DRAFT_B2_04.1_B057_Room_1026_Modular_Cleanroom_Design-Build_Requirements_053122.pdf

PDF 923 KB Posted

Attached to
SLAC Design-Build B057, Room 1026, Modular Cleanroom project
Solicitation number
329772
Issued by

View the file

Other files

File Type Posted
DRAFT_B2_04.0_RFP_Section_C_Cover.pdf PDF
DRAFT_B2_09.8_NTP_Submittal_Checklist.pdf PDF
DRAFT_B2_11.1_Section_L_B057_Modular_Cleanroom_Bid_Breakdown.xlsx XLSX spreadsheet
DRAFT_B2_09.5_Work Classification_329772.pdf PDF
DRAFT_B2_02_RFP_Section_A_(Subcontract_Award)_05.23.22_(B2).pdf PDF
DRAFT_B2_10.1_Section_K_Reps_and_Certs-Rider-Feb_2018.pdf PDF
DRAFT_B2_12.0_Section_M_Evaluation_Criteria.pdf PDF
DRAFT_B2_06.0_Section_G_(General_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.9_Final_Inspection_Report.docx DOCX document
DRAFT_B2_09.4_Section_J_Kobe.pdf PDF
DRAFT_B2_09.2_Section_J _ISEMS.pdf PDF
DRAFT_B2_06.1_FP_Construction_(Sept_2020).pdf PDF
DRAFT_B2_03_Section_B_(Supplies or Services).pdf PDF
DRAFT_B2_09.10_Final_Release.docx DOCX document
DRAFT_B2_00_RFP_Cover_Letter_329772_B057_Modular_Cleanroom_Project.pdf PDF
DRAFT_B2_08_Section_I_(Specific Subcontract Clauses).pdf PDF
DRAFT_B2_09.0_Section_J_(List_of_Attachments).pdf PDF
DRAFT_B2_01_Attachment_A_Request_for_Clarifications.docx DOCX document
DRAFT_B2_09.7_SubcontractorFormSQF.pdf PDF
DRAFT_B2_11.0_Section_L_Instructions_to_Offerors.pdf PDF
DRAFT_B2_07_Section_H_(Special_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.6_Section_J_SF1413-13g.pdf PDF
DRAFT_B2_09.3_Section_J_Subcontractor_Form_IIPP_052121.pdf PDF
DRAFT_B2_05_Sec_F_Deliveries_Performance.pdf PDF
DRAFT_B2_09.1_DBA_WD_CA20220018_060322_Mod_7.pdf PDF
DRAFT_B2_10.0_RFP_Section_K_Reps_and_Certs_Cover.pdf PDF
DRAFT_B2_06.2_COVID-19 Rider for Onsite_Contractors_(Nov_2021).pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SLAC NATIONAL ACCELERATOR LABORATORY

LCLS Facilities Engineering

Building 057 Room 1026

Modular Cleanroom Design-Build Requirement

Prepared by: 4/14/22 Kingston Chan Date LCLC Facilities Project Manager

Reviewed by:

Phil Cutino Date LCLC Facilities Manager

Approved by:

Professor Mattias Kling Date Director SRD Division

5/3/22

SLAC - ES&H - BIO

Authorized to Proceed onto Procurement

By:

Date:

NOT FOR CONSTRUCTION

5/31/2022

PRS# 22-084

Original

MAY 31 2022

Received

ESH/BIO

by SLC

SECTION 010000 - GENERAL REQUIREMENTS

B057Room 1026 March 27, 2022 Modular Cleanroom Design Build

SECTION 010000

GENERAL REQUIREMENTS

GENERAL

1.1 The following specification outlines the requirements for the complete “design-build” of an approximate 30 feet long x 33 feet wide x 9 feet high stand-alone modular cleanroom.

The modular cleanroom will be constructed in Room 1026 in the Arrillaga Science Center (ASC), Building 057, at the SLAC National Accelerator Laboratory (SLAC), 2575 Sand Hill Road, Menlo Park, San Mateo County, California.

1.2 SCOPE OF WORK:

The Subcontractor shall furnish all labor, materials, tools, equipment, and incidentals necessary to perform the work indicated in these specifications.

The purpose of this specification is to describe the intended results of the work, identify certain reference standards, and provide certain technical details. Where standards are not specified, the Subcontractor shall perform the work in accordance with the best general construction practices and industry standards, codes, and provide all new materials and workmanship of the first quality. Where the specifications do not provide complete details, the Subcontractor shall provide a submittal to SLAC for Prior Approval, showing the details of the planned method for meeting the Subcontract requirements. The term “contractor” as used in the Specifications and Drawings shall mean “Subcontractor”. The term “should" as used in the Drawings shall mean “shall”. The term “Provide” as used in the specifications and drawings shall mean “Furnish and Install”.

The Subcontractor shall verify all dimensions, locations and quantities in the field prior to providing price proposal and construction and shall furnish all construction surveys and tests required for correct location and installation of all work.

The Subcontractor is required to provide employees who are trained and experienced in performing the work required under the conditions existing for this project. A Supervisor having the authority to act as a representative for the subcontractor shall be on the job during the course of work being performed. The Subcontractor shall provide personal protective equipment for all Subcontractor personnel onsite, including steel toed footwear, hard hats, safety glasses, work gloves and reflective vests.

