DI-034_REV_6_HVAC_SYSTEM_REPORT.pdf
PDF 3 MB Posted
- Attached to
- NPS ISRO Ranger IV Vessel
- Solicitation number
- 140PS125R0009
About this file
This document is a Heating, Ventilation and Air Conditioning (HVAC) System Report for the Motor Vessel Ranger IV, prepared by Loch Harbour Group for the U.S. Department of Transportation. The report provides comprehensive technical details for the vessel's HVAC system design, including ventilation calculations for various ship spaces such as the engine room, crew accommodations, pilot house, and auxiliary machinery rooms. The document includes detailed calculations for air changes per hour, heat load requirements, fan capacities, and air flow volumes for different compartments, with a focus on maintaining specific temperature ranges between 64°F and 80°F across different zones.
The HVAC system is designed as a multi-zone configuration with the ability to segregate passenger and crew/cargo zones, allowing for winterization and reduced cooling/heating loads during off-peak periods. The report specifies two boiler units capable of supplying full heating load, with fan systems providing ventilation for spaces like the engine room (requiring up to 26,399 cfm), crew areas, and mechanical spaces. The system is tailored to meet the vessel's specific requirements, including ABS notations for A1 Passenger Vessel, Great Lakes Service, Ice Class IE, AMS, HAB, and COMF classifications, with provisions for temperature control in passenger accommodations, recreation spaces, and critical mechanical areas.
View the file
Other files
Show 40 more
Latest 50 of 68 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DI-034-00 Heating, Ventilation and Air Conditioning System Report Contract 6913G623P800007
Preliminary/Contract Design of Motor Vessel Ranger IV
HVAC System Report
Submitted by:
Loch Harbour Group
3060 Williams Drive, Suite 510
Fairfax, Virginia 22031
Preliminary/Contract Design of Motor Vessel Ranger IV
Contract No.: 6913G623P800007
CLIN-00100
DI-034-00 HEATING, VENTILATION AND
AIR CONDITIONING SYSTEM REPORT
Revision 6
Date: August 25, 2025
DISTRIBUTION Statement C: Distribution authorized to the U.S. Government agencies and their Contractors. Other request for this document shall be referred to US Department of Transportation Volpe Center.
DATA RIGHTS: This report, drawing, design, concept, and specification are the intellectual property of Loch Harbour
Group, LLC, and/or R.R.P CONSULTING ENGINEERS, L.L.C and contain information which is proprietary. The rights defined below are reserved by Loch Harbour Group, LLC, and/or R.R.P CONSULTING ENGINEERS, L.L.C.
The United States Government’s rights to use, modify, reproduce, release, perform, display, or disclose these technical data are unrestricted. Any reproduction of technical data or portions thereof marked with this legend must also reproduce the markings.
Preliminary/Contract Design of Motor Vessel Ranger IV
HVAC System Report
TABLE OF CONTENTS
REVISION TABLE
EXECUTIVE SUMMARY
A. DESCRIPTION
B. ATTACHMENTS
• Attachment 1 – DI-034_HVAC SYSTEM SCHEMATIC LAYOUTS
• Attachment 2 – DI-034_HVAC HEAT LOAD CALCULATIONS
• Attachment 3 – DI-034_HVAC- VENTILATION CALCULATIONS
C. REFERENCES
Preliminary/Contract Design of Motor Vessel Ranger IV
REVISION TABLE
HVAC System Report
REVISION DESCRIPTION DATE AUTHOR
0 Initial submission 04-19-2024 RRP 1 Updated to address government comments 07-26-2024 RRP 2 Updated to address government comments 08-13-2024 RRP 3 Updated to address government comments 08-28-2024 RRP 4 Updated to address Park comments 09-18-2024 RRP 5 Updated report and drawings 07-09-2025 VOLPE 6 Updated drawings 08-25-2025 VOLPE
Preliminary/Contract Design of Motor Vessel Ranger IV
HVAC System Report
EXECUTIVE SUMMARY
This document is submitted by Loch Harbour Group, 3060 Williams Drive, Suite 510, Fairfax, Virginia 22031, to satisfy CLIN 00100 DI-034-00 Heating, Ventilation and Air Conditioning
System Report, of Contract No. 6913G623P800007.
The purpose of this report will be to explain the level of details provided in the drawing along with the supporting calculations and representing the salient features and components of each HVAC system.
The report shall define the overall system configuration and will include preliminary supporting calculations for major system components, and system performance capability for each HVAC system in the next design phase.
Drawings have been prepared for each HVAC system identifying equipment and components, preliminary duct sizes, and material schedule for the next design phase.
The vessel shall be designed to have A1, Passenger Vessel, Great Lakes Service, Ice Class IE, AMS, HAB and COMF notations as per ABS.
Government REVIEW and COMMENT of this report is REQUIRED.
A. DESCRIPTION
Mechanical ventilation systems shall be provided in machinery spaces, crew accommodation areas, cargo areas, passenger spaces and other compartments or voids containing navigation and electronic equipment.
Individual and combined supply/exhaust fans were both incorporated in the design. Individual supply/exhaust fans were provided for the Aux machinery room, battery room, Engine room, main passenger deck 01 (level) and pilot house deck (02 level). Spaces other than those mentioned above have various combined supply/ exhaust fans based on the requirement.
The HVAC system is a multi-zone system capable of providing an adjustable range of air temperatures between 64 °F (17 °C) and 80 °F (26.5 °C). The system is split into passenger zones and crew/cargo zones. These zones shall have the ability to be segregated and allow for winterization to reduce the amount of cooling and heating load during winter lay-up months or periods without passengers and minimal crew. In all passenger accommodation and recreation spaces the temperature shall be maintained by temperature controllers. The Contractor shall be responsible for completing the detail design, final component selection and system commissioning. The installation shall be completed to the satisfaction of the NPS or their representative.
