Exhibit 1.1 911 FB Seismic-NOAA-Electrical Milestone Schedule 1.27.20.pdf
PDF 175 KB Posted
- Attached to
- 911 Fed Bldg Electrical System Upgrade Design Build Federal contract opportunity
- Solicitation number
- EQ10PCP-20-0005
About this file
This document provides details for an electrical system upgrade design-build project at the 911 Federal Building in Portland, Oregon. The General Services Administration is seeking to replace all medium and low-voltage switchgear, switchboards, and panel boards throughout the building, replace motor control centers, replace an emergency generator, and install a new lightning protection system. Tenants in the building include the U.S. House of Representatives, Senate, Department of the Interior, Department of Labor, Department of Homeland Security, and Bonneville Power Administration. The design-build contractor will be responsible for all design and construction efforts to deliver a highly collaborative project that meets stakeholders' needs and GSA's requirements. The solicitation number is EQ10PCP-20-0005 and responses are due based on the project schedule provided in the document.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish 1 911 FB PROSPECTUS (PHASED) MASTER MILESTONES 811 days? Tue 10/15/19 Mon 1/23/23 2 SCD NOAA OCCUPANCY (Critical NTE 1/20/23) 0 days Fri 1/20/23 Fri 1/20/23 3 SCD NOAA - TI Work Complete (Critical NTE 12/1/22) 0 days Thu 12/1/22 Thu 12/1/22 4 SCD NOAA - FF&E (Critical NTE 12/30/22) 0 days Fri 12/30/22 Fri 12/30/22 5 SCD ELECTRICAL SWGR (Critical NTE 9/1/22) 0 days Thu 9/1/22 Thu 9/1/22 6 SCD STRUCTURAL (Critical NTE 12/1/22) 0 days Thu 12/1/22 Thu 12/1/22 7 CMA/CxA ACQUISITION & PERFORMANCE 788 days Mon 11/18/19 Mon 1/23/23 8 CMA/CxA ACQUISITION PERIOD 122 days Mon 11/18/19 Wed 5/13/20 27 Contract Award (CMA/CxA) 1 day Thu 5/14/20 Thu 5/14/20 28 Contract Distro (CMA/CxA) 1 day Fri 5/15/20 Fri 5/15/20 29 CMA/CxA PERFORMANCE PERIOD 664 days Mon 5/18/20 Mon 1/23/23 30 Start CMA/CxA Performance Period 1 day Mon 5/18/20 Mon 5/18/20 31 CMA/CxA (DB-SN Step 2) ACQUISITION Phase 36 days Thu 8/13/20 Mon 10/5/20 35 Finish CMA/CxA (DB-SN Step 2) ACQUISITION Phase 0 days Mon 10/5/20 Mon 10/5/20 36 CMA/CxA Design & Construction Phase 561 days Fri 8/28/20 Wed 12/7/22 37 DB Design Phase Start 145 days Fri 8/28/20 Thu 4/8/21 40 DB Design Phase Complete 88 days Thu 12/31/20 Fri 5/14/21 43 DB Construction Phase Start 267 days Mon 1/4/21 Fri 2/4/22 46 DB Construction Phase Complete 103 days Fri 7/8/22 Wed 12/7/22 49 CMA/CxA FINANCIAL/CONTRACTUAL CLOSE-OUT 30 days Thu 12/8/22 Mon 1/23/23 52 CMA/CxA Performance Complete 0 days Mon 1/23/23 Mon 1/23/23 53 DB-E (ELEC) ACQUISITION & PERFORMANCE 678 days? Tue 10/15/19 Fri 7/8/22 54 DB-E (ELEC) ACQUISITION PHASE 207 days Tue 10/15/19 Tue 8/11/20 82 DB-E (ELEC) Contract Award 1 day Wed 8/12/20 Wed 8/12/20 84 DB-E (ELEC) PRE-PERFORMANCE PHASE 35 days? Wed 8/12/20 Wed 9/30/20 88 Issue DESIGN NTP