ESBD_474660_1767973672884_Attachment 8- Project Manual.pdf

PDF 4 MB Posted

Attached to
Fort Worth 1st Floor Restroom Renovation
Solicitation number
3202600095
Issued by
Tarrant County, Texas

About this file

Project Manual Summary

This is a comprehensive project manual prepared by the Texas Workforce Commission (TWC) and Baird Hampton & Brown engineering firm for the renovation of the first-floor restrooms at the TWC Telecenter located at 307 W 13th Street, Fort Worth, Texas. The project encompasses selective demolition, installation of new plumbing fixtures, mechanical systems, electrical work, interior finishes including gypsum board assemblies, ceramic tile, acoustical ceilings, and associated architectural elements such as hollow metal frames, flush wood doors, and hardware. The project manual specifies detailed technical requirements across 50+ specification divisions covering products, materials, workmanship standards, and execution procedures. The contract document is structured as a single prime contract based on total bid price plus allowances, with the contractor responsible for all labor, materials, equipment, and compliance with applicable codes including the National Electrical Code, plumbing codes, mechanical codes, and Texas Accessibility Standards.

The specifications require strict adherence to industry standards including ASTM, ANSI, SMACNA, ASHRAE, and NFPA guidelines, with all materials UL-listed and manufacturer-approved. The contractor must obtain all necessary permits and inspections at its own cost, coordinate work with existing building operations that will continue during construction, maintain weather protection, implement comprehensive quality assurance procedures including testing and balancing of systems, and provide one-year warranty coverage on all materials and labor. The project specifies mandatory preconstruction meetings, monthly progress meetings, detailed shop drawing submittals for review, and final commissioning services per the 2015 International Energy Conservation Code requirements. No specific budget figures, bid opening dates, or contract award dates are included in this manual document; those details appear in separate solicitation documents referenced throughout the specifications.

View the file

Other files

File Type Posted
ESBD_474660_1767973649582_Form 7- HUB Subcontracting Plan.pdf PDF
ESBD_474660_1768501789909_Attachment B - Preproposal Conference Presentation.pdf PDF
ESBD_474660_1770408135871_Attachment D-Questions and Answers.pdf PDF
ESBD_474660_1767975765005_RFP-3202600095 Solicitation.pdf PDF
ESBD_474660_1770642060524_Addendum 4 Notice-3202600095.pdf PDF
ESBD_474660_1768332630978_Addendum 1 Notice-320260095.docx DOCX document
ESBD_474660_1767973310183_Attachment 4-Proposal Submission Checklist.docx DOCX document
ESBD_474660_1770408136127_Addendum 3 Notice-3202600095.pdf PDF
ESBD_474660_1767973257835_Attachment 2- Uniform General Conditions.pdf PDF
ESBD_474660_1767973344457_Attachment 5- Supplementary General Conditions .docx DOCX document
ESBD_474660_1767973672884_TWC Procurement Portal Instructions to Respondents.docx DOCX document
ESBD_474660_1767973550443_Form 3- Past Project Performance.pdf PDF
ESBD_474660_1767973672884_Attachment 7- Project Drawings.pdf PDF
ESBD_474660_1767973424005_Attachment 10- HSP SubContracting Plan Guide.pdf PDF
ESBD_474660_1767973467840_Attachment 12- Progress Assessment Report.xls XLS spreadsheet
ESBD_474660_1767973569557_Form 4-Financial Questionnaire.docx DOCX document
ESBD_474660_1767973588477_Form 5-Title Page.pdf PDF
ESBD_474660_1767973531424_Form 2 - Cost Proposal .docx DOCX document
ESBD_474660_1768501809858_Attachment C- Updated Form 7 - HSP.pdf PDF
ESBD_474660_1767973160748_Attachment 1- T&C Architect & Engineer Version (12-18-2025).pdf PDF
ESBD_474660_1768501680323_Addendum 2 Notice-3202600095.docx DOCX document
ESBD_474660_1767973399390_Attachment 9- Asbestos Documents.pdf PDF
ESBD_474660_1767973625174_Form 6-Substitute W-9.docx DOCX document
ESBD_474660_1767973507164_Form 1- Execution of Response.docx DOCX document
ESBD_474660_1767973449199_Attachment 11- Overview of PAR.pdf PDF
ESBD_474660_1767973378991_Attachment 6- Prevailing Wage Scale.pdf PDF
ESBD_474660_1768501707252_Attachment A- Preproposal Sign in Sheet.pdf PDF
ESBD_474660_1767973486708_Attachment 13- Substitute W-9 Instructions.pdf PDF
ESBD_474660_1767973276170_Attachment 3-Evaluation Scoring Matrix.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

Texas Workforce Commission

Fort Worth 1st Floor Restrooms 307 W 13th. St.

Fort Worth, TX 76102

RFP: 3202600095

January 5, 2026

ELEMENTS PROJECT NO. 25-1018.00

OWNER TEXAS WORKFORCE COMMISSION

101 East 15th Street

Austin, Texas 78778 512.463.7486

ARCHITECT ELEMENTS OF ARCHITECTURE, INC.