SLAC - ES&H - BIO

Authorized to Proceed onto Procurement

By:

Date:

NOT FOR CONSTRUCTION

5/31/2022

SLC for

1.3 DESCRIPTION:

A. This project will construct a turnkey stand-alone modular cleanroom. The scope of work includes but not limited to the requirements necessary to furnish, install and complete a cleanroom, that meets the following requirements:

a. NB: The cleanroom will be constructed in an operating facility. The subcontractor shall keep the duct, noise and vibration to the minimum. Coordinate any required utility outages no less than 5 days in advance.

b. Provide protection, dust and debris control and temporary barriers as necessary to protect and keep safe adjacent labs which houses sensitive scientific equipment.

c. The subcontractor shall field verify dimensions of Room 1026, ASC Building 057.

d. The cleanroom’s dimensions shall be approximately 33 feet long x 30 feet wide x 9 feet high.

e. The cleanroom shall have three metal doors (located at the back of the cleanroom for separate entry/egress on both sides) and associated door hardware and locks.

f. Cleanroom shall be meet or exceed Class 10,000 or ISO 7 filtration performance.

g. Provide an extruded aluminum wall system including post connections, head tracks, floor tracks, corner details, and appurtenances.

h. Provide extruded aluminum cleanroom ceiling grid system, 2’x 4’ grid.

i. Provide sealing escutcheons or cover plates at penetrations thru clean room ceiling system for sprinklers and duct/pipe.

j. Provide wall cover plates with seals at pass thru openings.

k. Provide dimmable LEC lighting fixtures and switches.

a. Manufacture: Kenall Simpleseal

b. Model: CSEDO-24-67L40K-DDC-120-5F-2H-SYM, recessed 2x4 LED fixture, 67 Watt/7333 lumen package, 0-10v dimming.

l. Provide emergency lighting in accordance with NFPA Life Safety Code 101.

m. Provide fan powered HEPA filters. Filter element replacement shell be from below.

n. Provide low wall air return grills

o. Provide fire sprinklers, horn strobes (Siemens) and illuminated emergency exit signs. The fire protection/alarm system shall be compatible with and connected to the SLAC fire alarm system. Submit sprinkler design and layout plan for approval prior to installation.

p. Provide laser curtain structural supports as shown on sketch. SLAC furnishes the laser curtain and curtain rails.

q. Provide complete cleanroom electrical system (for fan powered HEPA filters, lighting, outlets, emergency lighting) and required electrical distribution panels.

Final connections for the panels will be done by other.

i. Panel board: Siemens with 50A MCB

ii. SLAC provides input power 208v, 1 phase.

r. Provide cleanroom Process Cooling Water (PCW) & Compressed Air (CA) service drops as indicated on the sketch. (PCW and CA from SLAC site utilities connections inside room 1026). Piping shall be copper type L. Pressure test shall be in accordance with ASME 31.9 Building Services Piping.

s. Submit comprehensive structural calculations for the modular cleanroom, signed and sealed by a California registered Structural Engineer in accordance with SLAC Seismic Design Specification for Building, Structures, Equipment and Systems.

i. Submit concurrent with shop drawings.

B. Hazardous wastes, Class II wastes, Universal wastes: Subcontractor shall segregate wastes and place them in containers labeled and provided by SLAC Waste Management (WM). Location and delivery of containers will be coordinated with building and/or area managers through SLAC Field Construction Manager (FCM).

C. Recyclable waste: Subcontractor shall provide bins for recyclable waste. SLAC requires that non-hazardous construction waste such as cardboard, wood, and scrap metal be recycled or reused instead of disposed as trash. Subcontractor shall provide municipal waste and recycling logs and receipts to SLAC Environmental Protection Department's Waste Minimization coordinator at the end of the project. The log shall include types and volumes of recycled material from the project.

a. Silica dust: Subcontractor shall collect generated silica dust with approved equipment and provide necessary worker PPE in accordance with CAL OSHA.

b. Clean, non-contaminated waste: Subcontractor shall provide bins and dispose the waste.

D. Any discrepancies between drawings and specifications or normal Construction practices shall be brought to the Project Manager and Field Construction Manager’s (FCM) attention before proceeding.

E. All work shall be coordinated with other trades and Subcontractors working in this area through SLAC FCM.

F. Deliverables:

1. Submit all materials provided for review and approval prior to ordering.

2. A fully functional Design-Build modular cleanroom per specification.

3. Submittal construction drawings and as-built drawings in AutoCAD and PDF formats.

4. Structural calculations signed and sealed by California registered Structural

Engineer.

1.4 SCHEDULE:

The work shall be completed 24 weeks after the Notice-To-Proceed (NTP), which is the performance period for this project. This date shall be the Beneficial Occupancy or user move in date for this project if not sooner.

1.5 SPECIAL REQUIREMENTS AND CONDITIONS:

SLAC requires additional documentation of your company safety program and specific documents within ten (10) days depending on the phase and hazards associated with a given project. These documents shall include, but are not limited to:

A. All workers shall obtain a SLAC badge prior to working on site. To obtain a permanent badge, workers must complete SLAC construction safety orientation (Course 375) and COVID 19 training, which are online courses approximately 30 minutes each in duration).

B. Company Hazardous Energy Control (Lockout/Tagout) Program – for electrical, mechanical and plumbing subcontractor and other subcontractors, as appropriate.

C. Job Safety Analysis (JSA).

D. Company Illness Injury Prevention Plan (one for each subcontractor)

Various SLAC specific plans and permits including, but not limited to, excavation, hot (burning/brazing) work, hoisting and rigging, excavations and penetrations, fall protection, confined space, demolition etc., if applicable.

1.6 Work Hours: SLAC working hours are 7:00 am to 4:30 pm. No worker shall work more than 10 hours/day, six (6) consecutive days and more than 60 hours per week.

1.7 ATTACHMENT: Sketch 1 – Cleanroom general layout and requirement.

1.8 REFERENCED STANDARDS:

All work performed shall meet or exceed requirements of the codes, standards, and regulations listed below. All codes, standards, and referenced specifications indicated shall mean the latest edition, including supplements when such exists, unless otherwise stated. Refer to individual sections for specific reference standards. Additional standards are stated in the “General Terms and Conditions” and “Request For Proposal” (RFP), which in addition to these specifications are part of your subcontract documents.