Preliminary/Contract Design of Motor Vessel Ranger IV
HVAC System Report
Table 1: Indoor Climate Requirements
Max. Summer Temp.
Limit
Relative Humidity Min. Winter Temp.
Limit
Living Quarters 73.5 ºF 30%-70% 72 ºF
Pilot House 72 ºF 30%-70% 64 ºF
Kitchen 86 ºF 30%-70% 64 ºF
The following spaces shall be temperature controlled via the HVAC system.
a) Pilothouse
b) All Crew Accommodations
c) Passenger Processing Area
d) Passenger Lounges
e) Passenger Heads
f) Passageways
g) Guest Staterooms
h) Engineering Compartment (ECR, Workshop, Engine Room)
i) Battery Room
j) Spaces containing main and ship service switchboards, and propulsion and thruster variable speed drives and converters, if installed.
k) IT Closet and other compartments or voids containing navigation and electronic equipment.
The air conditioning system, boiler units and electrical heaters provided shall be capable of maintaining the indoor climate requirements outlined in Table 1 and have the ability to isolate/winterize during the off season.
For Ranger IV, the Air Conditioning system is required to operate during the summer months when temperatures near the ports and islands rise rapidly. The system's capacity will be accurately determined during the Detailed Design and Construction (DD&C) phase with assistance from a specialized vendor.
Two boiler units (main and auxiliary) shall be provided. The boiler units shall be fuel fired and heat water in hydronic loops through individual HVAC zones. Each boiler unit shall be capable of supplying the full heating load of the vessel's hydronic heating system.
The heating system shall be capable of maintaining the indoor climate requirements outlined in Table 1 and have the ability to isolate/winterize.
Electric heaters may be incorporated in cargo or machinery areas for supplemental heating. Use of any electric heaters to satisfy climate requirements shall be approved by the NPS or their representative.
Preliminary/Contract Design of Motor Vessel Ranger IV
HVAC System Report
The below HVAC system depicts the major components with salient characteristics, preliminary ducting size, major vent trunks, space requirements and locations.
These calculations were performed based on preliminary inputs from available vendor information. The AC system's capacity will be determined during the Detailed Design and
Construction (DD&C) phase, which falls within the vendor's scope of work. Consequently, the relevant calculations and drawings are not included in this report.
B. ATTACHMENTS
The following serves as supporting documentation for this report.
• Attachment 1 – DI-034_HVAC SYSTEM SCHEMATIC LAYOUTS
• Attachment 2 – DI-034_HVAC HEAT LOAD CALCULATIONS
• Attachment 3 – DI-034_HVAC- VENTILATION CALCULATIONS
C. REFERENCES
• Appendix B - NPS VOLPE Ranger IV Basis of Design
• SNAME TECHNICAL AND RESEARCH BULLETIN
DISTRIBUTION Statement C: Distribution authorized to the U.S.
Government agencies and their Contractors. Other request for this document shall be referred to US Department of Transportation Volpe Center.
This report, drawing, design, concept, and specification are the intellectual property of Loch Harbour Group, LLC, and/or R.R.P CONSULTING ENGINEERS, L.L.C and contain information which is proprietary. The rights defined below are reserved by Loch Harbour Group, LLC, and/or R.R.P CONSULTING ENGINEERS, L.L.C. The United States Government’s rights to use, modify, reproduce, release, perform, display, or disclose these technical data are unrestricted. Any reproduction of technical data or portions thereof marked with this legend must also reproduce the markings.
SS
E E
65 60 55 50 45 40 35 30 25 20 15 10
UP
S S S S S
S
S S
S S S S S S S S S
E E E E
E
S
S S S S S S
E
70 65 60 55 50 45 40 35 30 25 20 15
DN
DNC
O N
SO
LE
E E
E E
E E
E E
E E
E
E E
EEEEEEEEEEEEEEEEEEEEEEE
EE
E
E
S
E E
S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S
S S
S S
S
S
S S
S S
S
S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S
S S
S S
S S
S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S S
S
SSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSS
S
S S
S
SSSSSS
S S S S S
E
EEEEEEEEEEEEEE
S S
SSSSSSSSSSSSS
S S
S S
S S
S
S EEEEE
E E
E E
E E
E E
S S S S S S S S S S S S
S S
S S
E E E E E E E E E E E E
E E
E E
E E
E
E
E E
E E
E E
E E
E
UPDN
55 50 45 40 35 30 25 20 15 10 5 34
UP
UPDN
D N
S S
S S
S S
S S
SS
E
E E
E
S
S S
S S
S S
S
E
E E
E E
E E
E E
E E
EEEEEEEEEEE
S S
S S
S S
S S S S S S S S S S S S S S S S S S S S S S S S S S S S
S
60 55 50 45 40 35 30 25 20 15 10
DN UP
UP
DN
DN
EEEEEEEEEEEEE
E E
E E
E
E E E E E E E
E E
E E
E E
E
S S S S S S S S S S S S S S S S S S S S S S S S S S S
S S
S S
S S
S
60 55 50 45 40 35 30 25 20 15 10
DN
DN
DN
UP
DN
EEEEEEEEEEE
E
E
E
S S S S S S S S
SSSSSSSSSSSSSSSSS
S S
S S
S S
S S
S
S S
S
S S
S S
S S
S S
S
S S
S S
S
E E
E E
E E
E
E
S S
S S
S S
E E
R.R.P CONSULTING ENGINEERS, L.L.C
HEAT LOAD CALCULATIONS
REPORT
(RANGER IV)
PROJECT NO. 1277
Rev. 0
06-18-2024
This report, drawing, design, concept, and specification are the intellectual property of Loch
Harbour Group, LLC, and/or R.R.P CONSULTING ENGINEERS, L.L.C and contain information which is proprietary. The rights defined below are reserved by Loch Harbour Group, LLC, and/or R.R.P
CONSULTING ENGINEERS, L.L.C. The United States Government’s rights to use, modify, reproduce, release, perform, display, or disclose these technical data are unrestricted. Any reproduction of technical data or portions thereof marked with this legend must also reproduce the markings.