1201 6th Avenue, Suite 100

Fort Worth, TX 76104 817.333.2880

MEP ENGINEERING BAIRD HAMPTON & BROWN

6300 Ridglea Place, Suite 700

Fort Worth, TX 76116 817-338-1277

01/05/2026

TWC – Fort Worth 1st Floor Restrooms 00 0110 - 1 TABLE OF CONTENTS

SECTION 00 0110

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01 1000 Summary

01 2000 Price and Payment Procedures

01 2100 Allowances

01 3000 Administrative Requirements

01 3546 Indoor Air Quality Management

01 3553 Security Procedures

01 4000 Quality Requirements

01 5000 Temporary Facilities and Controls

01 5500 Vehicular Access and Parking

01 6000 Product Requirements

01 7000 Execution and Closeout Requirements

01 7329 Cutting and Patching

01 7419 Construction Waste Management

01 7700 Closeout Procedures

DIVISION 02 – EXISTING CONDITIONS

02 4119 Selective Demolition

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 1000 Rough Carpentry

06 4100 Architectural Wood Casework

DIVISION 08 – OPENINGS

08 1113 Hollow Metal Frames

08 1416 Flush Wood Doors

08 7100 Door Hardware

08 7713 Automatic Door Openers

DIVISION 09 – FINISHES

09 2116 Gypsum Board Assemblies

09 3000 Tiling

09 5100 Acoustical Ceilings

09 6513 Resilient Base

09 6813 Tile Carpeting

09 9000 Paints and Coatings

TWC – Fort Worth 1st Floor Restrooms 00 0110 - 2 TABLE OF CONTENTS

DIVISION 10 – SPECIALTIES

10 2116 Plastic Toilet Compartments

10 2800 Toilet Accessories

DIVISION 12 – FURNISHINGS

12 3600 Countertops

DIVISION 22 - PLUMBING

22 0010 Basic Plumbing Requirements

22 0506 Plumbing Demolition

22 0512 Plumbing and Electrical Coordination

22 0529 Plumbing Supports and Anchors

22 0593 Plumbing Testing, Adjusting and Balancing

22 0716 Plumbing Piping Insulation

22 1000 Plumbing Piping

22 1001 Plumbing Specialties

22 1119 Piping Specialties

22 4001 Plumbing Fixtures

DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 0010 Basic Mechanical Requirements

23 0506 Mechanical Demolition

23 0512 Mechanical and Electrical Coordination

23 0529 Mechanical Supports and Anchors

23 0553 Mechanical Identification

23 0593 Mechanical Testing, Adjusting and Balancing

23 0713 Hvac Duct Insulation

23 3113 Metal Ductwork

23 3113.19 Ductwork Accessories

23 3713 Air Outlets and Inlets

DIVISION 26 - ELECTRICAL

26 0510 General Requirements For Electrical Work

26 0511 Work In Existing Building

26 0512 Mechanical And Electrical Coordination

26 0519 Wires And Cables

26 0520 Wire Connection And Devices

26 0526 Grounding

26 0527 Sealing Of Penetrations

26 0529 Supporting Devices

26 0532 Pull And Junction Boxes

TWC – Fort Worth 1st Floor Restrooms 00 0110 - 3 TABLE OF CONTENTS

26 0533 Conduits

26 0534 Outlet Boxes

26 2726 Wiring Devices

26 5113 Lighting

DIVISION 27 - COMMUNICATIONS

27 0528 Empty Conduit Systems

END OF TABLE OF CONTENTS

TWC – Fort Worth 1st Floor Restrooms 01 1000-1 SUMMARY

SECTION 01 1000

SUMMARY

PART 1 - GENERAL

1.01 PROJECT

A. Project Name: Texas Workforce Commission – Fort Worth 1st Floor Restrooms

B. Owner’s Name: Texas Workforce Commission, Procurement and HUB Services 101 East 15th Street, Room 316T Austin, Texas 78778-001

C. Architect’s Name: Elements of Architecture, Inc.

1201 6th Avenue. Suite 100 Fort Worth, Texas 76104

1.02 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on the total bid price plus the allowance if any as noted in the TWC solicitation.

1.03 DESCRIPTION OF WORK

A. Scope of work to include the renovations of existing restrooms and break room at the first floor in the TWC Telecenter in Fort Worth, TX.

1.04 COMPLIANCE WITH ACCESSIBILITY STANDARDS

A. The renovations shall be fully accessible to the disabled and handicapped in compliance with the State and Federal accessibility standards.

1. The Elimination of Architectural Barriers, Texas Department of Licensing and Regulation.

2. The American with Disabilities Act, U.S. Department of Transportation.

1.05 OWNER OCCUPANCY

A. Texas Workforce Commission intends to continue to occupy all portions of the existing building during the entire construction period.

B. All work shall be limited to after normal business hours and weekends unless previous arrangements are made with the Architect and with the Texas Workforce Commission.

C. Texas Workforce Commission intends to occupy the Project upon Substantial Completion.

D. Cooperate with Texas Workforce Commission to minimize conflict and to facilitate Texas Workforce Commission’s operations.

E. Schedule the Work to accommodate Texas Workforce Commission occupancy.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: The contractor shall confine his operations and personnel to the area within the limits of construction as shown on the drawings and the direct route from the construction area to the exterior or the designated staging area.

