This is a COMcheck Envelope Report for the Beatty Health Center, a new construction health care clinic project located in Chiloquin, Oregon, under the jurisdiction of the Klamath Tribal Health organization. The project, identified as Project No. 162136, involves the design and construction of a 4,065 square-foot, single-story health care clinic facility at 24110 Godowa Springs Road, Beatty, Oregon 97621. The project is being designed by Steele Associates (2738 NW Potts Court, Bend, Oregon 97703) with Jordan Arredondo serving as the owner's agent. The facility is designed to comply with ASHRAE 90.1 (2022) Standard energy code requirements for Climate Zone 5b and was evaluated using EnergyPlus 24.1.0 simulation software. The compliance report was issued on September 3, 2026.
The project achieved a compliance score of 47.0 energy credits against a required baseline of 66.8 credits through various efficiency measures including occupancy sensor controls (1.0 credits), reduced lighting power (18.0 credits), heating and cooling efficiency improvements (19.8 combined credits), energy monitoring (3.0 credits), and improved envelope performance (25.0 credits). The envelope design passed inspection with performance 1 percent better than code requirements. Key envelope components include a roof with R-30 insulation, wood frame exterior walls with R-21 cavity insulation, vinyl/fiberglass windows with U-factors of 0.290, and an unheated slab-on-grade foundation with R-10 insulation. The facility was exempted from renewable energy requirements due to its floor area being less than 10,000 square feet. All inspection checklist requirements related to building envelope, electrical systems, footing and foundation, and framing components were documented as compliant or marked for field verification during construction.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 1 of 12
Compliance Certificate
Project Information
Energy Code:
Project Title:
Location:
Climate Zone:
Project Type:
Project No:
Performance Sim. Specs:
Project Sub Type:
All Electric:
Is Renewable:
Has Battery:
Has Charger:
Has Heat Pump
90.1 (2022) Standard Klamath Tribal Health Chiloquin, Oregon 5b New Construction 162136 EnergyPlus 24.1.0 (EPW: ) New Building/Complete false false false false false
Construction Site: Owner/Agent: Designer/Contractor:
24110 Godowa Springs Rd Beatty , Oregon 97621
Jordan Arredondo Steele Associates 2738 NW Potts Ct Bend , Oregon 97703
Notes:
Energy Credits
Description Credit
L03 Occupancy Sensor Control Areas 1.0
L06 Reduced lighting power 18.0
H03 5% cooling efficiency improvement 16.4
H02 5% heating efficiency improvement 3.4
P01 Energy monitoring 3.0
Q02 Efficient kitchen equipment 0.0
G01 Lighting Load Management 0.0
G02 HVAC Load Management 0.0
W05 Point of Use Water Heater 0.0
E01 Improved Envelope Performance 25.0
Credits: 47.0 Required 66.8 Proposed
Renewable energy
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 2 of 12
Number of Floors:
Area of Three Largest Floors:
Proposed Capacity:
Required Capacity:
Exception:
Building effective floor area is less than 10,000 ft2.
Renewables Pass: Exception: Building effective floor area is less than 10,000 ft2.
Building Area
Description Floor Area
1-Health Care-Clinic (Health Care-Clinic) : Nonresidential 4065
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 3 of 12
Envelope Compliance Certificate
Project Information
Energy Code:
Project Title:
Location:
Climate Zone:
Project Type:
Vertical Glazing / Wall Area:
Performance Sim. Specs:
Project Sub Type:
90.1 (2022) Standard Klamath Tribal Health Chiloquin, Oregon 5b New Construction 0.128 EnergyPlus 24.1.0 (EPW: ) New Building/Complete
Construction Site: Owner/Agent: Designer/Contractor:
24110 Godowa Springs Rd Beatty , Oregon 97621
Jordan Arredondo Steele Associates 2738 NW Potts Ct Bend , Oregon 97703
Envelope Assemblies
Assembly Gross Area or Perimeter
Cavity R- Value
Cont.