A. California Building Code (CBC), 2019 edition.

B. California Plumbing Code (CPC), 2019 edition.

C. California Mechanical Code (CMC), 2019 edition.

D. California Fire Code (CFC), 2019 edition.

E. National Fire Protection Association (NFPA) Standards.

F. ADA Accessibility Guidelines for Buildings and Facilities (ADAAAG) G. Life Safety Code, NFPA 101, 2021 edition.

H. National Electrical Code (NEC) 2020 edition, NFPA 70.

I. Standard for Electrical Safety in the Workplace, NFPA 70E, 2021 edition J. Institute of Electrical and Electronics Engineers (IEEE) Standards.

K. Underwriters Laboratories (UL) listing and labeling of equipment.

L. American Concrete Institute (ACI) M. American National Standards Institute (ANSI).

N. American Welding Society, (AWS) Standards.

O. American Society of Mechanical Engineers (ASME).

P. American Society for Testing and Materials (ASTM).

Q. American Concrete Institute (ACI) Standards.

R. American Institute of Steel Construction (AISC).

S. American Iron and Steel Institute (AISI).

T. Steel Structures Painting Council (SSPC).

U. California Code of Regulations, Title 8, Cal/OSHA.

V. Bay Area Air Quality Management District (BAAQMD) – no load bearing structural members will be removed or modified, BAAQMD demolition notification will not be required.

W. CFR 29 Part 1910, Occupational Safety and Health Standards for the Industry, and 1926, Occupational Safety and Health Standards for the Construction Industry by OSHA, Occupational Safety and Health Administration.

X. SLAC Seismic Design Specification for Buildings, Structures, Equipment, and Systems (2020), SLAC-I-720-0A24E-001-R006.

Y. SLAC Storm Water Pollution Prevention Plan, SLAC-I-750-0A16M-002-R005 (November 2019).

Z. Manufacturer’s material and equipment installation and operating instructions and recommendations.

AA. Standards of other publicly recognized standards organizations.

BB. Codes and regulations of all agencies having jurisdiction.

CC. SLAC ES&H Manual, (http://www-group.slac.stanford.edu/esh/eshmanual/)

1.9 EXCLUSIONS, UNIVERSITY FURNISHED MATERIAL, EQUIPMENT AND

SERVICES:

A. University Furnished Materials:

Hazardous waste containers will be provided by SLAC Waste Management.

B. University Furnished Services:

Field Construction Manager.

END OF SECTION

http://www-group.slac.stanford.edu/esh/eshmanual/

Section 010001 – Hold Points

B057 Room 1026 March 27,2022

SECTION 010001 – HOLD POINTS

1.01 HOLD POINTS:

Prior to commencement of the following activities, approval is required as indicated:

TASK APPROVAL

Award of Subcontract. Approval by Procurement/the Contract Administrator.

Prior to commencement of on-site work.

Approval by the Contract Administrator.

Subcontractor and Sub-tiers as applicable shall complete the SLAC Site-specific Safety Plan Content and Approval Form (SSSP) SLAC-I-730- 0A21J-025-R009, 11-26-13 and be approved by

ES&H.

Attend the Pre-construction Meeting – Kick-off Meeting (KOM).

Submit detailed Project Schedule as required by Subcontract and approved by Project Manager.

Issuance of the Notice to Proceed (NTP) by the Contract Administrator and approved/signed by both parties.

Prior to commencement of on-site work provide written Job Safety Analysis (JSA) for the project at hand.

Approval by the Field Construction Manager (FCM) and Facilities Safety.

Submit detailed project Submittals – Material Submittal, Equipment Submittals, and Structural and Seismic Calculations as needed.

Approval by the SLAC Project Manager (PM), Operations, Fire Marshal’s Office as applicable, Building Inspection Office (BIO) as applicable, and Field Construction Manager (FCM).

onto Procurement

By:

Date:

NOT FOR CONSTRUCTION

Prior to ordering equipment and materials and installation.

Receipt of approved Submittals from the Project Manager (PM), Operations, Fire Marshal’s Office as applicable, and Field Construction Manager (FCM).

Prior to any utility shutdown or tie-ins provide proper isolation and plan, notifications to potential impacted Users, and LOTO. Provide FCM with a five

(5) day notice in advance as noted in Section 010000, so FCM can set it up with Operations.

Approval by the Field Construction Manager (FCM), Building Manager, and Operations.

Prior to fire protection system shutdown, provide isolation plan and LOTO. Provide FCM with a five (5) notice in advance, so FCM can set it up with Operations and obtain the SLAC Fire Marshal’s Office authorization prior to implementation.

Approval by the Field Construction Manager (FCM), Fire Technician, Fire Marshal’s Office, Building Manager, and Operations.

Prior to any demolition, i.e.:

piping, tubing, fire protection, equipment, Electrical, etc.

Strictly follow SLAC’s approved Demolition Procedures and get approval from the Field Construction Manager (FCM), Facilities Safety, Building Manager, and ES&H.

Prior to installation of any (N) services, receive the necessary Hot Work Permits, Penetration Permits, Asbestos and Lead Survey Reports, and any other permits or plan submissions required to perform the necessary work.

Approval by the Field Construction Manager (FCM), Facilities Safety, and ES&H.

Prior to anchoring the support on concrete walls

Submit Silica Exposure Control Plan

TASK

APPROVAL

Provide monthly report of landfill and recycling tonnage to – http://recycling.stanford.edu/contractors/CD-recycling.html

All Class II regulated wastes (concrete/asphalt/soil, saw cutting slurry, and/or non-friable asbestos) must be disposed of by WM or the Subcontractor to a SLAC approved disposal facility.

WM will provide Hazardous and Class II waste containers for the project. Lead time to order waste containers is 3-5 working days. Please complete a Hazardous Waste Empty Container and Pick-up Form:

http://www-group.slac.stanford.edu/esh/forms/hazpickup.pdf

For waste from excavations and penetrations (e.g., soils, asphalt, concrete) as applicable, please include the approved Excavation Permit Number (EPR) on the form or provide a copy of the Penetration Permit Form.