DI-034-00
Page13
LEGEND:
A = Boundary Area ft²
Q s = Head Load, Sensible Btu/hr
Q L = Heat Load, Latent Btu/hr
Q T = Heat Load, Total Btu/hr
Q W = Heat Load, Winter Btu/hr
U = Heat Transfer Coefficient Btu/hr/ft²
T = Space Design Temp. °F
T O = Temp. of Adjacent space/ Outside °F
∆T = Temperature Difference °F
SHF = Sensible Heat Fetor
LOAD KEY:
1 = Deck Over
2 = Deck Under
3 = Outboard Bulkhead/ Shell
4 = Forward Bulkhead
5 = Aft Bulkhead
6 = Inboard Bulkhead
7 = Lights
8 = Equipments
9 = Personnel
10 = Infiltration
KEY
Project Title:
1277- RANGER IV
Proj. no:
Subject:
HEAT LOAD CALCULATIONS
Date:
06-18-24
SYMBOLS
DI-034-00
Page1
Page14
73.5 °F 72 °F
Coeff Dir Coeff Dir Fwd Bhd-P.way 4 5 244.2 - - - ↔ - - - 20.0 52.0 0.354 ↔ 4495.2
Fwd Bhd-CL GR LKR 4 65 199.3 - - - ↔ - - - 18.0 54.0 0.200 ↔ 2152.7
Side Shell(P)-Solar 3 63 422.4 - - - ↔ - - - 17.6 54.4 0.900 ↔ 20680.7
Side Shell(S)-Solar 3 63 422.4 - - - ↔ - - - 17.6 54.4 0.900 ↔ 20680.7
Aft Bhd-Engine control room 5 65 196.7 - - - ↔ - - - 18.0 54.0 0.200 ↔ 2124.1
Aft Bhd-Crane pedestal 5 5 52.8 - - - ↔ - - - 17.6 54.4 0.354 ↔ 1016.8
Aft Bhd-Engineers Workshop 5 65 196.7 - - - ↔ - - - 18.0 54.0 0.200 ↔ 2124.1
Deck over-solar 1 63 1070.2 - - - ↑ - - - 17.6 54.4 0.900 ↓ 52397.0
Deck under-Inner bottom 2 63 1070.2 - - - ↓ - - - 17.6 54.4 0.200 ↑ 11643.8
Transmission Sub Total 0 0 0 117315
Lights (L.C=7) 1070.2 7491.4 0 7491.4
Equipment 12398.5 0 12398.5
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2ND DECK - HEAT LOAD CALCULATIONS
Date:
06-18-24
SPACE: ENGINE ROOM COOLING SEASON: T = HEATING SEASON: T =
T O ∆TAdjacent compartment Load key
Insul key
A T O ∆T U
QW
U
Q s Q L Q T
Page15
Personnel (2) 530 670 1200.0
Sensible Heat Sub Total 20420 117315
Latent Heat Sub Total 670
Total Heat (Btu/hr) 21090 117315
Total Heat (kW) 6.2 34.4
SHF= 0.968
Heat Load Total QW = 117315 BTU/hr
= 34.4 kW
Required Boiler Capacity = 34.4 kW
Notes: Glass solar Load = 160 Btu/hr/ft² x 0 =0 BTU/HR
Boiler requirement
Page16
Fwd Bhd-Engine room 4 5 113.2 - - - ↔ - - - 18 54.0 0.200 ↔ 1222.99
Side Shell(P)-Solar 3 63 118.6 - - - ↔ - - - 17.6 54.4 0.900 ↔ 5804.70
Aft Bhd-Ballast 5 65 40.3 - - - ↔ - - - 18 54.0 0.200 ↔ 435.02
Aft Bhd-Steering Gear 5 65 7.6 - - - ↔ - - - 18 54.0 0.200 ↔ 82.08 outboard Bhd-Engineers Workshop5 65 4.6 - - - ↔ - - - 20 52.0 0.200 ↔ 47.42 outboard Bhd-DEF tank 5 65 4.6 - - - ↔ - - - 20 52.0 0.200 ↔ 47.42 outboard Bhd-Crane Pedestal 5 65 3.0 - - - ↔ - - - 17.6 54.4 0.200 ↔ 33.08
Deck over-solar 1 63 229.5 - - - ↑ - - - 17.6 54.4 0.11 ↓ 1373.33
Deck under-Inner bottom 2 63 229.5 - - - ↓ - - - 17.6 72.0 0.354 ↑ 5849.50
Transmission Sub Total 0 0 0 14896
Lights (L.C=7) 229.5 1606.5 0 1606.5
Equipment 2000.0 0 2000.0
Personnel (2) 530 670 1200.0
Sensible Heat Sub Total 4137 14896
Latent Heat Sub Total 670
Total Heat (Btu/hr) 4807 14896
Total Heat (kW) 1.4 4.4
Q s Q L Q T
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2ND DECK - HEAT LOAD CALCULATIONS
Date:
06-18-24
SPACE: ENGINE CONTROL ROOM COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment QWT O ∆T ULoad key Insul key
A T O ∆T U
Page17
SHF= 0.861
Heat Load Total QW = 14896 BTU/hr = 4.4 kW
Required Boiler Capacity = 4.4 kW
Notes: Glass solar Load = 160 Btu/hr/ft² x 0 =0 BTU/HR
Boiler requirement
Page18
Fwd Bhd-Engine room 4 5 113.2 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1223.0
Side Shell(P)-Solar 3 63 118.6 - - - ↔ - - - 17.6 54.4 0.900 ↔ 5804.7
Aft Bhd-Steering Gear 5 65 140.6 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1518.5 outboard Bhd-Engine Control Room4 5 45.6 - - - ↔ - - - 18.0 54.0 0.200 ↔ 492.5 outboard Bhd-DEF tank 5 65 4.6 - - - ↔ - - - 18.0 54.0 0.200 ↔ 49.2 outboard Bhd-Crane Pedestal 5 65 3.0 - - - ↔ - - - 17.6 54.4 0.200 ↔ 33.1
Deck over-solar 1 63 250.4 - - - ↑ - - - 17.6 54.4 0.11 ↓ 1498.4
Deck under-Inner bottom 2 63 250.4 - - - ↓ - - - 17.6 54.4 0.354 ↑ 4822.1
Transmission Sub Total - - - 15441
Lights (L.C=7) 250.4 1752.8 0 1752.8
Equipment 1000.0 0 1000.0
Personnel (2) 530 670 1200.0
Sensible Heat Sub Total 3283 15441
Latent Heat Sub Total 670
Total Heat (Btu/hr) 3953 15441
Total Heat (kW) 1.2 4.5