R- Value
Proposed U-Factor
Budget U- Factor
Roof:Roof - R1, Insulation Entirely Above Deck, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
4619 --- 30.00 0.032 0.032
Floor:Floor, Unheated Slab-On-Grade, Vertical 2 ft., Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic] (c)
263 --- 10.00 0.540 0.520
NORTH
Ext Wall:Ext Wall_N, Wood Frame, Any Spacing, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
724 0.21 10.00 0.076 0.051
Window:Window_N, Vinyl/Fiberglass Frame, Perf. Specs.: Product ID , SHGC 0.39, PF 0.35, VT 0.70, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic] (b)
95 --- --- 0.290 0.360
EAST
Ext Wall:Ext Wall_E, Wood Frame, Any Spacing, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
1277 21.00 10.00 0.036 0.051
Window:Window - Storefront_E, Metal Frame, Perf. Specs.: Product ID , SHGC 0.39, PF 0.35, VT 0.70, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic] (b)
56 --- --- 0.290 0.360
Window:Window_E, Vinyl/Fiberglass Frame, Perf. Specs.: Product ID , SHGC 0.39, PF 0.35, VT 0.70, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic] (b)
126 --- --- 0.290 0.360
Door:Door - Glass_E, Perf. Specs.: Product ID , SHGC 0.39, PF 0.35, VT 0.70, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic] (b)
25 --- --- 0.290 0.630
SOUTH
Ext Wall:Ext Wall_S, Wood Frame, Any Spacing, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
704 21.00 10.00 0.036 0.051
Window:Window_S, Vinyl/Fiberglass Frame, Perf. Specs.: Product ID , SHGC 0.39, PF 0.35, VT 0.70, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic] (b)
60 --- --- 0.290 0.360
Door:Door 1 - Mtl_S, Insulated Metal, Swinging, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
25 --- --- 0.150 0.370
Door:Door 2 - Mtl_S, Insulated Metal, Swinging, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
25 --- --- 0.150 0.370
WEST
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 4 of 12
Assembly Gross Area or Perimeter
Cavity R- Value
Cont.
R- Value
Proposed U-Factor
Budget U- Factor
Ext Wall:Ext Wall_W, Wood Frame, Any Spacing, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
988 21.00 10.00 0.036 0.051
Window:Window_W, Vinyl/Fiberglass Frame, Perf. Specs.: Product ID , SHGC 0.39, PF 0.35, VT 0.70, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic] (b)
110 --- --- 0.290 0.360
Door:Door - Mtl_W, Insulated Metal, Swinging, Exterior Envelope, [Bldg. Use 1 - Health Care-Clinic]
25 --- --- 0.150 0.370
(a) Budget U-factors are used for software baseline calculations ONLY, and are not code requirements.
(b) Fenestration product performance must be certified in accordance with NFRC and requires supporting documentation.
(c) Slab-On-Grade proposed and budget U-factors shown in table are F-factors.
Envelope PASSES: Design 1% better than code
Envelope Compliance Statement
Compliance Statement: The proposed envelope design represented in this document is consistent with the building plans, specifications, and other calculations submitted with this permit application. The proposed envelope systems have been designed to meet the 90.1 (2022) Standard requirements in COMcheckWeb and to comply with any applicable mandatory requirements listed in the Inspection Checklist.
Name - Title Signature Date
09/03/2026
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 5 of 12
Inspection Checklist
Energy Code: 90.1 (2022) Standard
Requirements: 16% were addressed directly in the COMcheck software
Text in the "Comments/Assumptions" column is provided by the user in the COMcheck Requirements screen. For each requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Plan Review
Section
& Req.ID Plan Review Complies? Comments/Assumptions
4.2.2, 5.4.3.1.1,
5.7 [PR1]1
Plans and/or specifications provide all information with which compliance can be determined for the building envelope and document where exceptions to the standard are claimed.
Complies
Does Not Comply
Not Observable
Not Applicable
4.2.2, 8.4.1.1, 8.4.1.2, 8.7
[PR6]2
Plans, specifications, and/or calculations provide all information with which compliance can be determined for the electrical systems and equipment and document where exceptions are claimed. Feeder connectors sized in accordance with approved plans and branch circuits sized for maximum drop of 3%.
Complies
Does Not Comply
Not Observable
Not Applicable
Location on plans/spec: TBD
5.5.4.2.3
[PR7]2
In buildings > 2,500 ft2, any enclosed spaces directly under a roof with ceiling heights > 15 ft.
and used as an office, lobby, atrium, concourse, corridor, storage (including nonrefrigerated warehouse), gymnasium, fitness/exercise area, playing area, gymnasium seating area, convention exhibit/event space, courtroom, automotive service, fire station engine room, manufacturing corridor/transition and bay areas, retail, library reading and stack areas, distribution/sorting area, transportation baggage and seating areas, or workshop, the following requirements apply: The daylight zone under skylights is >= half the floor area and (a) the skylight area to daylight zone is >= 3 percent with a skylight VT >= 0.40 or (b) the minimum skylight effective aperture >= 1 percent. The skylights have a measured haze value > 90 percent.
