DRAFT_B2_09.9_Final_Inspection_Report.docx

DOCX document 61 KB Posted

Attached to
SLAC Design-Build B057, Room 1026, Modular Cleanroom project
Solicitation number
329772
Issued by

View the file

Other files

File Type Posted
DRAFT_B2_04.0_RFP_Section_C_Cover.pdf PDF
DRAFT_B2_09.8_NTP_Submittal_Checklist.pdf PDF
DRAFT_B2_11.1_Section_L_B057_Modular_Cleanroom_Bid_Breakdown.xlsx XLSX spreadsheet
DRAFT_B2_09.5_Work Classification_329772.pdf PDF
DRAFT_B2_02_RFP_Section_A_(Subcontract_Award)_05.23.22_(B2).pdf PDF
DRAFT_B2_10.1_Section_K_Reps_and_Certs-Rider-Feb_2018.pdf PDF
DRAFT_B2_12.0_Section_M_Evaluation_Criteria.pdf PDF
DRAFT_B2_06.0_Section_G_(General_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.4_Section_J_Kobe.pdf PDF
DRAFT_B2_09.2_Section_J _ISEMS.pdf PDF
DRAFT_B2_06.1_FP_Construction_(Sept_2020).pdf PDF
DRAFT_B2_03_Section_B_(Supplies or Services).pdf PDF
DRAFT_B2_09.10_Final_Release.docx DOCX document
DRAFT_B2_00_RFP_Cover_Letter_329772_B057_Modular_Cleanroom_Project.pdf PDF
DRAFT_B2_08_Section_I_(Specific Subcontract Clauses).pdf PDF
DRAFT_B2_09.0_Section_J_(List_of_Attachments).pdf PDF
DRAFT_B2_01_Attachment_A_Request_for_Clarifications.docx DOCX document
DRAFT_B2_09.7_SubcontractorFormSQF.pdf PDF
DRAFT_B2_11.0_Section_L_Instructions_to_Offerors.pdf PDF
DRAFT_B2_07_Section_H_(Special_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.6_Section_J_SF1413-13g.pdf PDF
DRAFT_B2_09.3_Section_J_Subcontractor_Form_IIPP_052121.pdf PDF
DRAFT_B2_04.1_B057_Room_1026_Modular_Cleanroom_Design-Build_Requirements_053122.pdf PDF
DRAFT_B2_05_Sec_F_Deliveries_Performance.pdf PDF
DRAFT_B2_09.1_DBA_WD_CA20220018_060322_Mod_7.pdf PDF
DRAFT_B2_10.0_RFP_Section_K_Reps_and_Certs_Cover.pdf PDF
DRAFT_B2_06.2_COVID-19 Rider for Onsite_Contractors_(Nov_2021).pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPLY CHAIN MANAGEMENT

SUPPLY CHAIN MANAGEMENT

SUPPLY CHAIN MANAGEMENT

Date: MM/DD/YYYY
2575 Sand Hill Road, MS: 01

Menlo Park, CA 94025

PH: (650) 926-XXXX

Contract Administrator: NAME

Email: ______@slac.stanford.edu

FINAL INSPECTION REPORT

(Required by Procurement to release Final Payment)

Subcontractor Name

Project Name

Subcontract No

SLAC Project Manager

SLAC Field Construction Manager

SLAC Subcontract Administrator

The work was found to meet the requirements of the Subcontract as indicated below:

1. The Final Inspection was held on (Date): ; and attended by:

a. Attendees for SLAC:_____________________________________________________________

b. Attendees for Subcontractor:_______________________________________________________

2. Red-Line As-Built Drawings:

a. Received on:; by:
b. Accepted on:; by:

3. Operation & Maintenance Manuals:

a. Received on:; by:
b. Accepted on:; by:

4. All ID Badges & Dosimeter Badges received on: ($500/dosimeter not returned to SLAC)

5. Keys (if applicable) received on:

6. Certified Payrolls are complete and finalized via LCP Tracker on:

7. Punch List approved:

a. A/E:By:Signature
b. Facilities & Operations By:Signature
c. SubcontractorBy:Signature

8. SLAC Building Inspection Office Final Certificate of Occupancy or Permit Card issued on:

ACKNOWLEDGEMENT AND ACCEPTANCE OF THIS FINAL INSPECTION REPORT:

Title
Name
Signature
Date

SLAC PM

SLAC FCM

Subcontractor PM

2575 Sand Hill Road Mail Stop 18 Menlo Park, CA 94025-7015 650-926-2241 Fax 650-926-8785 SLAC is operated by Stanford University for the U.S. Department of Energy image1.jpeg

File details come from the government source that posted it. Updated .