This Data Item Description (DID) provides guidelines for creating a First Article Qualification Test Plan and Procedures, with the document number DI-NDTI-81307A approved on 21 NOV 2006. The document outlines the required content for a test plan, which must include the purpose of the test, applicable documents, description of units to be tested, and detailed test description requirements.

Specific content requirements include step-by-step test procedures, operator instructions, definitions of readings and settings, test equipment descriptions, noncommercial fixture documentation, and inspection criteria. The inspection criteria must define minimum performance requirements for the test unit, covering worst-case scenarios for prime power input, signal level and timing inputs, and signal level and timing outputs. The document is meant to establish a standardized approach for contractors to follow when conducting first article qualification testing for government contracts.

View the file

Other files

File Type Posted
SPRTA1-26-R-0139.pdf PDF
Qualification Requirement.pdf PDF
Transportation-1653.pdf PDF
FA Test Plan.pdf PDF
First Article Report-Form 260.pdf PDF
Packaging-158.pdf PDF
IUID.pdf PDF
DI-NDTI-80809B.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: First Article Qualification Test Plan and Procedures

Number: DI-NDTI-81307A Approval Date: 21 NOV 2006 AMSC Number: 7649 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NS/I522 Applicable Forms: N/A

Use/relationship:

To establish test procedures, test equipment, and the inspection criteria that will be used by the contractor for first article qualification.

This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.

This DID supercedes DI-NDTI-81307.

Requirements:

1. Reference documents. None.

2. Format:

The plan shall be in the contractor’s format.

3. Content:

This test plan shall include the following:

a. Purpose of test.

b. Applicable documents.

c. Description of units to be tested.

d. Test description to include the following:

(1) Step-by-step procedures which are to be followed by the operator when performing each test.

(2) Define readings to be taken, settings to be used, and description of the test equipment, including commercial identification.

DI-NDTI-81307A

(3) Drawings, schematics, photographs, etc, of noncommercial fixtures and testers necessary for test evaluation.

e. Inspection criteria that defines the minimum performance requirements that the unit under test must meet in order to be considered acceptable to the Government. This shall include, as a minimum, worst case prime power input, worst case signal level and timing inputs, and signal level and timing outputs.

4. END OF DI-NDTI-81307A