Exhibit 1.1 911 FB Seismic-NOAA-Electrical Milestone Schedule 1.27.20.pdf

PDF 175 KB Posted

Attached to
911 Fed Bldg Electrical System Upgrade Design Build Federal contract opportunity
Solicitation number
EQ10PCP-20-0005
Issued by
General Services Administration Public Buildings Service Region 10

About this file

This document provides details for an electrical system upgrade design-build project at the 911 Federal Building in Portland, Oregon. The General Services Administration is seeking to replace all medium and low-voltage switchgear, switchboards, and panel boards throughout the building, replace motor control centers, replace an emergency generator, and install a new lightning protection system. Tenants in the building include the U.S. House of Representatives, Senate, Department of the Interior, Department of Labor, Department of Homeland Security, and Bonneville Power Administration. The design-build contractor will be responsible for all design and construction efforts to deliver a highly collaborative project that meets stakeholders' needs and GSA's requirements. The solicitation number is EQ10PCP-20-0005 and responses are due based on the project schedule provided in the document.

View the file

Other files for this federal contract opportunity

Other files attached to 911 Fed Bldg Electrical System Upgrade Design Build, newest first.
File Type Posted
Amd 02 Exhibit 1.2 911 Fed Bldg Electrical Upgrade Design Build SOW (Final) 4.24.20.docx DOCX document
Amd 02 Exhibit 2.2 RFI's & Responses 04.27.20.docx DOCX document
Amd 02 Exhibit 6 Price and Services Schedule 4.24.20.docx DOCX document
Amd 02 Division 01 Specifications-20200427T224125Z-001 (1).zip ZIP file
Amd 02 911 Fed Bldg Electrical Upgrade Design Build - Agreement 4.27.20 (Conformed).docx DOCX document
Amd 02 SF30.pdf PDF
Amd 02 Exhibit 7 Wage Determination Gen Decision OR20200029 Mod 3 04172020.pdf PDF
911 Electrical Site Visit Attendance Sheet.docx DOCX document
911 Electrical Agenda (Pre-Proposal Conference) (6).docx DOCX document
Exhibit 9 Key Personnel Resume Format.docx DOCX document
SF30 Amd 01.pdf PDF
Amd 01 911 Fed Bldg Electrical Upgrade Design Build - Solicitation 4.2.20 (Conformed).docx DOCX document
Amd 01 Exhibit 1.2 911 Fed Bldg Electrical Upgrade Design Build SOW (Draft) 4.6.20.docx DOCX document
Amd 01 Exhibit 9 CD-2020-05 - Digital Signatures for Bonds.pdf PDF
Amd 01 Exhibit 2 Pre-Proposal Conference Job Walk 4.2.20 (Conformed).docx DOCX document
Amd 01 Exhibit 6 Price and Services Schedule 4.2.20.docx DOCX document
Amd 01 911 Fed Bldg Electrical Upgrade Design Build - Agreement 4.6.20 (Conformed).docx DOCX document
Exhibit 2 Pre-Proposal Conference Job Walk.docx DOCX document