Email completed forms to waste@slac.stanford.edu http://recycling.stanford.edu/contractors/CD-recycling.html http://recycling.stanford.edu/contractors/CD-recycling.html http://www-group.slac.stanford.edu/esh/forms/hazpickup.pdf http://www-group.slac.stanford.edu/esh/forms/hazpickup.pdf

During Project Closeout. Submit written certification that the Contract Documents have been reviewed, work has been inspected, work is complete in accordance with the Contract Documents, and the work is ready for SLAC Field Construction Manager (FCM) and Project Manager (PM) to review.

Provide red-lined documents indicating the actual field conditions and installation for our Record Drawings and Specifications.

Provide Operations and Maintenance Manuals for all new devices, equipment, etc. provided and as applicable.

Provide product and Subcontractor’s warranties as applicable.

All work and Closeout documents must be approved by the Field Construction Manager, Operations, Users, and the Project Manager.

END OF SECTION 010001

March 27, 2022

B057 Room 1026

SECTION 01 35 43

ENVIRONMENTAL PROTECTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. General:

1. The following applies to this section:

a. The terms of the Subcontract, including General Provisions, and General Requirements.

b. Related requirements in other Subcontract Documents including, but not necessarily limited to, the Drawings and the Specification Sections in the Project Manual.

2. Review these documents for coordination with additional requirements and information that apply to work under this Section.

B. Related Sections:

1. Section 01 74 19 “Waste Construction Waste Management and Disposal”

1.2 RELATED DOCUMENTS

A. Submit material safety data sheets (MSDS) and hazardous material inventory records for all chemicals, oils, solvents, paints, epoxies, adhesives, petrochemical, or similar materials used on site.

1. SLAC must approve prior to any such materials being brought onto the SLAC premises.

2. Keep one copy of each Safety Data Sheet (SDS at the jobsite at all times.

3. Store materials in compliant containers within the construction boundary or as directed by the Field Construction Manager (FCM).

4. Remove and dispose of all such materials not incorporated in the work in accordance with the applicable federal, state, and local regulations.

1.3 STORM WATER POLLUTION PREVENTION PLAN (SWPPP)

A. Copies of the SLAC SWPPP are available for Subcontractor's review upon request. Refer to Terms and Conditions of the Subcontract and SLAC ES&H Manual for applicable Best Management Practices (BMPs).

B. Subcontractor is required to generate a SWPPP for the Work, submit it to the SLAC storm water program manager for review. SLAC will obtain a storm water discharge permit from the State Water Resources Control Board (file the Notice of Intent for the project) at least 10 working days before work begins. See requirements at:

http://www-group.slac.stanford.edu/esh/eshmanual/references/stormReqConstruction.pdf

1. The Subcontractor shall designate a Qualified SWPPP Developer (QSD) to prepare the

SWPPP, and a Qualified SWPPP Practitioner (QSP) to implement the provisions of the SWPPP and the Construction Site Monitoring Program (CSMP), and shall comply with the narrative effluent standards listed below:

a. The QSP shall have the appropriate training described and shall be listed on the Storm water Multi-Application Reporting and Tracking System (SMARTS) prior to the start

SECTION 01 35 43 -

onto Procurement

By:

Date:

NOT FOR CONSTRUCTION

5/31/2022

SLC for http://www-group.slac.stanford.edu/esh/eshmanual/references/stormReqConstruction.pdf http://www-group.slac.stanford.edu/esh/eshmanual/references/stormReqConstruction.pdf of construction. The Legally Responsible Person (LRP) shall ensure that SWPPPs for all traditional project sites are developed and amended or revised by a Qualified QSD.

2. The Subcontractor shall comply with the storm water runoff requirements for Federal Projects under Section 438 of the Energy Independence and Security Act.

3. Protect storm water: Subcontractor shall minimize or prevent pollutants in storm water discharges and authorized non-storm water discharges through the use of controls, structures, and management practices that achieve BAT (Best “economically” Available Technology) for toxic and non-conventional pollutants and BCT (Best Conventional “pollution control” Technology) for conventional pollutants.

a. All synthetic material used for erosion prevention and other storm water BMPs, such as wattles encased in plastic netting and synthetic silt fences shall be removed at the end of construction and shall not be part of the final site restoration.

4. Subcontractor may substitute alternate pollution prevention measures for those identified in SLAC's SWPPP. Submit alternate measures for SLAC review. SLAC acceptance of alternate pollution prevention measures will not relieve Subcontractor of responsibility for the quality and adequacy of the measures or Subcontractor's implementation of them. Such acceptance does not warrant, acknowledge, or admit the quality and adequacy of the alternate pollution prevention measures.

5. Provide all materials and labor required to implement and maintain pollution prevention measures, and perform all required storm water inspections, monitoring, sampling, recordkeeping, and reporting at no additional cost to SLAC.

6. Failure to comply may result in SLAC halting work until Subcontractor performs remedial action. Consequences shall be in accordance with the Terms and Conditions.

7. If SLAC determines that pollution is leaving the site, implement additional measures to prevent the discharge of pollution. Failure to comply with the requirements of the SWPPP may result in criminal and civil liability of Subcontractor under the Clean Water Act.

8. At the end of the project, provide SLAC with all SWPPP-related inspection sheets and record keeping. SLAC will file Notice of Termination (Completion)

9. The SWPPP should be prepared to comply with the California’s General Permit for Storm Water Discharges Associated with Construction and Land Disturbance Activities (General Permit) - State Water Resources Control Board (SWRCB) Order No. 2009-0009-DWQ, under National Pollutant Discharge Elimination System (NPDES) Permit No. CAS000002.