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2ND DECK - HEAT LOAD CALCULATIONS
Date:
06-18-24
QW
HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
SPACE: ENGINEERS WORKSHOP COOLING SEASON: T =
Page19
SHF= 0.830
Heat Load Total QW = 15441 BTU/hr = 4.5 kW
Required Boiler Capacity = 4.5 kW
Notes: Glass solar Load = 160 Btu/hr/ft² x 0 =0 BTU/HR
Boiler requirement
Page20
79.0 °F 72 °F
Aft Bhd- State Room 5 65 18.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 202.5
Inboard Bhd-T/S 6 5 13.6 - - - ↔ - - - 18.5 53.5 0.354 ↔ 257.6
Inboard Bhd-T/S 6 5 9.4 - - - ↔ - - - 18.5 53.5 0.354 ↔ 178.7
Aft Bhd-T/S 5 5 52.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 994.3
Inboard Bhd-P.way 6 5 44.3 - - - ↔ - - - 20.0 52.0 0.354 ↔ 814.6
Fwd Bhd-Bosuns Stores 5 65 57.0 - - - ↔ - - - 18.0 54.0 0.200 ↔ 615.6
Side Shell(P)-Solar 3 63 70.6 - - - ↔ - - - 17.6 54.4 0.900 ↔ 3458.1
Side Shell(P)-Solar 3
GLAS
S
2.12 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Deck Under- Un Assigned storage
2 92 56.0 - - - ↑ - - - 18.0 54.0 0.092 ↓ 278.0
Deck Over -P.Proce.area 1 92 56.0 - - - ↓ - - - 18.0 54.0 0.940 ↑ 2840.0
Transmission Sub Total - - - 9461
Lights (L.C=7) 7 56.0 391.7 0 391.7 0
Equipment 8 0.0 0 0.0 0
Personnel (2) 9 530 670 1200.0 0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEAT LOAD CALCULATIONS
Date:
06-18-24
SPACE: STATE ROOM (FR 14 to 19-PORT ) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
QW
Page21
Sensible Heat Sub Total 922 9461
Latent Heat Sub Total 670 0
Total Heat (Btu/hr) 1592 9461
Total Heat (kW) 0 3
SHF= 0.579
Heat Load Total QW = 9461 BTU/hr = 2.8 kW
Required Boiler Capacity = 2.8 kW
Boiler requirement
Notes: Glass solar Load = 160 Btu/hr/ft² x 2.12 =339.2 BTU/HR
Page22
Aft Bhd-State room 5 65 87.0 - - - ↔ - - - 18.0 54.0 0.200 ↔ 939.6
Inboard Bhd-T/S 6 5 15.9 - - - ↔ - - - 18.5 53.5 0.354 ↔ 301.1
Fwd Bhd-T/S 4 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard Bhd-P.way 6 5 39.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 717.9
Fwd Bhd-State Room 4 65 18.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 202.5
Side Shell(P)-Solar 3 63 60.1 - - - ↔ - - - 17.6 54.4 0.090 ↔ 294.4
Deck Under- Un Assigned storage 2 92 65.3 - - - ↑ - - - 18.0 54.0 0.920 ↓ 3244.1
Deck Over -P.Proce.area 1 92 65.3 - - - ↓ - - - 18.0 54.0 0.940 ↑ 3314.6 solar 3 Glass 2.1 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Transmission Sub Total - - - 10080
Lights (L.C=7) 7 65.3 457.1 0 457.1
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Sensible Heat Sub Total 987 10080
Latent Heat Sub Total 670
Project Title:
1277 - RANGER IV Proj. no:
Subject:
2nd DECK - HEAT LOAD CALCULATIONS Date:
06-18-24
SPACE: STATE ROOM (FR 19 to 23-PORT ) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
QW
Page23
Total Heat (Btu/hr) 1657 10080
Total Heat (kW) 0.5 3.0
SHF= 0.596
Heat Load Total QW = 10080 BTU/hr = 3.0 kW
Required Boiler Capacity = 3.0 kW
Boiler requirement
Notes: Glass solar Load = 160 Btu/hr/ft² x 2.1 = 339.2 BTU/HR
Page24
Side Shell(P)-Solar 3 63 54.8 - - - ↔ - - - 17.6 54.4 0.090 ↔ 268.1
Fwd Bhd-State Room 4 65 23.3 - - - ↔ - - - 18.0 54.0 0.200 ↔ 251.1
Aft Bhd(P)-Meeting room 5 65 39.6 - - - ↔ - - - 18.0 54.0 0.200 ↔ 427.7
Inboard aft Bhd-Meeting room 6 65 3.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 40.5
Aft Bhd(P)-Meeting room 5 65 58.5 - - - ↔ - - - 18.0 54.0 0.200 ↔ 631.8
Inboard Bhd-P.way 6 5 27.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 497.0
Inboard Bhd-T/S 6 5 23.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 440.3
Fwd Bhd-T/S 4 5 58.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1107.9
Deck Under- Battery room 2 92 63.9 - - - ↑ - - - 18.0 54.0 0.920 ↓ 3174.6
Deck Over -Interior Cargo Space 1 92 20.2 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1023.8
Deck Over -T/S 1 92 46.8 - - - ↓ - - - 18.5 53.5 0.940 ↑ 2353.6
Deck Over -P.way 1 92 17.6 - - - ↓ - - - 20.0 52.0 0.940 ↑ 860.3
Transmission Sub Total - - - 11077
Lights (L.C=7) 7 84.6 592.0 0 592.0
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEAT LOAD CALCULATIONS
Date:
06-18-24
SPACE: STATE ROOM (FR 23 to 26.5-PORT ) COOLING SEASON: T = HEATING SEASON: T =
T O ∆T U
QW∆T
U
