QA.pdf

PDF 10 KB Posted

Attached to
CA FTNP GOGA PRES 1(15) Golden Gate N. R. A. Tunnel Preservation
Solicitation number
DTFH6816B00024
Issued by

About this file

Questions and Answers to date 8/18/2016

View the file

Other files

File Type Posted
Option_Y_Tabs.pdf PDF
Schedule_A_Tabs.pdf PDF
Option_X_Tabs.pdf PDF
Bid_Opening_Summary_rev.pdf PDF
Bid_Opening_Summary.pdf PDF
Amend0005.pdf PDF
Amend0004.pdf PDF
Amend0003.pdf PDF
Amend0002.pdf PDF
QA3.pdf PDF
Amend0001.pdf PDF
Prebid_8_16_16.pdf PDF
CA_FTNP_GOGA_PRES_1(15)_-_Construction_Plans_-_Advertisement.pdf PDF
DTFH6816B00024.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidders Questions & Answers

CA FTNP GOGA PRES 1(15)

8/10/16

Q: Can Fusible C-900® pipe be used as an ‘or equal’ for the specified Certa-Lok C900/RJ system within the Baker-Barry Tunnel, Bid Items 61102-3450 and 61202-0700?

A: PENDING: The EOR has provided additional requirements for Fusible pipe which will need to be incorporated as an Amendment prior to responding.

8/11/16

Special Contract Requirements Section 725.30- Can DR 18 TerraBrute® CR pipe be used as an ‘or equal’ product because it provides similar or greater axial restraint capacities as the specified Certa-Lok C900/RJ PVC?

A: The proposed DR 18 TerraBrute® CR pipe does not appear to meet the requirements of Subsection 725.30 for Class 305 (DR 14) polyvinyl chloride pipe.

8/15/16

Q: Is the prebid for the Golden Gate NRA Tunnel preservation (8/16) mandatory?

A: This is not a mandatory visit.

8/18/16

Q: Can the Contractor Work Performance requirement be reduced (Page C-14) from 50%?

A: An amendment will be issued reducing the percentage.