BAAQMD Notification. The Bay Area Air Quality Management District (BAAQMD) requires notification of all demolition projects (defined as wrecking, intentionally burning, moving or dismantling of any load-supporting structural member, or portion thereof, of a building or facility, including any related cutting, disjointing stripping or removal of structural elements) at least 10 working days before work begins, whether or not Asbestos-Containing Materials (ACM) (friable or non-friable: Category I and II) are known to be present. Significant renovation projects that have the potential to remove greater than or equal to 100 linear feet, 100 square feet or 35 cubic feet of AM likely require notification, as well. Standard forms for both demolition and renovation projects are available on the BAAQMD website:

http://www.baaqmd.gov/ The subcontractor shall be responsible for completing the forms top half, signing on page 2, and forwarding them to the SLAC Air Quality Program Manager for submission to the BAAQMD when the baseline schedule has been accepted by SLAC.

C. Wastewater Disposal

1. Coordinate wastewater disposal with SLAC Environmental Protection. A limited amount of clean (no chemicals added) domestic water used for pipe flushing may be discharged under SLAC’s wastewater discharge permit. Additional water above the allowable amount may need to be discharged under a non-routine discharge permit. Water in which chemicals have been added shall be contained and sampled prior to discharge under a non-routine discharge permit.

http://www.baaqmd.gov/

2. Clean water from testing and flushing activities may be reused for dust control or as irrigation water, under the following conditions, and with approval from SLAC Environmental Protection:

a. It is not a prohibited discharge.

b. The water is not from copper piping.

c. If the water has been chlorinated, it shall be dechlorinated prior to discharge to the environment.

d. No other chemicals have been added.

e. The water shall not be permitted to enter the storm drain system.

3. Any water that comes into contact with asbestos fibers, or wastewater generated during transite pipe cutting work, needs to be collected and filtered in accordance with the following requirements prior to introduction into the sanitary sewer system:

a. Filter water using four in-line filter cartridges with 2" inlets and outlets.

b. The outlet of each filter cartridge shall be connected in series to the inlet of the next cartridge.

c. The first cartridge shall contain 100 μm prefilters and the second and third cartridge shall contain 25 μm filters and the final cartridge shall contain 0.5 μm absolute filters.

d. Contact SLAC Environmental Protection for sampling and discharge to the sanitary sewer under a non-routine discharge permit. Coordinate with SLAC FCM.

D. Prohibited Materials:

1. Asbestos Products: Ensure that no material or equipment containing more than 0.1% asbestos by weight is used at SLAC site.

2. Lead-Based Paint: No lead-based paint materials (defined as having greater than 600 ppm lead) will be allowed on the SLAC site.

E. Storage of Hazardous Materials: All chemicals or material that SLAC determines to be hazardous shall be stored within the construction zone in accordance with the SWPPP and Chapter 40 of the SLAC ES&H Manual.

F. Existing Asbestos: If unidentified asbestos-containing materials (ACMs) are encountered, immediately stop work, notify SLAC, and wait for further direction regarding resumption of the work.

G. Oil-Filled Equipment: Equipment containing petroleum products with a capacity of 55 gallons or more is required to have secondary containment. Refer to SLAC ES&H Manual Chapter 40, Hazardous Materials and SLAC Spill Prevention Control and Countermeasure Plan.

1.4 TESTING AND DISPOSAL OF MATERIALS

A. Materials and Waste Discharge: Do not discharge hazardous materials or wastes into the environment (i.e., air, soil, surface water, and groundwater). Protect all routes of entry to the environment, including direct discharges into air, soil, surface water, storm sewer, sanitary sewer, wells, and drainage channels from construction activities. This shall be achieved by the safe and proper use and storage of tools, equipment, and materials. Inspect construction equipment and vehicles daily for leaks of fuel, engine coolant, and hydraulic fluid. Contain, repair, and immediately report any leaks or spills to the Project Manager. The Subcontractor shall immediately notify the SLAC FCM and SLAC in the event of a leak or spill. Clean up all discharges into the environment according to the guidance provided by SLAC and provided in the ESH Manual Chapter 16, Spills. Clean-up costs of associated discharges or leaks of hazardous material into the environment will be the responsibility of Subcontractor owning said material. SLAC/WM is responsible for disposal of hazardous wastes and shall bill Subcontractor for clean-up and disposal costs associated with Subcontractor’s spills. Refer to SLAC ESH Manual Chapter 17, Hazardous Waste.

B. Disposal and Reuse of Excavated and/or Demolished Materials:

1. Sampling and Evaluation:

a. SLAC will sample and evaluate all soil and/or asphalt and concrete rubble resulting from excavating on the project site prior to Subcontractor removing it from the site.

Refer to SLAC ESH Manual Chapter 11, Excavation Safety. SLAC excavation permit will be required, see Division 01 Section 01 35 20 “Safety Provisions.”

b. To facilitate sampling and evaluation, contact SLAC Environmental Protection Department prior to excavation. Coordinate with SLAC FCM. SLAC may collect samples before or after excavation depending on project timelines. Stockpile excavated materials in separate piles at locations designated by SLAC by composition: asphalt, concrete, soil, debris, etc. Stake and identify each pile, and anchor 6 mm plastic sheeting under and on top of each pile. Maintain sheeting in place until materials are tested and approved for disposal.

c. Disposal of such materials demonstrating visually detectable contamination shall be coordinated through the SLAC Environmental Protection Department.

2. Clean Soil: Reuse excavated clean soil materials on the SLAC site as directed by the FCM with the concurrence of the SLAC Environmental Protection Department. Assume all incidental transportation costs and accomplish all reuse activities at the site as directed by

SLAC.

3. Nonhazardous Waste: The soil not designated for reuse and/or debris resulting from excavating and stripping of the project site shall be characterized by SLAC as non-designated, non-hazardous, and nonradioactive, and shall be approved by SLAC for removal from the site. Arrange for, and be responsible for, removal of all debris as directed by SLAC including to a permitted landfill or recycling facility.