Q s Q L Q TAdjacent compartment Load key
Insul key
A T O
Page25
Sensible Heat Sub Total 1122 11077
Latent Heat Sub Total 670
Total Heat (Btu/hr) 1792 11077
Total Heat (kW) 0.5 3.2
SHF= 0.626
Heat Load Total QW = 11077 BTU/hr = 3.2 kW
Required Boiler Capacity = 3.2 kW
Boiler requirement
Page26
Aft Bhd-Crew Lounge 5 65 102.0 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1101.6
Side Shell(P)-Solar 3 63 50.3 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2460.2
Inboard Bhd-P.Way 6 5 45.8 - - - ↔ - - - 20.0 52.0 0.354 ↔ 843.5
Fwd Bhd-Stater room 4 65 39.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 429.3
Fwd Bhd-Inboard meeting room
4 65 3.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 40.5
Fwd Bhd-Stater room 4 65 57.0 - - - ↔ - - - 18.0 54.0 0.200 ↔ 615.6
Deck Under- Battery room 2 92 72.8 - - - ↑ - - - 18.0 54.0 0.092 ↓ 361.7
Deck Over -Interior Cargo Space 1 92 76.5 - - - ↓ - - - 18.0 54.0 0.940 ↑ 3883.1
Deck Over -P.way 1 92 13.3 - - - ↓ - - - 20.0 52.0 0.940 ↑ 650.1
Transmission Sub Total - - - 10386
Lights (L.C=7) 7 89.8 628.6 0 628.6
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Sensible Heat Sub Total 1159 10386
Latent Heat Sub Total 670
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: MEETING ROOM (FR 26.5 to 30.5 -PORT) COOLING SEASON: T = HEATING SEASON: T =
Project Title:
1277 - RANGER IV
T O ∆T U
QW∆T
U
Q s Q L Q TAdjacent compartment Load key
Insul key
A T O
Page27
Total Heat (Btu/hr) 1829 10386
Total Heat (kW) 0.5 3.0
SHF= 0.634
Heat Load Total QW = 10386 BTU/hr = 3.0 kW
Required Boiler Capacity = 3.0 kW
Boiler requirement
Page28
Aft Bhd(P)-Officer 5 65 108.0 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1166.4
Side Shell(P)-Solar 3 63 67.5 - - - ↔ - - - 17.6 54.4 0.900 ↔ 3304.8
Inboard Bhd-P.Way 6 5 67.5 - - - ↔ - - - 20.0 52.0 0.354 ↔ 1242.5
Fwd Bhd-Meeting room 4 65 102.0 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1101.6
Deck Under- Battery room 2 92 102.8 - - - ↑ - - - 18.0 54.0 0.092 ↓ 510.7
Deck Over -Interior Cargo Space
1 92 124.9 - - - ↓ - - - 18.0 54.0 0.940 ↑ 6339.9
Transmission Sub Total - - - 13666
Lights (L.C=9) 7 124.9 1124.1 0 1124.1
Equipment (Refrigerator) 8 1300.0 0 1300.0
Personnel (10) 9 2650 3350 6000.0
Sensible Heat Sub Total 5074 13666
Latent Heat Sub Total 3350
Total Heat (Btu/hr) 8424 13666
Total Heat (kW) 2.5 4.0
SHF= 0.602
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE:CREW LOUNGE (FR 30.5 to 35-PORT ) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
QW
Page29
Heat Load Total QW = 13666 BTU/hr = 4.0 kW
Required Boiler Capacity = 4.0 kW
Boiler requirement
Page30
Aft Bhd-Crew 5 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Side Shell(P)-Solar 3 63 75.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 3672.0
Fwd Bhd - Crew Lounge 4 65 52.1 - - - ↔ - - - 18.0 54.0 0.200 ↔ 563.0
Fwd Bhd-T/S 4 5 63.8 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1207.4
Fwd Bhd-T/S inboard 4 5 25.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 482.9
Inboard Bhd-P.way 6 5 49.5 - - - ↔ - - - 20.0 52.0 0.354 ↔ 911.2
Deck Under-Sewage/grey water tank2 92 10.5 - - - ↑ - - - 18.0 54.0 0.092 ↓ 52.2
Deck Under-Fresh water tank 2 92 14.5 - - - ↑ - - - 18.0 54.0 0.092 ↓ 72.0
Deck Under-walk path/grating 2 92 72.9 - - - ↑ - - - 18.0 54.0 0.092 ↓ 362.1
Deck Over -Ref.Space 1 92 29.9 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1517.7
Deck Over -Interior Cargo Space
1 92 88.0 - - - ↓ - - - 18.0 54.0 0.940 ↑ 4466.7
Transmission Sub Total - - - 14514
Lights (L.C=7) 7 117.9 825.3 0 825.3
Equipment 8 0.0 0 0.0
Personnel (1) 9 265 335 600.0
Sensible Heat Sub Total 1090 14514
Latent Heat Sub Total 335
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: OFFICER (FR 35 to 40- PORT) COOLING SEASON: T = HEATING SEASON: T =
Q T T O ∆T U
QWAdjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L
Page31
Total Heat (Btu/hr) 1425 14514
Total Heat (kW) 0.4 4.3
SHF= 0.765
Heat Load Total QW = 14514 BTU/hr = 4.3 kW
Required Boiler Capacity = 4.3 kW
Boiler requirement
Page32
Aft Bhd-Crew 5 65 55.2 - - - ↔ - - - 18.0 54.0 0.200 ↔ 596.2
Side Shell(P)-Solar 3 63 60.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2937.6
