About this file

This document is a Pre-Proposal Conference Presentation outlining the HUB Subcontracting Plan (HSP) requirements for the Texas Workforce Commission (TWC) special trade contracts. The presentation addresses mandatory HSP submission requirements for all proposers, with a courtesy review deadline of Friday, January 16, 2026, at 5:00 P.M. CST. The TWC has established an 8.23% HUB subcontracting goal for all special trade contracts. The HSP is a pass/fail element, meaning proposers that fail to include an HSP will be rejected and not evaluated. Proposers may satisfy HSP requirements through three methods: Method A involves utilizing only VetHUB subcontractors to meet or exceed the 8.23% goal; Method B requires notifying at least three Texas VetHUB certified vendors for each subcontracted service or good at least nine days prior to proposal submission, along with notification to two trade and development centers, and providing justification for any non-VetHUB vendor selection; or Self-Performing, where the prime contractor furnishes all work using its own resources and employees.

Key compliance requirements include verification that all Texas VetHUB vendors maintain active (A) certification status on the solicitation due date, with certification expiration prior to that date resulting in HSP rejection. Proposers must provide supporting documentation of good faith efforts to notify HUB vendors and include contractor VID/TIN numbers, approximate dollar amounts, and percentage representations for each subcontractor. If awarded, the prime contractor must submit monthly Progress Assessment Reports (PAR) to TWCHUBInfo@twc.texas.gov before the fifth of each month as a condition of payment, along with invoices. Any modifications to the HSP after contract award require prior written approval from the TWC HUB department, with failure to comply constituting a breach of contract and potential debarment from all state contracting. VetHUB vendor lists are available through the Centralized Master Bidders List (CMBL) at the CPA website.

View the file

Other files

File Type Posted
ESBD_474660_1767973649582_Form 7- HUB Subcontracting Plan.pdf PDF
ESBD_474660_1770408135871_Attachment D-Questions and Answers.pdf PDF
ESBD_474660_1767975765005_RFP-3202600095 Solicitation.pdf PDF
ESBD_474660_1770642060524_Addendum 4 Notice-3202600095.pdf PDF
ESBD_474660_1768332630978_Addendum 1 Notice-320260095.docx DOCX document
ESBD_474660_1767973310183_Attachment 4-Proposal Submission Checklist.docx DOCX document
ESBD_474660_1770408136127_Addendum 3 Notice-3202600095.pdf PDF
ESBD_474660_1767973257835_Attachment 2- Uniform General Conditions.pdf PDF
ESBD_474660_1767973344457_Attachment 5- Supplementary General Conditions .docx DOCX document
ESBD_474660_1767973672884_TWC Procurement Portal Instructions to Respondents.docx DOCX document
ESBD_474660_1767973550443_Form 3- Past Project Performance.pdf PDF
ESBD_474660_1767973672884_Attachment 7- Project Drawings.pdf PDF
ESBD_474660_1767973424005_Attachment 10- HSP SubContracting Plan Guide.pdf PDF
ESBD_474660_1767973399390_Attachment 9- Asbestos Documents.pdf PDF
ESBD_474660_1767973625174_Form 6-Substitute W-9.docx DOCX document
ESBD_474660_1767973507164_Form 1- Execution of Response.docx DOCX document
ESBD_474660_1767973449199_Attachment 11- Overview of PAR.pdf PDF
ESBD_474660_1767973378991_Attachment 6- Prevailing Wage Scale.pdf PDF
ESBD_474660_1768501707252_Attachment A- Preproposal Sign in Sheet.pdf PDF
ESBD_474660_1767973486708_Attachment 13- Substitute W-9 Instructions.pdf PDF
ESBD_474660_1767973276170_Attachment 3-Evaluation Scoring Matrix.docx DOCX document
ESBD_474660_1767973467840_Attachment 12- Progress Assessment Report.xls XLS spreadsheet
ESBD_474660_1767973569557_Form 4-Financial Questionnaire.docx DOCX document
ESBD_474660_1767973588477_Form 5-Title Page.pdf PDF
ESBD_474660_1767973531424_Form 2 - Cost Proposal .docx DOCX document
ESBD_474660_1767973672884_Attachment 8- Project Manual.pdf PDF
ESBD_474660_1768501809858_Attachment C- Updated Form 7 - HSP.pdf PDF
ESBD_474660_1767973160748_Attachment 1- T&C Architect & Engineer Version (12-18-2025).pdf PDF
ESBD_474660_1768501680323_Addendum 2 Notice-3202600095.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HUB SUB-

CONTRACTING

PLAN OVERVIEW

PRE-BID CONFERENCE

KEY NOTES - HUB SUBCONTRACTING PLAN (HSP)

* HSP COURTESY REVIEW DEADLINE IS FRIDAY, JANUARY 16, 2026, 5:00 P.M CST. HIGHLY ENCOURAGED IF THERE ARE

ANY QUESTIONS.

* TWC HUB SUBCONTRACTING GOAL IS 8.23% FOR ALL SPECIAL TRADE CONTRACTS

* ALL PROPOSERS MUST SUBMIT AN HSP WITH THEIR PROPOSAL

* IT IS A PASS/FAIL ELEMENT, A PROPOSER THAT DOES NOT INCLUDE AN HSP WILL BE REJECTED

AND WILL NOT BE EVALUATED.

