Exhibit M10- Photovoltaic Maintenance Checklist.pdf
PDF 270 KB Posted
- Attached to
- Full Maintenance and Operations, Laredo, TX Federal contract opportunity
- Solicitation number
- 47PH0220R0014
View the file
Other files for this federal contract opportunity
Show all 50
Full Maintenance and Operations, Laredo, TX has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit M10
Item
PV Service Description
Frequency/ Response
Time
Visual inspection of Solar Facility’s general site conditions, PV arrays, electrical equipment, mounting structure, fence, shading, trackers, vegetation, animal damage, erosion, corrosion, and discolored panels.
Every 6 months
Visual inspection and correction of Solar Facility for loose electrical connections and ground connections.
String-level open-circuit voltage, DC operating current tests, and I-V curve traces on 100% of all strings.
1x per year
4 All switches and disconnects tested to ensure they are not jammed.
Infrared scans on 100% combiner and re-combiner boxes; tighten connections to manufacturer's torque specification; report broken terminal blocks.
Every 3 years
100% check calibration expiration on sensors and meters, including pyranometers, and anemometers and perform other service such as cleaning and replacement of any desiccant.
Turn off and on logging and communications to ensure they are communicating and ensure battery backups are working.
Inverter preventive maintenance for 100% of all inverters per manufacturer’s operating guidelines
See
8a,8b,8c & 8d
8a Clean inverter cabinet air vents.
8b Clean and change inverter air filters, if present, per manufacturer’s warranty requirements.
8c Clean/remove dust from inverter heat sinks per manufacturer’s warranty requirements.
8d Check torque marks and re-tightening appropriate wiring connections to design specification torque force per manufacturer’s guidelines.
9 Inspect roof penetrations to ensure sealant is applied properly and not degrading.
10 PV array module maintenance for all modules See 10a & 10b
10a Wash all panels with water with no chemicals in a method approved by the
Owner.
10b Perform infrared scan of 100% of modules for two types of circuitry connections: cells on the front and junction boxes on the back.
Every 3 years
*Adapted from the following authority:
Technical Report
NREL/TP-7A40-73822
December 2018