locations. EA X 10 = -$

M-7 TAB, Flow reading of hydronic systems with existing PT port, up to 5 coils and/or pumps. Includes resoration of disturbed insulation. EA X 10 = -$

M-8 TAB, Air flow of up to 10 diffusers. EA X 10 = -$

TOTAL ESTIMATED PRE-PRICED ITEMS FOR CONTRACT YEAR 3 -$

TOTAL A-E & Construction IDIQ CONTRACT YEAR 3 -$

Offerors shall propose loaded (incl. burden, G&A, overhead and profit) hourly rates for the following skill disiplines.

Contract Year 1 Proposed Annual IDIQ Loaded Estimated Est. Annual

Discipline Hourly Rate ($/hr) Hours A-E Price Senior Architect X 1,000 = -$ Architect X 700 = -$ Senior Civil Engineer X 500 = -$ Civil Engineer X 500 = -$ Senior Mechanical Engineer X 2,000 = -$ Mechanical Engineer X 1,000 = -$ Senior Electrical Engineer X 1,500 = -$ Electrical Engineer X 1,000 = -$ Senior Structural Engineer X 500 = -$ Structural Engineer X 500 = -$ Fire Protection Engineer X 1,000 = -$ Environmental Engineer X 500 = -$ Estimator X 1,000 = -$ Specification Writer X 300 = -$ CADD/BIM Technician X 500 = -$ Project Manager X 1,000 = -$ Interior Designer X 500 = -$ Scheduler X 1,000 = -$ Planner X 1,000 = -$ Sr. Systems Analyst X 300 = -$ Sr. Programmer Analyst X 300 = -$ Certified Surveyor X 200 = -$ GIS Technician X 200 = -$

TOTAL ESTIMATED FOR CONTRACT YEAR -$

Specialty A-E Subcontractor Mark-up (%) % X $200,000 = $

TOTAL Year 4 A-E Services (sum of hourly costs and specialty fee) #VALUE!

(b) CONSTRUCTION SERVICES

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Minimum Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 1,000,000$ = -$ >$100K X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Full Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 200,000$ = -$ $100K to $1M X 800,000$ = -$ >$1M X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

IDIQ

Construction/Design-Build Coefficient Estimated

EXHIBIT 15C ROME IDIQ A-E & Construction Prices - Year 4

Offerors shall propose a Specialty Subcontractor Fee percentage below to be applied to specialty subcontractor quotes for A-E Services as described in the Statement of Work.

Offerors shall propose Construction Management Coefficients below to be applied to the actual construction cost as described in the Statement of Work.

Design-Bid-Build Construction Only Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 700,000$ = -$ $100K to $1M X 7,000,000$ = -$ >$1M X 4,000,000$ = -$

TOTAL WITH CONSTRUCTION-ONLY COEFFICIENT 11,700,000$ -$

Annual TOTAL Construction (incl. D-B Minimum, D-B Full, and D-B-B Construction only) $ -

Pre-Priced Construction

Estimated Annual LABEL Unit Price ($) Unit Quantity Price

A-1 Remove Vinyl Composition Tile – remove tile and adhesive. SF X 10,000 = -$ A-2 Furnish & Install (F/I) VCT – includes subfloor preparation when required. SF X 10,000 = -$

A-3 Flash Patch Floor – entails application of leveling grout and final cleaning for new VCT or carpet.

Assumes project size of 400 sf or larger, otherwise productivity adjustment. SF X 2,000 = -$

A-4 Remove Carpet – remove carpet and adhesive. SF X 30,000 = -$

A-5 F/I Carpet Floor Tile. SF X 30,000 = -$

A-6 Remove and Reinstall Raised Access Floor Panels – entails one-time removal and replacement only.

Light furniture relocation included. Heavy equipment and furniture to be relocated by others. SF X 2,000 = -$

A-7 Remove Cove Base. LF X 1,000 = -$

A-8 F/I Cove Base. LF X 1,000 = -$

A-9 Demo CMU Wall – not cut-out demo. No toothing. Assumes full wall sections at least 10’ long. Includes dust protection. CY X 50 = -$

A-10 Demo Stud Wall – includes saw cutting if necessary. SF X 5,000 = -$

A-11 Stud/Drywall Partition – includes constructing stud wall, drywall, taping, spackling, and finishing;

excludes insulation. SF X 5,000 = -$

A-12 Skim Coat Patch Drywall – assumes entire wall needs refinishing. Includes applying Durabond and Lafarge compound skim coats. SF X 3,000 = -$

