DRAFT_B2_01_Attachment_A_Request_for_Clarifications.docx

DOCX document 18 KB Posted

Attached to
SLAC Design-Build B057, Room 1026, Modular Cleanroom project
Solicitation number
329772
Issued by

View the file

Other files

File Type Posted
DRAFT_B2_04.0_RFP_Section_C_Cover.pdf PDF
DRAFT_B2_09.8_NTP_Submittal_Checklist.pdf PDF
DRAFT_B2_11.1_Section_L_B057_Modular_Cleanroom_Bid_Breakdown.xlsx XLSX spreadsheet
DRAFT_B2_09.5_Work Classification_329772.pdf PDF
DRAFT_B2_02_RFP_Section_A_(Subcontract_Award)_05.23.22_(B2).pdf PDF
DRAFT_B2_10.1_Section_K_Reps_and_Certs-Rider-Feb_2018.pdf PDF
DRAFT_B2_12.0_Section_M_Evaluation_Criteria.pdf PDF
DRAFT_B2_06.0_Section_G_(General_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.9_Final_Inspection_Report.docx DOCX document
DRAFT_B2_09.4_Section_J_Kobe.pdf PDF
DRAFT_B2_09.2_Section_J _ISEMS.pdf PDF
DRAFT_B2_06.1_FP_Construction_(Sept_2020).pdf PDF
DRAFT_B2_03_Section_B_(Supplies or Services).pdf PDF
DRAFT_B2_09.10_Final_Release.docx DOCX document
DRAFT_B2_00_RFP_Cover_Letter_329772_B057_Modular_Cleanroom_Project.pdf PDF
DRAFT_B2_08_Section_I_(Specific Subcontract Clauses).pdf PDF
DRAFT_B2_09.0_Section_J_(List_of_Attachments).pdf PDF
DRAFT_B2_09.7_SubcontractorFormSQF.pdf PDF
DRAFT_B2_11.0_Section_L_Instructions_to_Offerors.pdf PDF
DRAFT_B2_07_Section_H_(Special_Terms_and_Conditions).pdf PDF
DRAFT_B2_09.6_Section_J_SF1413-13g.pdf PDF
DRAFT_B2_09.3_Section_J_Subcontractor_Form_IIPP_052121.pdf PDF
DRAFT_B2_04.1_B057_Room_1026_Modular_Cleanroom_Design-Build_Requirements_053122.pdf PDF
DRAFT_B2_05_Sec_F_Deliveries_Performance.pdf PDF
DRAFT_B2_09.1_DBA_WD_CA20220018_060322_Mod_7.pdf PDF
DRAFT_B2_10.0_RFP_Section_K_Reps_and_Certs_Cover.pdf PDF
DRAFT_B2_06.2_COVID-19 Rider for Onsite_Contractors_(Nov_2021).pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A SLAC Question and Answer Log

RFP # 329772 B057 Modular Cleanroom Project Solicitation Clarifications

#
Date Submitted
RFP Document Reference
Request for Information
Response Date
Response
RFP Actions

June 2022