B. The contractor shall be allowed to use the Owner’s restroom facilities.

C. Staging: Texas Workforce Commission may designate an area for staging of the contractor’s material and equipment. The same staging area may by utilized by other contractors on the project. Contractors are to coordinate the storage of their materials and equipment with each other and cooperate in the use of the staging area. The shall confine their staging and storage to the area designed by Texas Workforce Commission. The staging area shall be kept clean and orderly at all times.

D. Arrange use of site and premises to allow:

1. Texas Workforce Commission occupancy.

2. Work by other contractors.

3. Work by Texas Workforce Commission.

E. Provide access to and from site as required by law and by Texas Workforce Commission:

TWC – Fort Worth 1st Floor Restrooms 01 1000-2 SUMMARY

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

F. Existing building spaces may not be used for storage unless owner allows otherwise.

G. Time Restrictions:

1. All work shall be limited to after normal business hours and weekends.

H. Utility Outages and Shutdown:

1. Limit disruption of utility services to hours the building is unoccupied.

2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Texas Workforce Commission and authorities having jurisdiction.

3. Limit shutdown of utility services to 10 hours at a time, arranged at least 24 hours in advance with Texas Workforce Commission.

4. Prevent accidental disruption of utility services to other facilities.

5. At the end of the construction project, the contractor shall leave the building and grounds in the same condition as before the work began.

1.07 WORK SEQUENCE

A. Contractor will establish work sequence for Texas Workforce Commission’s approval. Work sequence shall provide for full occupancy during normal work hours such that building systems are operational and do not disrupt business operations.

PART 2 - PRODUCTS - NOT USED

PART 3 - EXECUTION - NOT USED

END OF SECTION

TWC – Fort Worth 1st Floor Restrooms 01 2000-1 PRICE AND PAYMENT PROCEDURES

SECTION 01 2000

PRICE AND PAYMENT PROCEDURES

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Describes the form for the Contractor’s Schedule of Values.

C. Change procedures.

D. Procedures for preparation and submittal of application for final payment.

1.02 RELATED REQUIREMENTS

A. Contract Documents defined in Division 0

B. Section 01 2100 – Allowances: Payment procedures related to allowances.

C. Section 01 3000 – Administrative Requirements related to progress schedule.

D. Section 01 7000 – Execution and Closeout Requirements related to close out procedures.

1.03 SCHEDULE OF VALUES

A. Forms filled out by hand will not be accepted.

B. Submit a printed schedule on AIA Form G703 – Application and Certificate for Payment Continuation Sheet. Contractor’s standard form or electronic media printout will be considered.

C. Submit Schedule of Values in duplicate within 7 days after date of Notice to Proceed.

D. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification Section. Identify site mobilization.

E. Revise schedule to list approved Change Orders, with each Application For Payment.

1.04 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Once each calendar month based on the work performed the prior calendar month.

B. Forms filled out by hand will not be accepted.

C. Present required information in typewritten form.

D. Form: AIA G702 Application and Certificate for Payment and AIA G703 Continuation Sheet, including continuation sheets when required.

E. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

3. Scheduled Values.

4. Previous Applications.

5. Work in Place and Stored Materials under this Application.

6. Authorized Change Orders.

7. Total Completed and Stored to Date of Application.

8. Percentage of Completion.

9. Balance to Finish.

10. Retainage.

F. Execute certification by signature of authorized officer.

G. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

H. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of Work.

I. Submit three copies of each Application for Payment to Architect.

TWC – Fort Worth 1st Floor Restrooms 01 2000-2 PRICE AND PAYMENT PROCEDURES

J. Each Application for Payment shall be accompanied by an Invoice on Company Letterhead, and Affidavit of Bills Paid (except the first application) and a Texas Workforce Commission HUB Progress Assessment Report.

K. When Architect requires substantiating information, submit data justifying dollar amounts in question.

Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

L. Each Application for Payment shall be accompanied with the construction progress schedule, revised and current.

M. When Architect requires substantiating information, submit data justifying dollar amounts in question.

Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

1.05 MODIFICATION PROCEDURES

A. Refer to solicitation for instructions on changes to the contract.

B. After execution of Change Order, promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Price.

C. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

D. Promptly enter changes in Project Record Documents.

1.06 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Price, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 01 7000.

2. All items noted on the Final In section Report have been completed to the satisfaction of Texas

Workforce Commission and the Architect.

3. Submittal of Certificate of Substantial Completion, AIA Document G704

4. Submittal of Contractor’s Affidavit of Payment of Debts and Claims, AIA Document G706

5. Submittal of Affidavit of Release of Liens, AIA Document G707

6. Submittal of final HUB Progress Report

7. Submittal of all warrantied/guaranties as required by other sections

8. Submittal of Consent of Surety to Final Payment

9. Operations and Maintenance manuals for all equipment as required by other sections

10. Execution and submittal of Texas Workforce Commission’s Statement of Non-Inclusion of Asbestos

Containing Materials (ACM)

11. Submittal of rebates as defined within each section as applicable for the project. If undefined, provide documentation of applicable rebates that Texas Workforce Commission may qualify for.