Fwd Bhd - officer 4 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Inboard Bhd-P.Way 6 5 36.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 662.7
Aft Bhd-T/S 5 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard -T/S 6 5 22.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 426.1
Deck Under-Do Tk. 2 92 36.0 - - - ↑ - - - 18.0 54.0 0.092 ↓ 178.8
Deck Under-Sewage/grey water tank2 92 11.9 - - - ↑ - - - 18.0 54.0 0.092 ↓ 59.1
Deck Under-walk way 2 92 32.6 - - - ↑ - - - 18.0 54.0 0.092 ↓ 162.0
Deck Over -Ref.Space 1 92 35.3 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1791.8
Deck Over -Interior Cargo Space
1 92 55.8 - - - ↓ - - - 18.0 54.0 0.940 ↑ 2832.4
Transmission Sub Total - - - 11919
Lights (L.C=4) 7 91.1 364.4 0 364.4
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: CREW (FR 40 to 44 - PORT) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
QW
Page33
Sensible Heat Sub Total 894 11919
Total Heat (Btu/hr) 1564 11919
Total Heat (kW) 0.5 3.5
SHF= 0.572
Heat Load Total QW = 11919 BTU/hr = 3.5 kW
Required Boiler Capacity = 3.5 kW
Boiler requirement
Page34
Aft Bhd-Crew 5 65 55.2 - - - ↔ - - - 18.0 54.0 0.200 ↔ 596.2
Side Shell(P)-Solar 3 63 60.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2937.6
Fwd Bhd - crew 4 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Inboard Bhd-P.Way 6 5 36.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 662.7
Aft Bhd-T/S 5 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard -T/S 6 5 22.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 426.1
Deck Under-Do Tk. 2 92 47.2 - - - ↑ - - - 18.0 54.0 0.092 ↓ 234.5
Deck Under-walk way 2 92 33.4 - - - ↑ - - - 18.0 54.0 0.092 ↓ 165.8
Deck Over -Ref.Space 1 92 35.3 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1791.8
Deck Over -Interior Cargo Space
1 92 55.8 - - - ↓ - - - 18.0 54.0 0.940 ↑ 2832.4
Transmission Sub Total - - - 11919
Lights (L.C=4) 7 91.1 364.4 0 364.4
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Sensible Heat Sub Total 894 11919
Latent Heat Sub Total 670
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: CREW (FR 44 to 48 - PORT) COOLING SEASON: T = HEATING SEASON: T =
Q T T O ∆T U
QWAdjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L
Page35
Total Heat (Btu/hr) 1564 11919
Total Heat (kW) 0.5 3.5
SHF= 0.572
Heat Load Total QW = 11919 BTU/hr = 3.5 kW
Required Boiler Capacity = 3.5 kW
Boiler requirement
Page36
Aft Bhd-P.way 5 5 55.2 - - - ↔ - - - 20.0 52.0 0.354 ↔ 1016.1
Side Shell(P)-Solar 3 63 60.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2937.6
Fwd Bhd - crew 4 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Inboard Bhd-P.Way 6 5 36.0 - - - ↔ - - - 18.0 54.0 0.354 ↔ 688.2
Aft Bhd-T/S 5 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard -T/S 6 5 22.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 426.1
Deck Under-Do Tk. 2 92 14.3 - - - ↓ - - - 18.0 54.0 0.940 ↑ 725.9
Deck Under-bunker Tk. 2 92 4.4 - - - ↓ - - - 18.0 54.0 0.940 ↑ 223.3
Deck Under-walk way 2 92 61.8 - - - ↓ - - - 18.0 54.0 0.092 ↓ 307.0
Deck Over -Interior Cargo Space
1 92 91.1 - - - ↑ - - - 18.0 54.0 0.092 ↓ 452.6
Transmission Sub Total - - - 9049
Lights (L.C=4) 7 91.1 364.4 0 364.4
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: CREW (FR 48 to 52 - PORT) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
QW
Page37
Sensible Heat Sub Total 894 9049
Total Heat (Btu/hr) 1564 9049
Total Heat (kW) 0.5 2.7
SHF= 0.572
Heat Load Total QW = 9049 BTU/hr = 2.7 kW
Required Boiler Capacity = 2.7 kW
Boiler requirement
Page38
Aft Bhd-CL GR LKR 5 5 55.2 - - - ↔ - - - 18.0 54.0 0.354 ↔ 1055.2
Side Shell(P)-Solar 3 63 60.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2937.6
Fwd Bhd - crew 4 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Inboard Bhd-P.Way 6 5 36.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 662.7
Aft Bhd-T/S 5 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard -T/S 6 5 22.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 426.1
Deck Under-Do Tk. 2 92 14.3 - - - ↑ - - - 18.0 54.0 0.092 ↓ 71.0
Deck Under-bunker Tk. 2 92 4.4 - - - ↑ - - - 18.0 54.0 0.092 ↓ 21.9
Deck Under-walk way 2 92 61.8 - - - ↑ - - - 18.0 54.0 0.092 ↓ 307.0