4. Hazardous Waste: See Division 01 Section 01 74 19 “Construction Waste Management and Disposal.”

C. Solid Waste Management:

1. SLAC encourages recycling and solid waste diversion and will assist Subcontractor in the establishment of cost effective construction site diversion program. Subcontractor must recycle at least 75% of non-hazardous construction debris (and demolition debris if applicable). See Division 01 Section 01 74 19 “Construction Waste Management and Disposal.”

2. Prepare an SWMP. The SWMP (Solid Waste Management Plan) shall include the nonhazardous construction and/or demolition solid waste components (e.g., wood and metals by type) and their proposed disposition (i.e., solid waste disposal or recycling). See Division 01 Section 01 74 19 “Construction Waste Management and Disposal.”

PART 2 - PRODUCTS NOT USED

PART 3 - EXECUTION NOT USED

SECTION 01 74 19

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

1.1 RELATED DOCUMENTS

A. General:

1. The following applies to this section:

a. General provisions of the Contract, including General and Supplementary Conditions.

b. The Contract Drawings.

c. Specification Sections and related requirements in other sections of the Project Manual.

d. Related requirements in other Contract Documents listed in the Agreement.

2. Review all Contract Documents for coordination with additional requirements and information that apply to work under this Section.

3. SLAC has established that this Project shall include proactive measures for waste management participation by all parties to the contract.

a. The purpose of this program is to ensure that during the course of the Project all diligent means are employed to pursue practical and economically feasible waste management and recycling options.

b. Upon award, each subcontractor shall be required to furnish documentation from suppliers or manufacturers regarding waste management and recycling options for those products and procedures furnished.

c. Waste disposal to landfills shall be minimized.

4. Project Special Conditions: If recycling facilities and infrastructure are not yet available nearby the project location, the Subcontractor shall obtain temporary storage space for construction waste, to be recycled as soon as facilities are available.

1.2 SUMMARY

A. Subcontractor shall implement procedures to minimize the creation of construction and demolition waste on the job site. As many of the non-hazardous waste materials as economically feasible shall be reused, salvaged, or recycled.

B. The Subcontractor shall develop a Waste Management Plan as defined in this Section and submit for review by SLAC.

C. Administrative and procedural requirements for the following:

1. Salvaging nonhazardous demolition and construction waste.

2. Recycling nonhazardous demolition and construction waste.

3. Disposing of nonhazardous demolition and construction waste.

D. This section applies to non-hazardous wastes, unless otherwise noted.

1.3 DEFINITIONS

A. Waste:

1. Any material that has reached the end of its intended use. Waste includes salvageable, returnable, recyclable and reusable construction materials that would otherwise be discarded or destroyed.

SECTION 01 74 19 -

SLAC - ES&H - BIO

Authorized to Proceed onto Procurement

By:

Date:

NOT FOR CONSTRUCTION

B. Construction Waste:

1. Solid wastes including, but not limited to, building materials, packaging materials, debris and trash resulting from construction operations. Land clearing debris and soils are not included in Construction Waste.

C. Demolition Waste:

1. Building and site improvement materials resulting from demolition or selective demolition operations.

D. Disposal:

1. Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill acceptable to authorities having jurisdiction.

E. Recycle:

1. Recovery of demolition or construction waste for subsequent processing in preparation for reuse.

2. Categories of salvageable or recyclable waste include the following:

a. Concrete, Masonry, and Other Inert Fill Material: concrete, brick, rock, broken up asphalt pavement, clay, and other inert (non-organic) materials.

b. Metals: metal scrap including iron, steel, copper, brass, and aluminum; includes beverage containers, packaging materials (such as metal banding), fencing, reinforcing bar, wiring, plumbing, etc.

c. Untreated Wood: unpainted, untreated dimensional lumber, wood edging, wood shipping pallets, etc. Does not include pressure treated or creosote treated wood.

d. Engineered Wood Products: plywood, oriented strand board, Masonite, particleboard, manufactured trusses and beams, and glue-laminated timbers.

e. Gypsum Wallboard: excess drywall construction materials including cuttings, other scrap, and excess materials.

f. Cardboard: clean, corrugated cardboard such as used for packaging, etc.

g. Paper Goods:

1) Office paper: includes any paper, such as manufacturer instructions, specification sheets, files, correspondence, packaging, stiffeners, etc.

2) Newsprint: shredded or whole newspaper goods.

h. Plastic: beverage containers, packaging materials (such as polystyrene “peanuts” and expanded polystyrene), containers (other than those used for hazardous materials), vinyl products, etc.

i. Glass: includes glass beverage containers, and recyclable glass building materials.

j. Insulation: rigid foam, batt, and loose fill insulation materials.

k. Carpet: face fiber, backing, padding, and carpet cushion scrap.

l. Paints: unused portions of paints and coatings applied on-site.

m. Fabric: uncontaminated fabric scraps.

n. Rubber: uncontaminated rubber scraps, including but not limited to recycled-content rubber flooring, rubber edging, tires that are no longer serviceable, etc.

o. Other: any additional materials identified on-site to be valued for salvage, reuse, or recycling by SLAC.

F. Salvage:

1. Recovery of demolition or construction waste and subsequent sale or reuse in another facility.

G. Salvage and Reuse:

1. Recovery of demolition or construction waste and subsequent incorporation into the Work.

H. Source Separated :

1. Materials that are separated on-site by category.

I. Hazardous waste:

1. Any material or byproduct of construction that is regulated by the Environmental Protection

Agency and/or State of California, and that may not be disposed in any landfill or other waste end-source without adherence to applicable laws.

J. Trash:

1. Any product or material unable to be returned, reused, recycled or salvaged.

K. Landfill:

1. Any public or private business involved in the practice of trash disposal.

L. Waste Management Plan:

1. A Project-related plan for the collection, transportation, recycling and disposal of the waste generated at the construction site.

