DTFH71-17-R-00003-Amend_0001.pdf
PDF 98 KB Posted
- Attached to
- Blue Ridge Parkway Preservation Federal contract opportunity
- Solicitation number
- DTFH71-17-R-00003
About this file
Amendment 0001 The Bid Opening date of March 28, 2017, at 2:00 p.m. will remain the same.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
DTFH7117R00003
x x
5 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sterling VA 20166-6511
EFLHD-CO
21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.
Federal Highway Administration
Sterling VA 20166-6511
EFLHD-AC
21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.
Federal Highway Administration
SEE BLOCK 1403/22/20170001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/24/2017
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
NP-BLRI PV PRES FY16
The purpose of this Amendment is to provide a summary of responses to questions/clarifications asked by potential bidders.
The Bid Opening date of March 28, 2017, at 2:00 p.m. will remain the same.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment No. 0001
Info Page 1 of 2
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Project NP-BLRI PV PRES FY16
Blue Ridge Parkway Pavement Preservation
(MP 64.5 to MP 101.0 and MP 120.9 to MP 174.6) Solicitation: DTFH71-17-R-00003
The purpose of this Amendment is to provide a summary of responses to questions/clarifications asked by potential bidders.
The Bid Opening date of March 28, 2017, at 2:00 p.m. will remain the same.
Questions / Clarifications
Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.
Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.
1. I have a question on the time limits on the project. It is my understanding that the project has to be completed by September 30, 2017. It has been a base Schedule A and then adds on up to Alternate Schedule G. If the time allowed for each alternate is added together, it is 285 days which will put the completion date well past the September 30 deadline.
Another factor is the micro needs to cure for 30 days prior to striping which equates to complete the macro by September 1.
Could you clarify the completion dates of each schedule and if all six options are accepted, what would be the overall completion date?
Response: Please refer to section 2.C. Completion of Work found on page 5 of the Proposal Schedule Instructions.
It is the Government's intention to award all schedules of work (Schedules A thru G) of the solicitation at one time.
However, if any additional funding beyond the Government's Engineer's Estimate is required to award the contract (i.e., the bids come in high), not all schedules will be awarded at one time. The Base Contract (Schedule A) will be awarded and some combination of the Government Options (Schedules B thru G) will be awarded based on the funding available. If funding becomes available after the award of the Base Contract (Schedule A), the Government will make a determination on which, if any, of the remaining Government Options (Schedules B thru G) will be awarded.
mailto:eflhd.contracts@dot.gov
Info Page 2 of 2
As stated in section 2.C. Completion of Work found on page 5 of the Proposal Schedule Instructions, if all schedules (A thru G) of work are awarded at one time, all contract work (A thru G) is required to be completed by September 30, 2017.
The bidder points out that if the performance periods of each of the individual schedules of work are added together, they add up to 285 calendar days. This 285 day calculation is true but it is based on the assumption that the individual schedules would be awarded individually and that only one schedule would be available to be worked on at one time (i.e., working in series). The Government's calculation of completing work by September 30 is based on the assumption that all schedules would be awarded at one time and that all schedules would have overlapping work periods (i.e., working concurrently).
Additional information can also be found in section 2.B. Schedules of Work found on page 4 of the Proposal Schedule Instructions. This explains the award timeframes if the individual schedules of work are not awarded at the same time as Schedule A (the Base Contract). If Schedule A only is awarded, Schedule B would be awarded (or decision not to award would be made) no later than the completion of Schedule A (i.e., 65 calendar days after Schedule A's Notice to Proceed). As also explained in section 2.B. Schedules of Work, if Schedule B is awarded, the decision to award the remaining schedules (C thru G), would be made by the completion of Schedule B (i.e., 35 calendar days after Schedule B's Notice to Proceed, or 100 total calendar days after the initial award of the contract). The Government has estimated that there should be adequate time to complete the remaining C thru G work by the September 30 completion date. If the actual award scenarios do not happen as explained in sections 2.B. and 2.C. of the Proposal Schedule Instructions, then a mutual agreement will be worked out with the Contractor and the Government.
Please also see the last paragraph of section 2.C. Completion of Work (which can be found on page 6), which states that Offerors are to assume that the start of construction activities is anticipated to start no earlier than May 2017.
To address the bidder's concern with curing time for micro surfacing and striping application, any type of manufacturer/supplier recommendations can be discussed with the CO during construction.
File details come from the government source that posted it. Updated .