Deck Over -Interior Cargo Space
1 92 91.1 - - - ↓ - - - 18.0 54.0 0.940 ↑ 4624.2
Transmission Sub Total - - - 12378
Lights (L.C=4) 7 91.1 364.4 0 364.4
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: CREW (FR 48 to 52 - STBD) COOLING SEASON: T = HEATING SEASON: T =
Q T T O ∆T U
QWAdjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L
Page39
Sensible Heat Sub Total 894 12378
Total Heat (Btu/hr) 1564 12378
Total Heat (kW) 0.5 3.6
SHF= 0.572
Heat Load Total QW = 12378 BTU/hr = 3.6 kW
Required Boiler Capacity = 3.6 kW
Boiler requirement
Page40
Aft Bhd-Crew 5 65 55.2 - - - ↔ - - - 18.0 54.0 0.200 ↔ 596.2
Side Shell(P)-Solar 3 63 60.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2937.6
Fwd Bhd - crew 4 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Inboard Bhd-P.Way 6 5 36.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 662.7
Aft Bhd-T/S 5 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard -T/S 6 5 22.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 426.1
Deck Under-Do Tk. 2 92 47.2 - - - ↑ - - - 18.0 54.0 0.092 ↓ 234.5
Deck Under-walk way 2 92 55.4 - - - ↑ - - - 18.0 54.0 0.092 ↓ 275.1
Deck Over -Ref.Space 1 92 35.3 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1791.8
Deck Over -Interior Cargo Space
1 92 78.0 - - - ↓ - - - 18.0 54.0 0.940 ↑ 3957.2
Transmission Sub Total - - - 13153
Lights (L.C=4) 7 113.3 453.0 0 453.0
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: CREW (FR 44 to 48 - STBD) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
QW
Page41
Sensible Heat Sub Total 983 13153
Total Heat (Btu/hr) 1653 13153
Total Heat (kW) 0.5 3.9
SHF= 0.595
Heat Load Total QW = 13153 BTU/hr = 3.9 kW
Required Boiler Capacity = 3.9 kW
Boiler requirement
Page42
Aft Bhd-Crew 5 65 55.2 - - - ↔ - - - 18.0 54.0 0.200 ↔ 596.2
Side Shell(P)-Solar 3 63 60.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2937.6
Fwd Bhd - officer 4 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Inboard Bhd-P.Way 6 5 36.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 662.7
Aft Bhd-T/S 5 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard -T/S 6 5 22.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 426.1
Deck Under-Do Tk. 2 92 36.0 - - - ↑ - - - 18.0 54.0 0.092 ↓ 178.8
Deck Under-Sewage/grey water tank2 92 11.9 - - - ↑ - - - 18.0 54.0 0.092 ↓ 59.1
Deck Under-walk way 2 92 53.4 - - - ↑ - - - 18.0 54.0 0.092 ↓ 265.3
Deck Over -Ref.Space 1 92 35.3 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1791.8
Deck Over -Interior Cargo Space
1 92 78.0 - - - ↓ - - - 18.0 54.0 0.940 ↑ 3957.2
Transmission Sub Total - - - 13147
Lights (L.C=4) 7 113.3 792.8 0 792.8
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: CREW (FR 40 to 44 - STBD) COOLING SEASON: T = HEATING SEASON: T =
Q T T O ∆T U
QWAdjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L
Page43
Sensible Heat Sub Total 1323 13147
Total Heat (Btu/hr) 1993 13147
Total Heat (kW) 0.6 3.9
SHF= 0.664
Heat Load Total QW = 13147 BTU/hr = 3.9 kW
Required Boiler Capacity = 3.9 kW
Boiler requirement
Page44
Aft Bhd-Crew 5 65 111.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1206.9
Side Shell(P)-Solar 3 63 75.0 - - - ↔ - - - 17.6 54.4 0.900 ↔ 3672.0
Fwd Bhd - Crew Lounge 4 65 52.1 - - - ↔ - - - 18.0 54.0 0.200 ↔ 563.0
Fwd Bhd-T/S 4 5 63.8 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1207.4
Fwd Bhd-T/S inboard 4 5 25.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 482.9
Inboard Bhd-P.way 6 5 49.5 - - - ↔ - - - 20.0 52.0 0.354 ↔ 911.2
Deck Under-Sewage/grey water tank2 92 10.5 - - - ↑ - - - 18.0 54.0 0.092 ↓ 52.2
Deck Under-Fresh water tank 2 92 14.5 - - - ↑ - - - 18.0 54.0 0.092 ↓ 72.0
Deck Under-walk path/grating 2 92 72.9 - - - ↑ - - - 18.0 54.0 0.092 ↓ 362.1
Deck Over -Ref.Space 1 92 29.9 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1517.7
Deck Over -Interior Cargo Space
1 92 88.0 - - - ↓ - - - 18.0 54.0 0.940 ↑ 4466.7
Transmission Sub Total - - - 14514
Lights (L.C=7) 7 117.9 825.3 0 825.3
Equipment 8 0.0 0 0.0
Personnel (1) 9 265 335 600.0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: OFFICER (FR 35 to 40- STBD) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
QW
Page45