1.4 PERFORMANCE GOALS AND REQUIREMENTS

A. General:

1. Develop Waste Management Plan that results in end-of-Project rates for salvage/recycling of a minimum of 75 percent by weight of total waste generated by the Work, with a goal of 95 percent or more.

1.5 ENVIRONMENTAL ACTION SUBMITTALS

A. Waste Management Plan:

1. Submit plan within 14 calendar days of the Notice to Proceed. See below for details.

1.6 INFORMATIONAL SUBMITTALS

A. Waste Reduction Progress Reports: Submit monthly as part of Application for Payment.

1. Concurrent with each Application for Payment, submit copies of report. Include separate report for demolition and construction waste. Include the following information:

a. Material category.

b. Generation point of waste.

c. Total quantity of waste in tons.

d. Quantity of waste salvaged, both estimated and actual in tons.

e. Quantity of waste recycled, both estimated and actual in tons.

f. Quantity of land clearing debris waste, in tons.

g. Total quantity of waste recovered (salvaged plus recycled) in tons.

h. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste.

i. Supporting waste/recycling tags.

B. Records of Sales:

1. Indicate receipt and acceptance of salvageable waste sold to individuals and organizations.

Indicate whether organization is tax exempt.

C. Recycling and Processing Facility Records:

1. Indicate receipt and acceptance of waste by landfill facilities licensed to accept them.

2. Include manifests, weight tickets, receipts, and invoices.

3. Include overall percentage of commingled waste diverted from landfill. Percentage may be project specific or represent overall performance of waste facility.

4. Requirement of documentation for the overall percent of waste diverted for commingled waste. The diversion rate can be for the overall facility or specific to the project.

D. Landfill Disposal Records:

1. Indicate receipt and acceptance of waste by landfills facilities licensed to accept them.

Include non-hazardous manifests, weight tickets, receipts, and invoices.

E. Waste Reduction Calculations:

1. Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total non-hazardous waste generated by the Work.

F. Subcontractor shall provide a copy of the final progress report to SLAC Environmental Protection Department's Waste Minimization coordinator at the end of the project. If the project extends over fiscal years, provide an interim report by October 15 for each fiscal year for which waste was disposed or recycled.

1.7 QUALITY ASSURANCE

A. Regulatory Requirements:

1. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Disposal Sites, Recyclers, and Waste Materials Processors: Use only facilities properly permitted by state and local authorities.

C. Waste Management Conference:

1. SLAC shall conduct conference at Project site to review methods and procedures related to waste management including but not limited to, the following:

a. Review and discuss Waste Management Plan.

b. Review requirements for documenting quantities of each type of waste and its disposition.

c. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays.

d. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.

e. Review waste management requirements for each trade.

1.8 WASTE MANAGEMENT PLAN

A. General:

1. Develop plan consisting of waste identification and waste reduction work plan. Include separate sections in plan for demolition and construction waste. Indicate quantities by weight.

2. Show compliance with applicable state and local ordinances and regulations.

B. Waste Identification:

1. Indicate anticipated types and quantities of demolition, land-clearing and construction waste generated by the Work. Include estimated quantities and assumptions for estimates.

C. Waste Reduction Work Plan:

1. List each type of waste and whether it will be salvaged, recycled, or disposed in landfill.

Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures.

a. Recycled Materials: Assign recycling to recycling subcontractor, or list local receivers and processors, and type of recycled materials each will accept. Include names, addresses, and telephone numbers.

2. Disposed Materials:

a. Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill facility. Provide documentation to justify decision not to recycle any items.

b. Ensure loads are secure and securely covered prior to departing site.

3. Handling and Transportation Procedures:

a. Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location on Project site where materials separation will be located; and off-site location for temporary storage if necessary.

4. Waste Management Plan shall include locations of sorting and waste storage facilities on Site Plan of project.

1.9 HAZARDOUS WASTES, CLASS II WASTES, UNIVERSAL WASTES:

A. Subcontractor shall segregate wastes and place them in appropriate labeled bins provided by SLAC Waste Management (WM). Any and all hazardous waste, including sludge removed from sewer lines, and other Class II regulated wastes generated by this project will be disposed of by Subcontractor in coordination with SLAC’s Waste Management Department. Subcontractor shall coordinate with FCM for procedures.

1.10 NON-HAZARDOUS RECYCLABLES AND WASTE:

A. Subcontractor shall provide bins for recyclable waste. SLAC requires that non-hazardous construction waste such as cardboard, wood, and scrap metal be recycled or reused instead of disposed as trash as described above.

B. Clean, non-contaminated waste: Subcontractor shall provide bins and dispose the waste.

1.11 STORAGE AND HANDLING:

A. Recyclable Waste: Remove all recyclable materials, as identified in the Waste Management Plan, from the work location to approved containers daily. Failure to remove waste materials will be considered cause for withholding payment and/or termination of Contract.

B. Provide separate collection containers as required by recycling haulers and to prevent contamination of materials, including protection from rain as applicable.

C. Replace loaded containers with empty ones as demand requires but not less than weekly.

D. Handling: Deposit all indicated recyclable materials in the containers in a clean (no mud, adhesives, solvents, petroleum contamination), debris-free condition. Do not deposit contaminated materials into the containers until such time as such materials have been cleaned.

E. If contamination chemically combines with the material so that it cannot be cleaned, do not deposit into the recycle containers.

1.12 PROJECT/ SITE CONDITIONS

A. Environmental Requirements: Transport recyclable waste materials from the Work Area to the recycle containers and carefully deposit in the containers in a manner to minimize noise and dust. Close container covers immediately after materials are deposited. Do not place recyclable waste materials on the ground adjacent to a container.

