DRAFT_B2_09.2_Section_J _ISEMS.pdf

PDF 547 KB Posted

Attached to
SLAC Design-Build B057, Room 1026, Modular Cleanroom project
Solicitation number
329772
Issued by

View the file

Other files

File Type Posted
DRAFT_B2_04.0_RFP_Section_C_Cover.pdf PDF
DRAFT_B2_09.8_NTP_Submittal_Checklist.pdf PDF
DRAFT_B2_11.1_Section_L_B057_Modular_Cleanroom_Bid_Breakdown.xlsx XLSX spreadsheet
DRAFT_B2_09.5_Work Classification_329772.pdf PDF
DRAFT_B2_02_RFP_Section_A_(Subcontract_Award)_05.23.22_(B2).pdf PDF
DRAFT_B2_10.1_Section_K_Reps_and_Certs-Rider-Feb_2018.pdf PDF
DRAFT_B2_12.0_Section_M_Evaluation_Criteria.pdf PDF
DRAFT_B2_06.0_Section_G_(General_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.9_Final_Inspection_Report.docx DOCX document
DRAFT_B2_09.4_Section_J_Kobe.pdf PDF
DRAFT_B2_06.1_FP_Construction_(Sept_2020).pdf PDF
DRAFT_B2_03_Section_B_(Supplies or Services).pdf PDF
DRAFT_B2_09.10_Final_Release.docx DOCX document
DRAFT_B2_00_RFP_Cover_Letter_329772_B057_Modular_Cleanroom_Project.pdf PDF
DRAFT_B2_08_Section_I_(Specific Subcontract Clauses).pdf PDF
DRAFT_B2_09.0_Section_J_(List_of_Attachments).pdf PDF
DRAFT_B2_01_Attachment_A_Request_for_Clarifications.docx DOCX document
DRAFT_B2_09.7_SubcontractorFormSQF.pdf PDF
DRAFT_B2_11.0_Section_L_Instructions_to_Offerors.pdf PDF
DRAFT_B2_07_Section_H_(Special_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.6_Section_J_SF1413-13g.pdf PDF
DRAFT_B2_09.3_Section_J_Subcontractor_Form_IIPP_052121.pdf PDF
DRAFT_B2_04.1_B057_Room_1026_Modular_Cleanroom_Design-Build_Requirements_053122.pdf PDF
DRAFT_B2_05_Sec_F_Deliveries_Performance.pdf PDF
DRAFT_B2_09.1_DBA_WD_CA20220018_060322_Mod_7.pdf PDF
DRAFT_B2_10.0_RFP_Section_K_Reps_and_Certs_Cover.pdf PDF
DRAFT_B2_06.2_COVID-19 Rider for Onsite_Contractors_(Nov_2021).pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contact Information POC / PM to complete

Project name

SLAC POC / PM name / phone

SLAC FCM / SM name / phone

Oct 25, 2013 SLAC-I-730-0A21T-011-R003

Work Planning and Control Summary for

Subcontractors

Work Planning and Control Summary for

Subcontractors

Notes

Life-threatening Emergency Dial 911 then call SLAC Site Security (ext. 5555 or cell 650-926-5555) and contact your supervisor / foreman immediately

Non-life-threatening Incident Contact your supervisor / foreman immediately then call SLAC Site Security (ext. 5555 or cell 650-926-5555)

Notify the POC / PM of any incident

Work Planning and Control Work planning and control (WPC) is a standardized process used at SLAC to

Understand the scope of work Identify quali�ed workers Evaluate and control hazards Communicate hazards and controls to workers Authorize, coordinate, and release work and perform it within established controls Your assigned POC / PM or designee will review our WPC process with you and assist with implementation, including helping identify permits, plans, or safety precautions that must be in place before work can begin. Examples of work that may involve additional requirements are

Electrical work Work involving hazardous energy (lockout/tagout) Hoisting and rigging Work at unprotected height greater than six feet Hot work Con�ned space entry Excavation Work in a controlled or radiologically controlled area, on accelerator shielding, or with radioactive material

Hazardous waste generation (requires storage or treatment)

Demolition Penetration of a �oor, wall, or ceiling Work that requires a mobile elevated work platform and/or powered industrial truck

Pre-job / Tailgate Brie�ngs For non-green projects, a documented brie�ng is required before the start of work to verify controls are in place.

For More Information

Chapter 42, “Subcontractor Safety”, http://www-group.slac.stanford.edu/esh/general/subcontractor/

“Worker Safety and Health Program”, http://www-group.slac.stanford.edu/esh/general/wshp/

Integrated Safety and Environmental

Management System

Integrated Safety and Environmental

Management System

Define Scope of Work

Analyze Hazards

Develop / Implement Hazard Controls

Perform Work Within Controls

Feedback and Improvement

Define Scope of Work

Analyze Hazards

Develop / Implement Hazard Controls

Perform Work Within Controls

Feedback and Improvement

Integrated Safety and Environmental Management System (ISEMS) To successfully manage risk and continually improve work processes, SLAC incorporates ISEMS into every work process. Adherence to these �ve core functions is expected.

De�ne Scope of Work Subcontractors should fully understand the scope of work provided by the SLAC project manager (PM) or point of contact (POC). Analyze Hazards

During the site visit, if one is required, you will be identifying and discussing hazards associ-ated with the scope of work and becoming more familiar with hazards you may encoun-ter on-site or in the course of your work.

Develop / Implement Hazard Controls You will develop and implement controls for identi�ed hazards.

Perform Work within Controls All workers are expected to work within estab-lished controls. Any work that is not described in the scope is considered not authorized and shall be reviewed for hazards and controls prior to commencing that activity. All workers have the authority to stop any unsafe activities.

Feedback and Improvement The central question is: "How can I do better next time?" Tell your POC or PM both what went well and what can be improved.

This will support SLAC's e�orts to continu-ously improve the work planning process in order to minimize the risk of accident, illness, or injury.