TWC – Fort Worth 1st Floor Restrooms 01 2100-1 ALLOWANCES

SECTION 01 2100

ALLOWANCES

PART 1 - GENERAL

1.01 SUMMARY

A. Section Includes:

1. Contingency allowance.

B. Related Sections

1. Section 01 2000 – Price and Payment Procedures.

1.02 CONTINGENCY ALLOWANCE

A. A Contingency Allowance as noted and defined within the TWC solicitation shall be included in the bid price for the use by Texas Workforce Commission at their discretion for items, labor or assemblies that they may want to incorporate into the project.

B. Contractor’s costs for products, delivery, installation, labor, insurance, payroll, taxes, bonding, equipment rental, overhead and profit will be included in Change Orders authorizing expenditure of funds from this Contingency Allowance.

C. Funds will be drawn from Contingency Allowance only by Change Order and at the direction of Texas Workforce Commission.

D. At closeout of Contract, funds remaining in Contingency Allowance will be credited to Texas Workforce Commission by Change Order.

1.03 ALLOWANCE SCHEDULE

A. Contingency Allowance: Include the stipulated sum/price of as noted in the solicitation for use upon Owner’s instructions.

TWC – Fort Worth 1st Floor Restrooms 01 3000-1 ADMINISTRATIVE REQUIREMENTS

SECTION 01 3000

ADMINISTRATIVE REQUIREMENTS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Preconstruction meeting.

B. Progress meetings.

C. Construction progress schedule.

D. Submittals for review, information, and project closeout.

E. Number of copies of submittals

F. Submittal procedures.

1.02 RELATED REQUIREMENTS

A. Section 01 1000 - Summary: Stages of the Work.

B. Section 01 7000 - Execution and Closeout Requirements: Additional coordination requirements.

C. Section 01 7800 - Closeout Submittals: Project record documents.

1.03 PROJECT COORDINATION

A. Project Coordinator: Project Manager as designated by Texas Workforce Commission.

B. Cooperate with the Project Coordinator in allocation of mobilization areas of site; for field offices and sheds, for access, traffic, and parking facilities.

C. During construction, coordinate use of site and facilities through the Project Coordinator.

D. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.

E. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities.

F. Coordinate field engineering and layout work under instructions of the Project Coordinator.

G. Make the following types of submittals to Architect through the Project Coordinator:

1. Requests for interpretation.

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Manufacturer's instructions and field reports.

6. Applications for payment and change order requests.

7. Progress schedules.

8. Coordination drawings.

9. Closeout submittals.

PART 2 - PRODUCTS - NOT USED

PART 3 - EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Texas Workforce Commission will schedule a meeting after Notice of Intent to Award.

B. Attendance Required:

1. Texas Workforce Commission

2. Architect.

3. All contractors and subcontractors on the project.

4. Any other major sub Contractors.

C. Agenda:

TWC – Fort Worth 1st Floor Restrooms 01 3000-2 ADMINISTRATIVE REQUIREMENTS

1. Execution and distribution of Texas Workforce Commission Purchase Order and Notice to Proceed to Contractor.

2. Distribution of Contract Documents.

3. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

4. Designation of personnel representing the parties to Contract, Owner, Contractor and Architect.

5. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

6. Scheduling.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Texas Workforce Commission, participants, and those affected by decisions made.

3.02 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals.

B. Attendance Required: Job superintendent, major Subcontractors and suppliers, Texas Workforce Commission, Architect, as appropriate to agenda topics for each meeting.

C. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Texas Workforce Commission, participants, and those affected by decisions made.

3.03 CONSTRUCTION PROGRESS SCHEDULE

A. The contract period is established by the Owner as an outside limit for completion of the work, however time is of the essence in the completion of this work and the contractor should make every reasonable effort to expedite the work in order to complete the work before the scheduled contract date.

B. A complete construction progress schedule must be submitted within seven days after the Notice to Proceed is issued for the project.

C. Submit an updated schedule with each new Application for Payment.

3.04 PROGRESS PHOTOGRAPHS

A. Submit photographs with each application for payment, taken not more than 3 days prior to submission of application for payment.

B. Photography Type: Digital; electronic files.

C. Provide photographs of site and construction throughout progress of Work produced by a competent photographer, acceptable to Architect.

D. Views:

1. Provide non-aerial photographs from four cardinal views at each specified time, until Date of

Substantial Completion.

2. Consult with Architect for instructions on views required.

3. Provide factual presentation.

4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

TWC – Fort Worth 1st Floor Restrooms 01 3000-3 ADMINISTRATIVE REQUIREMENTS

E. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: Via email.

2. File Naming: Include project identification, date and time of view, and view identification.

3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.

4. Hard Copy: Printed hardcopy (grayscale) of PDF file and point of view sketch.

3.05 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

C. Samples will be reviewed only for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 7800 - CLOSEOUT

SUBMITTALS.

E. Submittals which require color selections or substitutions shall be submitted as early as possible to prevent delays in the work.

3.06 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Submit for Architect's knowledge as contract administrator or for Texas Workforce Commission. No action will be taken.

3.07 SUBMITTALS FOR PROJECT CLOSEOUT

A. When the following are specified in individual sections, submit them at project closeout:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Documents for Final Payment as listed in Section 01 2000 Price and Payment Procedures.