PART 2 - PRODUCTS NOT USED

PART 3 - EXECUTION

3.1 WASTE MANAGEMENT PLAN IMPLEMENTATION

A. General: Implement Waste Management Plan as approved by SLAC. Provide handling, containers, storage, signage, transportation, and other items as required to implement Waste

Management Plan during the entire duration of the Contract. Comply with the following procedures:

1. Define specific areas to facilitate separation of materials for recycling, salvage, reuse or return.

2. Separate, store, protect, and handle at the project site all identified recyclable and salvageable waste products to prevent contamination of materials and maximize recyclability and salvageability of materials.

3. Recycle and waste bin areas are to be maintained in an orderly manner and clearly marked to avoid contamination of materials. Inspect containers and bins weekly for contamination and remove contaminated materials if found.

4. Do not mix recyclable materials.

5. Stockpile processed materials on site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust. Furnish and install storm water runoff protection at all stockpiles.

6. Store materials away from construction area. Do not store within drip line of remaining trees.

7. Store components off the ground and protect from weather.

8. Arrange for timely pickups from the site or deliveries to approved recycling facilities of designated waste materials to keep construction site clear and prevent contamination of recyclable materials.

9. Remove construction waste off Owner’s property and transport to appropriate receiver or processor.

10. Refer to Division 01 Section 01 35 43 “Environmental Protection Procedures” for storm water management requirements.

B. Hazardous Wastes: Store in secure areas and comply with the following:

1. Hazardous wastes shall be separated and stored in accordance with SLAC local and EPA regulations and additional criteria listed below:

a. Building products manufactured with PVC or containing chlorinated compounds shall not be incinerated.

b. Storage of fluorescent tubes to open containers is not permitted.

2. Unused fertilizers shall not be co-mingled with construction waste.

C. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at Project site.

1. Provide on-site instruction on appropriate separation, handling, recycling, and salvaging methods to be used by all parties at the appropriate stages of the work at the site.

D. Distribute Waste Management Plan to all necessary parties within seven days of submittal return.

E. Distribute Waste Management Plan to entities when they first begin work on site. Review plan procedures and locations established for salvage, recycling, and disposal.

F. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

G. Designate and label specific areas on Project site necessary for separating materials that are to salvaged, recycled, reused, donated, and sold; or if adequate space are not available on site obtain a secure location off-site for temporary storage of construction waste prior to recycling.

H. Comply with environmental controls specified in Division 01 Section 01 35 43 “Environmental Protection Procedures.”

I. Materials identified in the Report shall be reported by weight.

J. Where weight is not applicable, Subcontractor shall report materials by units applicable to material recipient.

K. Procure receipts or other validation of waste management procedures and include them as part of the submittal.

L. Keep and maintain records of all deliveries to recycling facilities and all pickups of waste materials at the site by others as specified above.

3.2 RECYCLING WASTE

A. General: Recycle paper and beverage containers used by on-site workers.

B. Waste Materials: materials defined in paragraph 1.3.E.2 above shall be salvaged or recycled according to this specification. Strategies for salvage and recycling shall be identified in the Waste Management Plan as required above.

C. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall go to the Subcontractor.

3.3 DISPOSAL OF NON-HAZARDOUS WASTE

A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill acceptable to authorities having jurisdiction.

B. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.

C. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

D. Burning: Do not burn waste materials on site.

E. Disposal: Transport waste materials off Owner’s property and legally dispose of them.

3.4 DISPOSAL OF HAZARDOUS WASTE

A. All hazardous waste generated from this project must be disposed by Subcontractor with SLAC Waste Management oversight.

B. Subcontractor to provide all Class I and Class II material removal to SLAC-approved disposal facility including, but not limited to the following:

1. Asbestos abatement waste

2. PCB, TPH and other hazardous contaminated materials

3. Soil classified Class I or Class II by Subcontractor or SLAC Environmental Protection

4. Oily or solvent absorbent from spills

5. Partially filled aerosol cans

6. Tubes last containing corrosion or acid inhibiting compounds

7. Adhesives, epoxy, paint, grease, oil containing compounds

8. Lubricants, cutting fluid, cleaning solvents, ballasts

9. Other hazardous wastes that may have not been used on the job but brought in by the

Subcontractor

C. Subcontractor shall provide all hazardous waste containers for the project unless noted otherwise. Refer to SLAC Environment, Safety and Health (ES&H) Manual Chapter 17, Hazardous Waste.

3.5 PROPERTY CONTROL/SALVAGE REQUIREMENTS

A. A salvage form will be required for any equipment/material sent to salvage. Coordinate with FCM for obtaining the form.

https://www-internal.slac.stanford.edu/ocfo/purchasing/propertycontrol/propertySalvage.htm https://www-internal.slac.stanford.edu/ocfo/purchasing/propertycontrol/propertySalvage.htm https://www-internal.slac.stanford.edu/ocfo/purchasing/propertycontrol/propertySalvage.htm

SECTION 13 61 13

CLEANROOM PARTITION SYSTEMS(CRCS)

CLEANROOM PARTITION SYSTEMS (CRPS)

1.1 SUMMARY

A. Furnish engineering, labor, materials, tools, equipment, and services for Cleanroom Partition Systems, as indicated, in accordance with provisions of Contract Documents.

B. Section Includes:

1. Partition system including components, fasteners, and accessories for a complete and functional system.

2. Doors in the cleanroom partitions, excluding doors in the furred systems on gypsum board and stud walls, including door framing, and door hardware.

3. Studded non-progressive partition systems which typically span from the floor system to the cleanroom ceiling system.

4. Furred non-progressive partition systems applied over gypsum board and stud enclosure walls around cleanrooms.

C. Related Sections:

1. Section 13 62 13, Cleanroom Ceiling Systems (CRCS)

D. Completely coordinate with work of other trades.

1.2 QUALITY ASSURANCE

A. Manufacturer's Qualifications:

1. Fabricator of cleanroom wall systems for minimum five (5)…