* IT’S A WIN-WIN! FOR THE AGENCY, THE PRIME VENDOR AND THE HUB VENDORS

TO MEET OR EXCEED THE SET GOAL

COMPLETING THE HUB

SUBCONTRACTING

PLAN (HSP)

HSP - QUICK CHECK LIST

• DETERMINATION OF GOOD FAITH METHOD (GFE)

• IDENTIFIES SECTIONS NEEDED TO BE COMPLETED

• RESPONDENT’S SUBCONTRACTING INTENTIONS

METHOD A-COMPLETING THE HSP

*Method A - Prime Vendor

• Utilize only VetHUB subcontractors or aggregate percentage of the contract to be performed, and will meet or exceed the agency goal, 8.23%

• Texas VetHUB vendors must have an active (A) certification on the date the solicitation is due. If the vendor’s VetHUB certification expires before the solicitation due date the HSP will be rejected as a failure to comply with the Good Faith Effort (GFE)

• Affirmation must be signed and dated by the responsible respondent.

METHOD B- COMPLETING THE HSP

* Method B –Prime Vendor

* Must notify at least three (3) Texas VetHUB certified vendors for each service/goods sub-contracted;

* Submit notification to VetHUB vendors and two (2) trade and/or development centers at least nine (9) days prior to submitting your response;

• The date of notification to the HUB vendors and two trade/development centers does not count in the 7-day notification period as set forth in the HSP.

* Submit supporting documentation (i.e., email, fax, certified mail) demonstrating good faith effort to notify Texas HUBs.

* Texas VetHUB vendors must have an active (A) certification on the date the solicitation is due. If the vendor’s VetHUB certification expires before the solicitation due date the HSP will be rejected as a failure to comply with the Good Faith Effort (GFE).

* Provide Justification for selection of a Non-VetHUB vendor(s)

REMINDERS AND USEFUL INFORMATION _COMPLETING THE

HUB SUBCONTRACTING PLAN (HSP)

Method B

* Locate a list of HUB subcontractors on the Centralized Master Bidders List (CMBL) at the CPA website https://mycpa.cpa.state.tx.us/tpasscmblsearch/tpasscmblsearch.do.

* Texas HUB vendors must have active (A) certification on date the solicitation is due.

* Identify all sub-contractors intended for the project

• Provide the contractor VID#/TIN#; Approximate dollar amount; and the percentage the amount represents for each subcontractor utilized

• Trade organizations and development centers may be found Texas Comptrollers website http://www.window.state.tx.us/procurement/prog/hub/mwb-links-1 . A list of trade and developments organizations is attached to the HSP form. You are not limited to using these organizations on the list.

* Affirmation must be signed and dated by the responsible respondent. Failure to sign could disqualify the submittal.

https://mycpa.cpa.state.tx.us/tpasscmblsearch/tpasscmblsearch.do http://www.window.state.tx.us/procurement/prog/hub/mwb-links-1

SELF- PERFORMING _ COMPLETING THE HUB

SUBCONTRACTING PLAN (HSP)

* Self Performing is if you will not be sub-contracting any portion of the contract

* Section 3 Self Performing Justification:

• Must provide a thorough explanation of how you will be fulfilling all aspects of the contract.

• How you will utilize all of your own resources, i.e., equipment, supplies, material, and/or employees. You cannot claim self-performance for individuals that receive a 1099, unlike your employees who receive W2’s.

* Section – Affirmation must be signed and dated by the responsible respondent

PAR’S _PROGRESS ASSESSMENT REPORT & OTHER

REMINDERS

* By signing the affirmation:

• “Respondent understands if awarded any portion of the contract: The Prime Contractor must submit monthly compliance reports

(Progress Assessment Report (PAR) to the agency verifying its compliance with the HSP. PAR is required as a condition of payment along with the invoice. “

• Must be emailed to TWCHUBInfo@twc.texas.gov and is due before the 5th of each month.

* Modifications to the HSP after award –

• Respondent must contact TWC HUB department prior to making any modifications to the HSP. The HUB department must approve any modification before the vendor may act upon them. Failure to adhere to these requirements is a breach of contract and include a debarment from all state contracting!

* Questions on the HUB component please contact Patricia Campos or Sonya Thulin at the following:

TWCHUBINFO@twc.texas.gov https://twcgov.sharepoint.com/sites/BusOPS/pcs/procurement-services/Shared%20Documents/HUB/HUB_HSP/PRE%20BID%20CONFERENCE/TWCHUBInfo@twc.texas.gov mailto:TWCHUBinfo@twc.texas

HUB Sub-contracting planoverview
��key notes - HUB Subcontracting Plan (HSP)�* HSP Courtesy Review deadline is Friday, January 16, 2026, 5:00 P.M CST. Highly encouraged if there are any questions. ��* TWC HUB subcontracting goal is 8.23% for all special trade contracts��* All proposers must submit an HSP with their proposal��* It is a Pass/Fail element, A proposer that does not include an HSP will be rejected � and will not be evaluated.��* It’s a Win-Win! for the agency, the prime vendor and the HUB vendors �to meet or exceed the set Goal��
Completing the HUB Subcontracting Plan (HSP)�
METHOD a-Completing the HSP
Method B- Completing the HSP�
Reminders and useful information _Completing the HUB Subcontracting Plan (HSP)�
Self- Performing _ Completing the HUB Subcontracting Plan (HSP)�
PAR’S _Progress assessment Report & Other Reminders

File details come from the government source that posted it. Updated .