Exhibit 6 Price and Services Schedule.docx DOCX document
Exhibit 8 Offerors Representations and Certifications.docx DOCX document
911 Fed Bldg Electrical Upgrade Design Build - Agreement 3.23.20.docx DOCX document
911 Fed Bldg Electrical Upgrade Design Build - Solicitation 3.23.20.docx DOCX document
Exhibit 00 SF1442.pdf PDF
Exhibit 1 911 Fed Bldg Electrical Upgrade Scope Summary.docx DOCX document
Exhibit 0 SBU Document.docx DOCX document
Exhibit 7 Wage Determination Gen Decision OR20200029 Mod 2 03062020.pdf PDF
Exhibit 4 Performance Evaluation Survey - Commercial Client.docx DOCX document
Exhibit 3 Project Experience.docx DOCX document
Exhibit 5 GACA - GSA Affiliated Customer Accounts May 2014.docx DOCX document
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish 1 911 FB PROSPECTUS (PHASED) MASTER MILESTONES 811 days? Tue 10/15/19 Mon 1/23/23 2 SCD NOAA OCCUPANCY (Critical NTE 1/20/23) 0 days Fri 1/20/23 Fri 1/20/23 3 SCD NOAA - TI Work Complete (Critical NTE 12/1/22) 0 days Thu 12/1/22 Thu 12/1/22 4 SCD NOAA - FF&E (Critical NTE 12/30/22) 0 days Fri 12/30/22 Fri 12/30/22 5 SCD ELECTRICAL SWGR (Critical NTE 9/1/22) 0 days Thu 9/1/22 Thu 9/1/22 6 SCD STRUCTURAL (Critical NTE 12/1/22) 0 days Thu 12/1/22 Thu 12/1/22 7 CMA/CxA ACQUISITION & PERFORMANCE 788 days Mon 11/18/19 Mon 1/23/23 8 CMA/CxA ACQUISITION PERIOD 122 days Mon 11/18/19 Wed 5/13/20 27 Contract Award (CMA/CxA) 1 day Thu 5/14/20 Thu 5/14/20 28 Contract Distro (CMA/CxA) 1 day Fri 5/15/20 Fri 5/15/20 29 CMA/CxA PERFORMANCE PERIOD 664 days Mon 5/18/20 Mon 1/23/23 30 Start CMA/CxA Performance Period 1 day Mon 5/18/20 Mon 5/18/20 31 CMA/CxA (DB-SN Step 2) ACQUISITION Phase 36 days Thu 8/13/20 Mon 10/5/20 35 Finish CMA/CxA (DB-SN Step 2) ACQUISITION Phase 0 days Mon 10/5/20 Mon 10/5/20 36 CMA/CxA Design & Construction Phase 561 days Fri 8/28/20 Wed 12/7/22 37 DB Design Phase Start 145 days Fri 8/28/20 Thu 4/8/21 40 DB Design Phase Complete 88 days Thu 12/31/20 Fri 5/14/21 43 DB Construction Phase Start 267 days Mon 1/4/21 Fri 2/4/22 46 DB Construction Phase Complete 103 days Fri 7/8/22 Wed 12/7/22 49 CMA/CxA FINANCIAL/CONTRACTUAL CLOSE-OUT 30 days Thu 12/8/22 Mon 1/23/23 52 CMA/CxA Performance Complete 0 days Mon 1/23/23 Mon 1/23/23 53 DB-E (ELEC) ACQUISITION & PERFORMANCE 678 days? Tue 10/15/19 Fri 7/8/22 54 DB-E (ELEC) ACQUISITION PHASE 207 days Tue 10/15/19 Tue 8/11/20 82 DB-E (ELEC) Contract Award 1 day Wed 8/12/20 Wed 8/12/20 84 DB-E (ELEC) PRE-PERFORMANCE PHASE 35 days? Wed 8/12/20 Wed 9/30/20 88 Issue DESIGN NTP DB-E (ELEC) 0 days Fri 8/28/20 Fri 8/28/20 89 DB-E (ELEC) DESIGN PHASE 95 days Mon 8/31/20 Wed 1/20/21 100 DB-E (ELEC) DESIGN COMPLETE 0 days Thu 12/31/20 Thu 12/31/20 101 DB-E (ELEC) CONSTRUCTION PHASE 360 days? Tue 12/29/20 Mon 