Complies
Does Not Comply
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1) 2 Medium Impact (Tier 2) 3 Low Impact (Tier 3)
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 6 of 12
Footing / Foundation Inspection
Section
& Req.ID Footing / Foundation Inspection
Plans Verified Value
Field Verified Value Complies? Comments/Assumptions
4.2.4
[FO1]2
Installed below-grade wall insulation type and R-value consistent with insulation specifications reported in plans and COMcheck reports.
R- R- Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
4.2.4
[FO3]2
Installed slab-on-grade insulation type and R-value consistent with insulation specifications reported in plans and COMcheck reports.
R-
Unheated
Heated
R-
Unheated
Heated
Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.8.1.2
[FO4]2
Slab edge insulation installed per manufacturer’s instructions.
Complies
Does Not Comply
Not Observable
Not Applicable
5.5.3.5
[FO5]2
Slab edge insulation depth/length. ft ft Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.8.1.7
[FO6]1
Exterior insulation protected against damage, sunlight, moisture, wind, landscaping and equipment maintenance activities.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.7.3
[FO7]1
Insulation in contact with the ground has <=0.3% water absorption rate per
ASTM C272.
Complies
Does Not Comply
Not Observable
Not Applicable
6.4.4.1.5
[FO11]3
Bottom surface of floor structures incorporating radiant heating insulated to >=R-3.5.
R- R- Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 7 of 12
Framing / Rough-In Inspection
Section # & Req.ID
Framing / Rough-In Inspection
Plans Verified Value
Field Verified Value Complies? Comments/Assumptions
5.4.3.2
[FR1]3
Continuous air barrier is wrapped, sealed, caulked, gasketed, and/or taped in an approved manner.
Complies
Does Not Comply
Not Observable
Not Applicable
5.4.3.1
[FR15]1
The buildings complies with measured air leakage requirements in Section
5.4.3.1.4 or with continuous air barrier design and installation in accordance with Section 5.9.1.2
Complies
Does Not Comply
Not Observable
Not Applicable
5.4.3.4
[FR4]3
Vestibules are installed where building entrances separate conditioned space from the exterior, and meet exterior envelope requirements. Doors have self-closing devices, and are >=7 ft apart (>= 16 ft apart for adjoinging floor area >= 40000 sq.ft.). Vestibule floor area <=7 50 sq.ft. or 2 percent of the adjoining conditioned floor area.
Complies
Does Not Comply
Not Observable
Not Applicable
5.5.4.3a
[FR8]1
Vertical fenestration U-Factor. U- U- Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.5.4.3b
[FR9]1
Skylight fenestration U-Factor. U- U- Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.5.4.4.1
[FR10]1
Vertical fenestration SHGC value. SHGC: SHGC: Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.5.4.4.2
[FR11]1
Skylight SHGC value. SHGC: SHGC: Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.8.2.1, 5.8.2.3, 5.8.2.4, 5.8.2.5
[FR12]2
Fenestration products rated (U-factor, SHGC, and VT) in accordance with NFRC or energy code defaults are used.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.2.2
[FR13]1
Fenestration and door products are labeled, or a signed and dated certificate listing the U-factor, SHGC, VT, and air leakage rate has been provided by the manufacturer.
Complies
Does Not Comply
Not Observable
Not Applicable
5.5.3.6
[FR14]2
U-factor of opaque doors associated with the building thermal envelope meets requirements.
U-
Swinging
Nonswinging
U-
Swinging
Nonswinging
Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 8 of 12
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 9 of 12
Rough-In Electrical Inspection
Section
& Req.ID Rough-In Electrical Inspection Complies? Comments/Assumptions
8.4.2
[EL10]2
At least 50% of all 125 volt 15- and 20-Amp receptacles are controlled by an automatic control device.
Complies
Does Not Comply
Not Observable
Not Applicable
Location on plans/spec: TBD
8.4.3
[EL11]2
New buildings have electrical energy use measurement devices installed. Where tenant spaces exist, each tenant is monitored separately. In buildings with a digital control system the energy use is transmitted to to control system and displayed graphically.
Complies
Does Not Comply
Not Observable
Not Applicable
Location on plans/spec: TBD
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 10 of 12
Insulation Inspection
Section
& Req.ID Insulation Inspection
Plans Verified Value
Field Verified Value Complies? Comments/Assumptions
5.8.1.1
[IN10]2
Building envelope insulation is labeled with R-value or insulation certificate has been provided listing R-value and other relevant data.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.9
[IN18]2
Building envelope insulation extends over the full area of the component at the proposed rated R or U value.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.4
[IN11]2
Eaves are baffled to deflect air to above the insulation.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.5
[IN12]2
Insulation is installed in substantial contact with the inside surface separating conditioned space from unconditional space.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.6
[IN13]2
Recessed equipment installed in building envelope assemblies does not compress the adjacent insulation.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.7.1
[IN15]2
Attics and mechanical rooms have insulation protected where adjacent to attic or equipment access.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.7.2
[IN16]2
Foundation vents do not interfere with insulation.