6. Other types as indicated.

B. Submit for Texas Workforce Commission’s benefit during and after project completion.

C. Submit the following to Architect for transmittal to Texas Workforce Commission:

1. An affidavit that all payrolls, bills for materials and equipment, and other indebtedness connected with the work for which Texas Workforce Commission or his property might in any way be responsible, have been paid or otherwise satisfied.

2. Consent of surety to Final Payment.

3. Data establishing payment or satisfaction of all such obligations, such as receipts, releases and waivers of claims arising out of the Contract, to the extent and in such form as may be designated by Texas Work Force Commission.

3.08 NUMBER OF COPIES OF SUBMITTALS

A. Documents for Review:

TWC – Fort Worth 1st Floor Restrooms 01 3000-4 ADMINISTRATIVE REQUIREMENTS

1. Small Size Sheets, Not Larger Than 8-1/2 x 11 inches: Submit the number of copies that Contractor requires, plus two copies that will be retained by Architect.

2. Larger Sheets, Not Larger Than 24x36 inches: Submit the number of copies that the Contractor requires, plus two copies that will be retained by the Architect.

B. Documents for Information: Submit two copies.

C. Documents for Project Closeout: Make one reproduction of submittal originally reviewed. Submit one extra of submittals for information.

D. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.09 LOGGING AND NUMBERING

A. The Contractor shall keep a “submittal log” detailed enough for tracking and identifying each Submittal and indicating the dates of submission and returns.

B. Identify all submittals according to the CSI Division format and number consecutively in the order submitted. Accompany each with a letter of transmittal containing all pertinent information required for identification.

3.10 SUBMITTAL PROCEDURES

A. The Contractor shall review submittals for Conformation to the Contract Documents in quality, quantity, design and dimension before sending to the Architect for review.

B. Transmit each submittal with AIA Form G810.

C. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.

D. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate on each copy.

E. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.

F. Deliver submittal to Architect at business address.

G. Schedule submittals to expedite the Project, and coordinate submission of related items.

H. For each submittal for review, allow 15 days excluding delivery time to and from the Contractor.

I. Identify variations from Contract Documents and Product or system limitations that may be detrimental to successful performance of the completed Work.

J. Provide space for Contractor and Architect review stamps.

K. When revised for resubmission, identify all changes made since previous submission.

L. Distribute reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

M. Submittals not requested will not be recognized or processed.

3.11 OPERATING AND MAINTENANCE MANUALS

A. On or before the date of Substantial Completion, the Contractor shall submit two (2) copies of the Operating and Maintenance Manuals for Texas Workforce Commission’s use. The manuals are to include all approved submittals, operating instructions on all equipment, and maintenance information including parts lists, services manuals (if furnished), and relevant schematic or control diagrams and cleaning instructions for installed finishes.

B. Include as-built drawings with O&M manuals for Architect’s review.

TWC – Fort Worth 1st Floor Restrooms 01 3000-5 ADMINISTRATIVE REQUIREMENTS

TWC – Fort Worth 1st Floor Restrooms 01 3546-1 INDOOR AIR QUALITY MANAGEMENT

SECTION 01 3546

INDOOR AIR QUALITY MANAGEMENT

PART 1 - GENERAL

1.01 SUMMARY

A. Section Includes:

1. Indoor Air Quality Management Plan.

2. During construction:

a. Protection of heating, ventilating, and air conditioning systems.

b. Reducing emissions through source control.

c. Pathway interruption.

d. Housekeeping.

e. Scheduling.

3. Before occupancy:

a. Flush-out

b. Air testing.

1.02 REFERENCES

A. American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE) (www.ashrae.org)

52.2 - Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size.

B. Sheet Metal and Air Conditioning Manufacturer’s Association International (SMACNA) (www.smacna.org)

- IAQ Guidelines for Occupied Buildings Under Construction.

C. U.S. Green Building Council (USGBC) (www.usgbc.org) - Leadership in Energy and Environmental Design (LEED) 2009 - Green Building Rating System for New Construction and Major Renovations.

1.03 SUBMITTALS

A. Indoor Air Quality Management Plan:

1. Submit Indoor Air Quality Management Plan for review within seven days after date of Notice to

Proceed. Include:

a. Procedures for implementing requirements of SMACNA IAQ Guideline.

b. Substitution procedures for products that are responsibility of Contractor and proposed source control implementation measures to minimize building contamination.

c. Construction sequencing and storage plans for protection of stored on-site or installed absorptive materials against moisture absorption and contamination.

d. Filter media change schedule and Product Data for filters including MERV ratings.

e. Name and phone number of Contractor’s personnel responsible for instructing workers and overseeing and documenting results of Indoor Air Quality Management Plan.

2. Submit electronically in Adobe PDF format to Architect and Texas Workforce Commission.

3. If required, revise and resubmit plan within three days after receipt of comments.

4. Distribute copies of approved Indoor Air Quality Management Plan to concerned parties.

B. Photographs: Document indoor air quality management measures with date-stamped photographs including protection of ducts, on-site storage, and protection of installed absorptive materials.

C. Indoor Air Quality Testing Report showing results of air quality testing.

1.02 QUALITY ASSURANCE

A. Review and discuss Indoor Air Quality Management Plan implementation and progress at Preconstruction Conference and Progress Meetings.