6/13/22 125 SUBSTANTIAL COMPLETION (SCD) - DB-E (ELEC) 0 days Mon 5/16/22 Mon 5/16/22 126 DB-E (ELEC) FINANCIAL/CONTRACTUAL CLOSE-OUT 38 days Mon 5/16/22 Fri 7/8/22 129 DB-E (ELEC) PROJECT COMPLETION 0 days Fri 7/8/22 Fri 7/8/22 130 DB-S_N (STRUCT_NOAA TI) ACQUISITION & PERFORMANCE 745 days? Mon 12/9/19 Wed 12/7/22 131 DB-S_N (STRUCT_NOAA) ACQUISITION PHASE 208 days Mon 12/9/19 Fri 10/2/20 159 DB-S_N (STRUCT_NOAA) Contract Award 1 day Mon 10/5/20 Mon 10/5/20 161 DB-S_N (STRUCT_NOAA) PRE-PERFORMANCE PHASE 43 days? Tue 10/6/20 Wed 12/9/20 165 Issue DESIGN NTP - DB-S_N (STRUCTURAL/SEISMIC) 0 days Wed 12/9/20 Wed 12/9/20 166 DB-S_N (STRUCTURAL/SEISMIC) DESIGN PHASE 77 days Thu 12/10/20 Thu 4/8/21 178 DESIGN (STRUCTURAL/SEISMIC) COMPLETE 0 days Thu 4/8/21 Thu 4/8/21 179 Issue DESIGN NTP - DB-S_N (NOAA TI) 0 days Wed 12/9/20 Wed 12/9/20 180 DB-S_N (NOAA TI) DESIGN PHASE 103 days Thu 12/10/20 Fri 5/14/21 192 DESIGN (NOAA TI) COMPLETE 0 days Fri 5/14/21 Fri 5/14/21 193 DB-S_N (STRUCT_NOAA) CONSTRUCTION PHASE 361 days? Fri 4/9/21 Thu 9/15/22 194 DB-S_N (STRUCT/SEISMIC) CONSTRUCTION 361 days? Fri 4/9/21 Thu 9/15/22 195 DB-S_N (STRUCT/SEISMIC) CONSTRUCTION NTP 1 day Fri 4/9/21 Fri 4/9/21 196 MEP/FINISHES RESTORATION PHASE 360 days? Mon 4/12/21 Thu 9/15/22 199 CORE PHASE 90 days? Mon 4/12/21 Tue 8/17/21 202 BATHROOMS PHASE 200 days? Mon 4/12/21 Fri 1/28/22 205 EAST STAIRWELL PHASE 180 days? Mon 4/12/21 Wed 12/29/21 208 WEST STAIRWELL PHASE 170 days? Thu 12/30/21 Wed 8/31/22 211 Substantial Completion (STRUCT/SEISMIC) 0 days Thu 9/15/22 Thu 9/15/22 212 DB-S_N (NOAA TI) CONSTRUCTION PHASE 115 days? Fri 2/4/22 Wed 7/20/22 220 Substantial Completion (NOAA TI) 0 days Wed 7/20/22 Wed 7/20/22 221 SUBSTANTIAL COMPLETION (SCD) - DB-S_N (STRUCT_NOAA) 0 days Thu 9/15/22 Thu 9/15/22 222 NOAA FF&E (NOAA Tenant Responsibility Items) 30 days Thu 7/28/22 Thu 9/8/22 228 NOAA TI Build-out / FF&E COMPLETE 0 days Thu 9/8/22 Thu 9/8/22 229 DB-S_N (STRUCT_NOAA) CONSTRUCTION CLOSEOUT PHASE 20 days Fri 9/16/22 Fri 10/14/22 235 DB-S_N (STRUCT_NOAA) FINANCIAL/CONTRACTUAL CLOSE-OUT 35 days Mon 10/17/22 Wed 12/7/22 238 DB-S_N (STRUCT_NOAA) PROJECT COMPLETION 0 days Wed 12/7/22 Wed 12/7/22

1/20 12/1

12/30 9/1

12/1

10/5

1/23

8/28

12/31

5/16

7/8

12/9

4/8 12/9

5/14

9/15

7/20 9/15

9/8

12/7

Apr '19May '19Jun '19Jul '19Aug '19Sep '19Oct '19Nov '19Dec '19Jan '20Feb '20Mar '20Apr '20May '20Jun '20Jul '20Aug '20Sep '20Oct '20Nov '20Dec '20Jan '21Feb '21Mar '21Apr '21May '21Jun '21Jul '21Aug '21Sep '21Oct '21Nov '21Dec '21Jan '22Feb '22Mar '22Apr '22May '22Jun '22Jul '22Aug '22Sep '22Oct '22Nov '22Dec '22Jan '23Feb '

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

Project: 911 FB COMBO PROJECT M Date: Mon 2/17/20