Complies
Does Not Comply
Not Observable
Not Applicable
5.8.1.8
[IN17]3
Insulation intended to meet the roof insulation requirements cannot be installed on top of a suspended ceiling.
Mark this requirement compliant if insulation is installed accordingly.
Complies
Does Not Comply
Not Observable
Not Applicable
4.2.4 [IN2]1 Installed roof insulation type and R-value consistent with insulation specifications reported in plans and COMcheck reports. For some ceiling systems, verification may need to occur during Framing Inspection.
R-
Above deck
Metal
Attic
R-
Above deck
Metal
Attic
Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.8.1.2, 5.8.1.3
[IN3]1
Roof insulation installed per manufacturer’s instructions. Blown or poured loose-fill insulation is installed only where the ceiling slope is <= 3:12.
Complies
Does Not Comply
Not Observable
Not Applicable
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 11 of 12
Section
& Req.ID Insulation Inspection
Plans Verified Value
Field Verified Value Complies? Comments/Assumptions
4.2.4 [IN6]1 Installed above-grade wall insulation type and R-value consistent with insulation specifications reported in plans and COMcheck reports.
R-
Mass
Metal
Steel
Wood
R-
Mass
Metal
Steel
Wood
Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
5.8.1.2
[IN7]1
Above-grade wall insulation installed per manufacturer’s instructions.
Complies
Does Not Comply
Not Observable
Not Applicable
4.2.4 [IN8]2 Installed floor insulation type and R-value consistent with insulation specifications reported in plans and COMcheck reports.
R-
Mass
Steel
Wood
R-
Mass
Steel
Wood
Complies
Does Not Comply
Not Observable
Not Applicable
See the Envelope Assemblies table for values
Report Title: Klamath Tribal Health Report Date: Sep 03, 2026, 04:04 PM (PDT) 12 of 12
Final Inspection
Section
& Req.ID Final Inspection Complies? Comments/Assumptions
5.4.3.3
[FI1]1
Weatherseals installed on all loading dock cargo doors in Climate Zones 4-8.
Complies
Does Not Comply
Not Observable
Not Applicable
11.5.2.3.3a
[FI55]2
W05: Point of Use Water Heater energy credit measure requires hot water to be supplied from localized source without recirculation or heat trace. Pipe insulation according to Table 6.8.3- 1 and volume of water in piping limited to 2 oz for nonresidential lavatories or 0.25 oz for all other plumbing fixtures.
Complies
Does Not Comply
Not Observable
Not Applicable
See the Mechanical Systems list for values
11.5.2.4
[FI60]2
P01: Energy Monitoring energy credit measure requires projects that are not required to have electrical energy monitoring systems installed shall be equipped to measure, monitor, record, and report energy consumption data in compliance with Section 8.4.3.
Complies
Does Not Comply
Not Observable
Not Applicable
11.5.2.5.3
[FI62]2
L03: Occupancy Sensors Control Areas energy credit measure requires buildings use “Simplified Building Method Compliance Path,” or in spaces where automatic partial OFF or automatic full OFF is not required, it shall be installed in accordance with Section 11.5.2.5.3.
Complies
Does Not Comply
Not Observable
Not Applicable
See the Interior Lighting fixture schedule for values Location on plans/spec: TBD
11.5.2.7.2
[FI67]2
Q02: Efficient Kitchen Equipment energy credit measure requires buildings with a commercial kitchen with at least one gas or electric fryer and all other cooking appliances comply with Section 11.5.2.7.2.
Complies
Does Not Comply
Not Observable
Not Applicable
Location on plans/spec: TBD
11.5.2.8.1
[FI69]2
G01: Lighting Load Management energy credit measure requires luminaires have dimming capability and load management controls reduce general lighting power with continuous dimming in 75% of the project area during peakprice periods coincident with high building load.
Complies
Does Not Comply
Not Observable
Not Applicable
Energy credit params: Percentage lighting load management (in %): 0.0
11.5.2.8.2
[FI70]2
G02: HVAC Load Management energy credit measure requires load management shall a) increase cooling set point > 3F or reduce cooling capacity to 60% of installed capacity;
b) for electric heating, reduce heating set point > 3F or reduce heating capacity to 60% of installed capacity; and c) provide excess outdoor air and reduce outdoor air in accordance with ASHRAE Standard 62.1, Section 6.2.5.2.
Complies
Does Not Comply
Not Observable
Not Applicable
File details come from the government source that posted it. Updated .