1.03 DELIVERY, STORAGE AND HANDLING

B. Designate specific storage areas to facilitate protection of stored absorptive materials.

C. Clearly identify storage area. Keep clean and orderly; prevent contamination of materials.

D. Monitor storage areas for contamination; correct problems and implement preventative measures.

TWC – Fort Worth 1st Floor Restrooms 01 3546-2 INDOOR AIR QUALITY MANAGEMENT

1.04 TRAINING

A. Provide training of indoor air quality management methods to be used at appropriate stages of Project.

B. Require participation of all subcontractors.

PART 2 - PRODUCTS - NOT USED

PART 3 - EXECUTION

3.01 IMPLEMENTATION - DURING CONSTRUCTION

A. Meet or exceed SMACNA minimum requirements for heating, ventilating, and air conditioning system protection, source control, pathway interruption, housekeeping, and scheduling.

B. Protect stored on-site or installed absorptive materials from moisture damage and volatile organic compound contamination through construction sequencing and proper storage.

C. If air handlers are used during construction, use filtration media with Minimum Efficiency Reporting Value (MERV) of 8 per ASHRAE 52.2.

D. Replace filtration media just prior to occupancy.

E. Heating, Ventilating, and Air Conditioning System Protection:

1. Keep duct systems including supply air, return air, and exhaust air and associated equipment including air handlers, variable air volume boxes, silencers, fans, and filter boxes, clean and uncontaminated.

2. Seal taps and open ends not actively being worked on with plastic and tape.

3. Provide 1-inch polyester filter media over return and exhaust air inlets during construction and until

Substantial Completion.

4. Ensure that temporary and permanent filters are in place and openings are closed before running fans.

5. Protect existing heating, ventilating, and air conditioning systems with 1-inch polyester media installed over outside air intakes. Change out filter media on intakes to minimize pressure drops. Provide frequent filter change out to keep filter pressure drop at existing fan-coils below approximately 0.30 inch s.p.

F. Source Control:

1. For temporary and ancillary materials used in construction, follow requirements of similar products to minimize indoor air quality impacts.

2. Use nontoxic formulations and implement other control measures to minimize building contamination.

G. Pathway Interruption: Isolate areas where work is being performed to prevent contamination of clean and occupied spaces.

H. Housekeeping:

1. Implement cleaning activities concentrating on heating, ventilating, and air conditioning systems and building space to remove contaminants prior to occupancy.

2. Protect materials from weather and store in clean area prior to unpacking.

3. Clean coils, air filters, and fans before performing testing and balancing.

4. Provide temporary walkoff mats at entry points to construction areas; replace or clean daily.

I. Scheduling:

1. Sequence construction activities to reduce absorption of and volatile organic compounds by materials.

2. Complete applications of wet and odorous materials before installing absorptive materials.

3.02 IMPLEMENTATION - BEFORE OCCUPANCY

A. After completion of construction, prior to Owner occupancy, and after completion of interior finishes, perform building flush-out:

1. Supply total air volume of 14,000 CF of outdoor air per square foot of floor area.

2. Maintain minimum interior temperature of 60 degrees F and maximum relative humidity of 60 percent during flush-out.

TWC – Fort Worth 1st Floor Restrooms 01 3553-1 SECURITY PROCEDURES

SECTION 01 3553

SECURITY PROCEDURES

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Security measures including entry control, personnel identification, guard service, and miscellaneous restrictions.

B. Fire safety measures during construction.

1.02 RELATED REQUIREMENTS

A. Section 01 1000 - Summary: Use of premises and occupancy.

B. Section 01 5000 – Temporary Facilities and Controls: Temporary lighting.

1.03 SECURITY PROGRAM

A. Protect work, existing premises and Texas Workforce Commission’s operations from theft, vandalism, and unauthorized entry.

B. Initiate program in coordination with Texas Workforce Commission’s existing security system at project mobilization.

C. Maintain program throughout construction period until Texas Workforce Commission acceptance precludes the need for Contractor security.

D. Background checks and badging requirements apply to all personnel entering Texas Workforce Commission facilities.

1.04 ENTRY CONTROL

A. Restrict entrance of persons and vehicles into Project site and existing facilities.

B. Allow entrance only to authorized persons with proper identification.

C. Maintain log of workers and visitors, make available to Texas workforce Commission on request.

D. Texas Workforce Commission will control entrance of persons and vehicles related to Texas Workforce Commission’s operations.

E. Contractor personnel or subcontract personnel building access is restricted to the designated limits of construction. Workers found outside of the designated limits of construction will be subject to dismissal from the building.

1.05 PERSONNEL IDENTIFICATION

A. Refer to solicitation for specific requirements for personnel.

B. Badge will be provided to the project superintendent. Other personnel are not required to be badged.

C. Badge to Include: Personal photograph, name, expiration date and employer.

D. Maintain a list of accredited persons, submit copy to Texas Workforce Commission on request.

E. Require return of badges at expiration of their employment on the Work.

1.06 RESTRICTIONS

A. Do not allow cameras on site or photographs taken except by written approval of Texas Workforce Commission.

B. Contractor personnel or subcontract personnel will not be allowed access to the building or the work area unless the designated contractor superintendent is on-site.

1.07 SAFETY MEASURES

A. Contractor shall maintain a two hour “Fire Watch” during and after work utilizing welding, torch cutting, brazing or work where open flame or spark is present.