DB-E (ELEC) 0 days Fri 8/28/20 Fri 8/28/20 89 DB-E (ELEC) DESIGN PHASE 95 days Mon 8/31/20 Wed 1/20/21 100 DB-E (ELEC) DESIGN COMPLETE 0 days Thu 12/31/20 Thu 12/31/20 101 DB-E (ELEC) CONSTRUCTION PHASE 360 days? Tue 12/29/20 Mon 6/13/22 125 SUBSTANTIAL COMPLETION (SCD) - DB-E (ELEC) 0 days Mon 5/16/22 Mon 5/16/22 126 DB-E (ELEC) FINANCIAL/CONTRACTUAL CLOSE-OUT 38 days Mon 5/16/22 Fri 7/8/22 129 DB-E (ELEC) PROJECT COMPLETION 0 days Fri 7/8/22 Fri 7/8/22 130 DB-S_N (STRUCT_NOAA TI) ACQUISITION & PERFORMANCE 745 days? Mon 12/9/19 Wed 12/7/22 131 DB-S_N (STRUCT_NOAA) ACQUISITION PHASE 208 days Mon 12/9/19 Fri 10/2/20 159 DB-S_N (STRUCT_NOAA) Contract Award 1 day Mon 10/5/20 Mon 10/5/20 161 DB-S_N (STRUCT_NOAA) PRE-PERFORMANCE PHASE 43 days? Tue 10/6/20 Wed 12/9/20 165 Issue DESIGN NTP - DB-S_N (STRUCTURAL/SEISMIC) 0 days Wed 12/9/20 Wed 12/9/20 166 DB-S_N (STRUCTURAL/SEISMIC) DESIGN PHASE 77 days Thu 12/10/20 Thu 4/8/21 178 DESIGN (STRUCTURAL/SEISMIC) COMPLETE 0 days Thu 4/8/21 Thu 4/8/21 179 Issue DESIGN NTP - DB-S_N (NOAA TI) 0 days Wed 12/9/20 Wed 12/9/20 180 DB-S_N (NOAA TI) DESIGN PHASE 103 days Thu 12/10/20 Fri 5/14/21 192 DESIGN (NOAA TI) COMPLETE 0 days Fri 5/14/21 Fri 5/14/21 193 DB-S_N (STRUCT_NOAA) CONSTRUCTION PHASE 361 days? Fri 4/9/21 Thu 9/15/22 194 DB-S_N (STRUCT/SEISMIC) CONSTRUCTION 361 days? Fri 4/9/21 Thu 9/15/22 195 DB-S_N (STRUCT/SEISMIC) CONSTRUCTION NTP 1 day Fri 4/9/21 Fri 4/9/21 196 MEP/FINISHES RESTORATION PHASE 360 days? Mon 4/12/21 Thu 9/15/22 199 CORE PHASE 90 days? Mon 4/12/21 Tue 8/17/21 202 BATHROOMS PHASE 200 days? Mon 4/12/21 Fri 1/28/22 205 EAST STAIRWELL PHASE 180 days? Mon 4/12/21 Wed 12/29/21 208 WEST STAIRWELL PHASE 170 days? Thu 12/30/21 Wed 8/31/22 211 Substantial Completion (STRUCT/SEISMIC) 0 days Thu 9/15/22 Thu 9/15/22 212 DB-S_N (NOAA TI) CONSTRUCTION PHASE 115 days? Fri 2/4/22 Wed 7/20/22 220 Substantial Completion (NOAA TI) 0 days Wed 7/20/22 Wed 7/20/22 221 SUBSTANTIAL COMPLETION (SCD) - DB-S_N (STRUCT_NOAA) 0 days Thu 9/15/22 Thu 9/15/22 222 NOAA FF&E (NOAA Tenant Responsibility Items) 30 days Thu 7/28/22 Thu 9/8/22 228 NOAA TI Build-out / FF&E COMPLETE 0 days Thu 9/8/22 Thu 9/8/22 229 DB-S_N (STRUCT_NOAA) CONSTRUCTION CLOSEOUT PHASE 20 days Fri 9/16/22 Fri 10/14/22 235 DB-S_N (STRUCT_NOAA) FINANCIAL/CONTRACTUAL CLOSE-OUT 35 days Mon 10/17/22 Wed 12/7/22 238 DB-S_N (STRUCT_NOAA) PROJECT COMPLETION 0 days Wed 12/7/22 Wed 12/7/22
1/20 12/1
12/30 9/1
12/1
10/5
1/23
8/28
12/31
5/16
7/8
12/9
4/8 12/9
5/14
9/15
7/20 9/15
9/8
12/7
Apr '19May '19Jun '19Jul '19Aug '19Sep '19Oct '19Nov '19Dec '19Jan '20Feb '20Mar '20Apr '20May '20Jun '20Jul '20Aug '20Sep '20Oct '20Nov '20Dec '20Jan '21Feb '21Mar '21Apr '21May '21Jun '21Jul '21Aug '21Sep '21Oct '21Nov '21Dec '21Jan '22Feb '22Mar '22Apr '22May '22Jun '22Jul '22Aug '22Sep '22Oct '22Nov '22Dec '22Jan '23Feb '
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Project: 911 FB COMBO PROJECT M Date: Mon 2/17/20