A-13 Prepare and Paint Walls – includes repairing any minor imperfections, sanding, and painting with 1 coat primer and 2 coats latex. SF X 25,000 = -$

A-14 F/I 1/4" drywall over existing wall - includes adhesive or mechanical fasteners and preparation for painting. SF X 25,000 = -$

A-15 F/I Room Signs – includes Hermes #723-087 frame with header and 3-lines. Only room number tag is included. EA X 50 = -$

A-16 Wall Penetrations up to 4" in diameter – used for conduit or pipe wall penetrations through masonry or partition walls. Core drilling through concrete not included. Fire caulk not included. EA X 20 = -$

A-17 Fire Caulk Penetration up to 4" in diameter – fire caulk only. Does not include special fire penetration assemblies. EA X 20 = -$

A-18 Demo Door and Frame – as part of wall demo or part of door replacement. EA X 50 = -$ A-19 F/I Wood Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 30 = -$

A-20 F/I Wood Door & Frame (6’x7’) – no cut-out or jamb work included. No finishing included. Not fire rated.

Not an egress door. EA X 10 = -$

A-21 F/I Red Oak Door & Frame (3’x7’) – installed door with frame and hardware. EA X 10 = -$ A-22 F/I Metal Door and Frame (3’x7’) – includes caulking, door stop, hinges, and lockset. EA X 20 = -$ A-23 Paint Door and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 50 = -$

A-24 Paint Door and Half-Leaf and Frame – includes sanding and painting with 1 coat primer and 2 coats latex. EA X 5 = -$

A-25 Remove and Replace Ceiling Tile – includes 2’x2’ tile and 2’x4’ tile. SF X 30,000 = -$ A-26 Demo Suspended Ceiling – removal of ceiling grid, suspension system and tiles. SF X 10,000 = -$

A-27 F/I Ceiling Grid and Tile – includes support attachments, suspension system, grid and tiles (2’x2’ or 2’x4’). SF X 10,000 = -$

A-28 F/I Handicapped Door Opener - per Construction Specifications requirements - includes push buttons, door opening device, and provision of electrical power. EA X 5 = -$

E-1 F/I Light Switch – including wiring, conduit (including fittings, connectors, hangers, offsets, bends, etc.), box, wall plate, and wall plate identification label. Includes up to 50 LF of wiring and conduit. EA X 50 = -$

E-2

F/I Receptacle – includes wiring, conduit (including fittings, connectors, hangers, offsets, bends, etc.), box, wall plate, and wall plate identification label. Includes up to 50 LF of wiring and conduit (to panelboard). Update panelboard schedule. EA X 50 = -$

E-3 F/I Wire/Conduit for Lighting and Receptacle Circuits (25 LF) – includes wire and conduit (including fittings, hangers, offsets, etc). Wire and conduit size - 3#12, ¾" EMT. EA X 100 = -$

E-4 Remove Existing Lights – includes the removal of interior 2’ x 4’ fluorescent fixtures, wiring, and conduit back to nearest JB (10 LF). EA X 100 = -$

E-5

F/I New lights. Provide 2’ x 4’, 7200 lumens LED recessed fixture (Lithonia catalog # 2GTL4 72L EZ1 LP40 or equal). fixture supports, wire and conduit (including fittings, hangers, offsets, bends, etc.).

Includes up to 6 LF of MC cable for connection to nearest junction box. Update panelboard schedule.

Includes work up to 15 feet in height. EA X 50 = -$

E-6

F/I New lights. Provide 2’ x 4’, 5000 lumens LED recessed fixture (Lithonia catalog # 2AVL4 50L MDR EZ1 LP40 or equal). Includes up to 6 LF of MC cable for connection to nearest junction box. Update panelboard schedule. Includes work up to 15 feet in height. EA X 50 = -$

E-7

F/I Ceiling Mounted Motion Sensors (Lighting Control) – includes motion sensor (WattStopper W500A or equal), power pack, and all required wire and conduit. Includes up to 10 LF of power wiring/conduit and up to 50 LF of control wiring (from power pack to sensor). EA X 20 = -$

E-8 F/I 700 Wiremold – includes wiremold (10 LF), box, wall plate, connector, and fittings. EA X 30 = -$

E-9 F/I New Receptacle or Switch using Wiremold – includes wire, and wall plate identification label. EA X 20 = -$

E-10 F/I Power/LAN Floor Box – entails a complete installation including core drill floor penetration, conduit, drilling, anchors, water control, etc. EA X 20 = -$