TWC – Fort Worth 1st Floor Restrooms 01 3553-2 SECURITY PROCEDURES

B. Contractor shall furnish fire extinguishers as required by OSHA.

PART 2 - PRODUCTS - NOT USED

PART 3 – EXECUTION – NOT USED

TWC – Fort Worth 1st Floor Restrooms 01 4000-1 QUALITY REQUIREMENTS

SECTION 01 4000

QUALITY REQUIREMENTS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Control of installation.

B. Tolerances.

C. Testing and inspection services.

D. Manufacturers' field services.

1.02 RELATED REQUIREMENTS

A. Section 01 3000 - Administrative Requirements: Submittal procedures.

B. Section 01 6000 - Product Requirements: Requirements for material and product quality.

1.03 REFRENCE STANDARDS

A. ASTM C1021 - Standard Practice for Laboratories Engaged in Testing of Building Sealants; 2008.

B. ASTM E329 - Standard Specification for Agencies Engaged Construction Inspection and/or Testing;

2011.

C. ASTM E543 - Standard Specification for Agencies Performing Nondestructive Testing; 2009.

1.04 SUBMITTALS

A. Design Data: Submit for Architect's knowledge as contract administrator for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents, or for Owner's information.

B. Test Reports: After each test/inspection, promptly submit two copies of report to Architect and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Conformance with Contract Documents.

k. When requested by Architect, provide interpretation of results.

C. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to Architect, in quantities specified for Product Data.

1. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

2. Certificated maybe recent or previous test results on material or product, but must be acceptable to Architect.

D. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the Texas Workforce Commission’s information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

E. Manufacturer's Field Reports: Submit reports for Architect's benefit as contract administrator or for Texas Workforce Commission.

1. Submit report in duplicate within 30 days of observation to Architect for information.

TWC – Fort Worth 1st Floor Restrooms 01 4000-2 QUALITY REQUIREMENTS

2. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.05 TESTING AND INSPECTION AGENCIES

A. Owner will employ services of an independent testing agency to perform certain specified testing;

payment for cost of services will be derived from allowance specified in Section 01 2100; see Section 01 2100 and applicable sections for description of services included in allowance.

B. Contractor shall employ and pay for services of an independent testing agency to perform other specified testing.

C. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

D. Contractor Employed Agency:

1. Testing agency: Comply with requirements of ASTM E329, ASTM E543, ASTM C1021, ASTM

C1077, and ASTM C1093.

2. Laboratory: Authorized to operate in Texas.

PART 2 - MATERIALS - NOT USED

PART 3 - EXECUTION

3.01 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in the sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Architect before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have Work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.02 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from Architect before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

3.03 TESTING AND INSPECTION

A. See individual specification sections for testing required.

B. Testing Agency Duties:

1. Test samples submitted by Contractor.

2. Provide qualified personnel at site. Cooperate with Architect and Contractor in performance of services.

3. Perform specified sampling and testing of products in accordance with specified standards.

4. Ascertain compliance of materials with requirements of Contract Documents.

5. Promptly notify Architect and Contractor of observed irregularities or non-conformance of Work or products.

6. Perform additional tests and inspections required by Architect.

7. Submit reports of all tests/inspections specified.

TWC – Fort Worth 1st Floor Restrooms 01 4000-3 QUALITY REQUIREMENTS

C. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

D. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify Architect and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

6. Arrange with Owner's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

E. Re-testing required because of non-conformance to specified requirements shall be performed by the same agency on instructions by Architect.

F. Re-testing required because of non-conformance to specified requirements shall be paid for by Contractor.

3.04 MANUFACTURERS’ FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to Architect 30 days in advance of required observations.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

3.05 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not conforming to specified requirements.

B. If, in the opinion of Architect, it is not practical to remove and replace the Work, Architect will direct an appropriate remedy or adjust payment.

TWC – Fort Worth 1st Floor Restrooms 01 5000-1 TEMPORARY FACILITIES AND CONTROLS

SECTION 01 5000

TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Temporary utilities.

B. Temporary sanitary facilities.

C. Temporary Controls: Barrier, enclosures, and fencing.

D. Security requirements.

E. Vehicular access and parking.

F. Waste removal facilities and services.

G. Field offices.

1.02 RELATED REQUIREMENTS

A. Section 01 5500 – Vehicular Access and Parking

B. Section 01 3553 – Security Procedures

1.03 TEMPORARY UTILITIES

A. The contractor may use the existing facility utilities and existing restrooms assigned for such use.

B. Use trigger-operated nozzles for water hoses, to avoid waste of water.

1.04 TEMPORARY SANITARY FACILITIES

A. Contractor will be allowed to use the Owner’s restroom facilities during the renovations.

B. Maintain daily in clean and sanitary condition.

1.05 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Provide barricades and covered walkways required by governing authorities for public rights-of-way and for public access to existing building.

C. Provide protection for plants designated to remain or in areas impacted by work. Replace damaged plants.

D. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.06 EXTERIOR ENCLOSURES

A. Provide temporary insulated weather tight closure of exterior openings to accommodate acceptable working conditions and protection for Products, to allow for temporary heating and maintenance of required ambient temperatures identified in individual specification sections, and to prevent entry of unauthorized persons. Provide access doors with self-closing hardware and locks.

1.07 INTERIOR ENCLOSUERS

A. Provide temporary partitions and ceiling as indicated to separate work areas from Texas Workforce Commission’s occupied areas to prevent penetration of dust and moisture into Texas Workforce Commission’s occupied areas, and to prevent damage to existing materials and equipment.

B. Construction: Framing and reinforced polyethylene sheet materials with closed joints and sealed edges at intersections with existing surfaces.

1.08 SECURITY (reference Section 01 3553)

A. Provide security and facilities to protect Work, existing facilities, and Texas Workforce Commission’s

TWC – Fort Worth 1st Floor Restrooms 01 5000-2 TEMPORARY FACILITIES AND CONTROLS operations from unauthorized entry, vandalism, or theft.

B. Coordinate with Texas Workforce Commission’s security program.

C. At the request of TWC, provide web-connected security cameras, minimum of 2 locations to be selected by Owner. Cameras to be web accessible for viewing online 24 hours per day, during the duration of the project.

D. Cameras to have recording capability; data to be archived and available to Owner.

1.09 VEHICULAR ACCESS PARKING (reference Section 01 5500)

A. Comply with regulations relating to use of streets and sidewalks, access to emergency facilities, and access for emergency vehicles.

B. Coordinate access and haul routes with governing authorities and Texas Workforce Commission.

C. Provide and maintain access to fire hydrants, free of obstructions.

D. Provide means of removing mud from vehicle wheels before entering streets.

E. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.

F. Existing parking areas located at the site and as designated by Texas Workforce Commission may be used for construction parking during hours when building is unoccupied.

1.10 WASTE REMOVAL (reference Section 01 7419)

A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.

B. Provide containers with lids. Remove trash from site periodically.

C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

D. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

E. Coordinate waste containers and waste removal with other projects to limit encumbering site with multiple containers and removal times.

1.11 SITE EXAMINATION

A. Location: The location of the proposed work is within the building. Confine the work area to those rooms, except as required by the Contract Documents to do work outside of that area.

B. Clean and repair damage caused by installation or use of temporary work.

TWC – Fort Worth 1st Floor Restrooms 01 5000-1 TEMPORARY FACILITIES AND CONTROLS

SECTION 01 5500

VEHICULAR ACCESS AND PARKING

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Parking

B. Existing pavements and parking areas.

C. Maintenance

D. Mud from site vehicles

1.02 RELATED REQUIREMENTS

A. Section 01 1000 – Summary; access to site, work sequence and occupancy.

B. Section 01 5000 – Temporary Facilities and Controls

PART 2 - PRODUCTS - NOT USED

PART 3 - EXECUTION

3.01 ACCESS ROADS

A. Use of designated existing on-site streets and driveways for construction traffic is permitted during hours when work is permitted.

B. Provide unimpeded access for emergency vehicles. Maintain 20 foot width driveways with turning space between and around combustible materials.

C. Provide and maintain access to fire hydrants free of obstructions.

3.02 PARKING

A. Use of designated areas of existing parking facilities by construction personnel is permitted during hours when building is unoccupied.

B. Vehicular traffic and parking on the surrounding surface parking deck is permitted only after 6:00 PM on weekdays and any time on weekends and holidays.

C. When site space is not adequate, provide additional off-site parking.

D. Designated parking areas will be determined as needed.

3.03 CONSTRUCTION PARKING CONTROL

A. Control vehicular parking to prevent interference with public traffic and parking, access by emergency vehicles, and Texas Workforce Commission’s operations.

B. Monitor parking of construction personnel’s vehicles in existing facilities. Maintain vehicular access to and through parking areas.

C. Prevent parking on or adjacent to access roads or in non-designated areas.

3.04 HAUL ROUTES

A. Consult with authority having jurisdiction, establish public thoroughfares to be used for haul routes and site access.

B. Confine construction traffic to designated haul routes.

C. Provide traffic control at critical areas of haul routes to regulate traffic and to minimize interference with public traffic.

3.05 MAINTENANCE

A. Maintain traffic and parking areas in a sound condition free of excavated material, construction equipment, products, mud, snow and ice.

TWC – Fort Worth 1st Floor Restrooms 01 5000-2 TEMPORARY FACILITIES AND CONTROLS

B. Maintain existing paved areas used for construction: promptly repair breaks, potholes, low areas, standing water, and other deficiencies to maintain paving and drainage in original, or specified, condition.

3.06 MUD FROM SITE VEHICLES

A. Provide means of removing mud from vehicle wheels before entering streets.

TWC – Fort Worth 1st Floor Restrooms 01 6000-1 PRODUCT REQUIREMENTS

SECTION 01 6000

PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. General product requirements.

B. Transportation, handling, storage and protection.

C. Product option requirements.

D. Substitution limitations and procedures.

E. Maintenance materials, including extra materials, spare parts, tools, and software.

1.02 RELATED REQUIREMENTS

A. Section 01 1100 – Summary: Lists of products to be removed from existing building.

B. Section 01 4000 - Quality Requirements: Product quality monitoring.

1.03 REFERENCE STANDARDS

A. 16 CFR 260.13 – Guides for the Use of Environmental Marketing Claims; Federal Trade Commission;

Recycled Content; Current Edition.