E-11 Remove Power/LAN Floor Box – entails a complete removal of box, conduit, wire and patching the floor. EA X 20 = -$

E-12 Remove Receptacle – entails complete removal back to nearest junction box. Not to exceed 10’. Trace circuit. EA X 50 = -$

E-13 Remove Wiremold (700) (per 10’) – includes demo of wire and receptacles. EA X 50 = -$ E-14 Demo Wire/Conduit (per 10’) – includes hangers and straps. EA X 300 = -$

E-15 Remove Circuit Breakers 20-90A 1P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 100 = -$

E-16 Remove Circuit Breakers 20-100A 2P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-17 Remove Circuit Breakers 20-100A 3P – includes blank cover plate and re-label. Does not include lock out/tag out or R&R panel cover. EA X 50 = -$

E-18 Remove Underfloor Quads (30’ liquidtight) – includes removal of conduit and wire from power source and relabeling. EA X 20 = -$

E-19 Remove/Blank-off Telephone Floor Stacks – includes removal of conduit and wire to nearest J-box.

Blank off with floor inserts. EA X 20 = -$

E-20

F/I Underfloor Quads (30’ liquidtight) – includes circuit breaker, ¾" sealtite, #12 wire from power source to underfloor location. Includes KO’s, connectors, terms, boxes, covers, receptacles. Does not include lock out/tag out or R&R panel cover. EA X 25 = -$

E-21 Demo Wall Switch – includes removal of conduit/wire back to J-box and wall patching. EA X 100 = -$ F-1 Demo Sprinkler Head – includes removal of head, pipe hangers and replace ceiling tile. EA X 100 = -$

F-2 Update Sprinkler Head – involves replacement with a new head at the same location. Includes pipe modifications, escutcheons, ceiling tile. EA X 100 = -$

F-3

Relocate Sprinkler Head – includes piping, anchoring, hangers, escutcheons, ceiling tile. Maximum distance is 5' -0" in one direction (left, right, straight, or down) from the original location of the sprinkler head elbow down turn. EA X 100 = -$

F-4 Demo Smoke Detector – includes removal of conduit/wire back to J-box. EA X 40 = -$ F-5 Demo Motion Sensor – includes removal of conduit/wire back to j-box. EA X 20 = -$ F-6 Update Smoke Detector, wiring included as necessary EA X 100 = -$

F-7 F/I Emergency Exit Sign, not including wiring EA X 20 = -$

F-8 F/I Emergency Light, not including wiring EA X 20 = -$

M-1 Demo Metal Pipe up to 2" diameter – includes removal of hangers and capping of pipe. Bare non-insulated pipe only. LF X 650 = -$

M-2 Remove and Reinstall Ceiling Diffusers – includes disconnection, removal, storage, and reinstallation of diffusers. Up to 15’ height in its same location. EA X 100 = -$

M-3 Relocate Ceiling Diffusers – same scope as item M-2 but reinstallation at a different location, and includes up to 5’ of flex duct. EA X 50 = -$

M-4 F/I 24"x24" Ceiling Diffusers – includes up to 5’ flex duct. Balancing not included. EA X 100 = -$ M-5 Relocate thermostat, furnish up to 25' of wire, no conduit required. EA X 10 = -$ M-6 TAB, Ultra sonic water flow measurement , up to 3 locations. EA X 10 = -$

M-7 TAB, Flow reading of hydronic systems with existing PT port, up to 5 coils and/or pumps. Includes resoration of disturbed insulation. EA X 10 = -$

M-8 TAB, Air flow of up to 10 diffusers. EA X 10 = -$

TOTAL ESTIMATED PRE-PRICED ITEMS FOR CONTRACT YEAR 4 -$

TOTAL A-E & Construction IDIQ CONTRACT YEAR 4 -$

Offerors shall propose loaded (incl. burden, G&A, overhead and profit) hourly rates for the following skill disiplines.

Contract Year 1 Proposed Annual IDIQ Loaded Estimated Est. Annual

Discipline Hourly Rate ($/hr) Hours A-E Price Senior Architect X 1,000 = -$ Architect X 700 = -$ Senior Civil Engineer X 500 = -$ Civil Engineer X 500 = -$ Senior Mechanical Engineer X 2,000 = -$ Mechanical Engineer X 1,000 = -$ Senior Electrical Engineer X 1,500 = -$ Electrical Engineer X 1,000 = -$ Senior Structural Engineer X 500 = -$ Structural Engineer X 500 = -$ Fire Protection Engineer X 1,000 = -$ Environmental Engineer X 500 = -$ Estimator X 1,000 = -$ Specification Writer X 300 = -$ CADD/BIM Technician X 500 = -$ Project Manager X 1,000 = -$ Interior Designer X 500 = -$ Scheduler X 1,000 = -$ Planner X 1,000 = -$ Sr. Systems Analyst X 300 = -$ Sr. Programmer Analyst X 300 = -$ Certified Surveyor X 200 = -$ GIS Technician X 200 = -$

TOTAL ESTIMATED FOR CONTRACT YEAR -$

Specialty A-E Subcontractor Mark-up (%) % X $200,000 = $

TOTAL Year 5 A-E Services (sum of hourly costs and specialty fee) #VALUE!

(b) CONSTRUCTION SERVICES

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Minimum Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 1,000,000$ = -$ >$100K X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

IDIQ

Construction/Design-Build Coefficient Estimated

Design-Build Full Design Construction/ Annual Annual Design-Build Estimated Construction

Project Value Coefficient Construction Price

$0 to $100K X 200,000$ = -$ $100K to $1M X 800,000$ = -$ >$1M X 1,000,000$ = -$

TOTAL WITH CONSTRUCTION DESIGN-BUILD COEFFICIENT 2,000,000$ -$

EXHIBIT 15D ROME IDIQ A-E & Construction Prices - Year 5

Offerors shall propose a Specialty Subcontractor Fee percentage below to be applied to specialty subcontractor quotes for A-E Services as described in the Statement of Work.

Offerors shall propose Construction Management Coefficients below to be applied to the actual construction cost as described in the Statement of Work.

Design-Bid-Build Construction Only Construction/ Annual Annual

Design-Build Estimated Construction Project Value Coefficient Construction Price

$0 to $100K X 700,000$ = -$ $100K to $1M X 7,000,000$ = -$ >$1M X 4,000,000$ = -$

TOTAL WITH CONSTRUCTION-ONLY COEFFICIENT 11,700,000$ -$

Annual TOTAL Construction (incl. D-B Minimum, D-B Full, and D-B-B Construction only) $ -

Pre-Priced Construction

Estimated Annual LABEL Unit Price ($) Unit Quantity Price

A-1 Remove Vinyl Composition Tile – remove tile and adhesive. SF X 10,000 = -$ A-2 Furnish & Install (F/I) VCT – includes subfloor preparation when required. SF X 10,000 = -$

A-3 Flash Patch Floor – entails application of leveling grout and final cleaning for new VCT or carpet.

Assumes project size of 400 sf or larger, otherwise productivity adjustment. SF X 2,000 = -$

A-4 Remove Carpet – remove carpet and adhesive. SF X 30,000 = -$

A-5 F/I Carpet Floor Tile. SF X 30,000 = -$

A-6 Remove and Reinstall Raised Access Floor Panels – entails one-time removal and replacement only.

Light furniture relocation included. Heavy equipment and furniture to be relocated by others. SF X 2,000 = -$

A-7 Remove Cove Base. LF X 1,000 = -$

A-8 F/I Cove Base. LF X 1,000 = -$

A-9 Demo CMU Wall – not cut-out demo. No toothing. Assumes full wall sections at least 10’ long. Includes dust protection. CY X 50 = -$

A-10 Demo Stud Wall – includes saw cutting if necessary. SF X 5,000 = -$

A-11 Stud/Drywall Partition – includes constructing stud wall, drywall, taping, spackling, and finishing;

excludes insulation. SF X 5,000 = -$

A-12 Skim Coat Patch Drywall – assumes entire wall needs refinishing. Includes applying Durabond and Lafarge compound skim coats. SF X 3,000 = -$

A-13 Prepare and Paint Walls – includes repairing any minor imperfections, sanding, and painting with 1 coat primer and 2 coats latex. SF X 25,000 = -$

A-14 F/I 1/4" drywall over existing wall - includes adhesive or mechanical fasteners and preparation for painting. SF X 25,000 = -$

A-15 F/I Room Signs – includes Hermes #723-087 frame with header and 3-lines. Only room number tag is included. EA X 50 = -$

A-16 Wall Penetrations up to 4" in diameter – used for conduit or pipe wall penetrations through masonry or partition walls. Core drilling through concrete not included. Fire caulk not included. EA X 20 = -$

A-17 Fire Caulk Penetration up to 4" in diameter – fire caulk only.

This is the start of the file's text. The full file is on GovTribe.