Sensible Heat Sub Total 1090 14514
Latent Heat Sub Total 335
Total Heat (Btu/hr) 1425 14514
Total Heat (kW) 0.4 4.3
SHF= 0.765
Heat Load Total QW = 14514 BTU/hr = 4.3 kW
Required Boiler Capacity = 4.3 kW
Boiler requirement
Page46
Aft Bhd-Crew Galley 5 65 63.4 - - - ↔ - - - 18.0 54.0 0.200 ↔ 684.5
Side Shell(S)-Solar 3 63 97.5 - - - ↔ - - - 17.6 54.4 0.900 ↔ 4773.6
Aft Bhd - Officer 5 65 106.5 - - - ↔ - - - 18.0 54.0 0.200 ↔ 1150.2
Inboard Bhd-P.Way 6 5 57.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 1049.3
Inboard Bhd-P.Way 6 5 33.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 607.5
Inboard Bhd-P.Way 6 5 39.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 717.9
Deck Under-battery room 2 92 120.6 - - - ↑ - - - 18.0 54.0 0.092 ↓ 599.3
Deck Over -Freezer 1 92 33.3 - - - ↓ - - - 18.0 54.0 0.940 ↑ 1690.3
Deck Over -Cargo Space 1 92 83.7 - - - ↓ - - - 18.0 54.0 0.940 ↑ 4247.1
Transmission Sub Total - - - 15520
Lights (L.C=7) 7 117.0 818.8 0 818.8
Equipment 8 0.0 0 0.0
Personnel (1) 9 265 335 600.0
Sensible Heat Sub Total 1084 15520
Latent Heat Sub Total 335
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: CREW DINING (FR 28.5 to 35- STBD) COOLING SEASON: T = HEATING SEASON: T =
Q T T O ∆T U
QWAdjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L
Page47
Total Heat (Btu/hr) 1419 15520
Total Heat (kW) 0.4 4.5
SHF= 0.764
Heat Load Total QW = 15520 BTU/hr = 4.5 kW
Required Boiler Capacity = 4.5 kW
Boiler requirement
Page48
Aft Bhd-P.way 5 5 32.3 - - - ↔ - - - 20.0 52.0 0.354 ↔ 593.7
Aft Bhd-Crew galley 5 65 54.8 - - - ↔ - - - 18 54.0 0.200 ↔ 591.3
Inboard Bhd-T/S 6 5 15.9 - - - ↔ - - - 18.5 53.5 0.354 ↔ 301.1
Fwd Bhd-T/S 4 5 56.3 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1065.3
Inboard Bhd-P.way 6 5 39.0 - - - ↔ - - - 20 52.0 0.354 ↔ 717.9
Fwd Bhd-State Room 4 65 18.8 - - - ↔ - - - 18 54.0 0.200 ↔ 202.5
Side Shell(P)-Solar 3 63 60.1 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2944.0
Deck Under- Un Assigned storage 2 92 65.3 - - - ↑ - - - 18 54.0 0.092 ↓ 324.4
Deck Over -P.Proce.area 1 92 65.3 - - - ↓ - - - 18 54.0 0.940 ↑ 3314.6
Solar 3
GLAS
S
2.1 - - - ↔ - - - 20 52.0 - ↔ 0.0
Transmission Sub Total - - - 10055
Lights (L.C=7) 7 65.3 457.1 0 457.1
Equipment 8 0.0 0 0.0
Personnel (2) 9 530 670 1200.0
Sensible Heat Sub Total 987 10055
Latent Heat Sub Total 670
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
SPACE: STATE ROOM (FR 19 to 23-STBD ) COOLING SEASON: T = HEATING SEASON: T =
Q T T O ∆T U
QWAdjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L
Page49
Total Heat (Btu/hr) 1657 10055
Total Heat (kW) 0.5 2.9
SHF= 0.596
Heat Load Total QW = 10055 BTU/hr = 2.9 kW
Required Boiler Capacity = 2.9 kW
Boiler requirement
Notes: Glass solar Load = 160 Btu/hr/ft² x 2.1 = 336 BTU/HR
Page50
79 °F 72 °F
Aft Bhd- State Room 5 65 18.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 202.5
Inboard Bhd-T/S 6 5 13.6 - - - ↔ - - - 18.5 53.5 0.354 ↔ 257.6
Inboard Bhd-T/S 6 5 9.4 - - - ↔ - - - 18.5 53.5 0.354 ↔ 178.7
Aft Bhd-T/S 5 5 52.5 - - - ↔ - - - 18.5 53.5 0.354 ↔ 994.3
Inboard Bhd-P.way 6 5 44.3 - - - ↔ - - - 20.0 52.0 0.354 ↔ 814.6
Fwd Bhd-Bosuns Stores 4 65 57.0 - - - ↔ - - - 18.0 54.0 0.200 ↔ 615.6
Side Shell(P)-Solar 3 63 70.63 - - - ↔ - - - 17.6 54.4 0.900 ↔ 3458.1
Solar-port 3
GLAS
S
2.1 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Deck Under- Un Assigned storage
2 92 56.0 - - - ↑ - - - 18.0 54.0 0.092 ↓ 278.0
Deck Over -P.Proce.area 1 92 56.0 - - - ↓ - - - 18.0 54.0 0.94 ↑ 2840.0
Transmission Sub Total - - - 9639
Lights (L.C=7) 7 56.0 391.7 0 391.7 0
Equipment 8 0.0 0 0.0 0
Personnel (2) 9 530 670 1200.0 0
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
2nd DECK - HEATING & COOLING LOAD CALCULATIONS
Date:
06-18-24
QW
SPACE: STATE ROOM (FR 14 to 19-STBD ) COOLING SEASON: T = HEATING SEASON: T =
Adjacent compartment Load key
Insul key
A T O ∆T U
Q s Q L Q T T O ∆T U
Page51
Sensible Heat Sub Total 922 0
Latent Heat Sub Total 670 0
Total Heat (Btu/hr) 1592 9639
Total Heat (kW) 0 2.8
SHF= 0.579
Heat Load Total QW = 9639 BTU/hr = 2.8 kW
Required Boiler Capacity = 2.8 kW
Boiler requirement
Notes: Glass solar Load = 160 Btu/hr/ft² x 2.12 =339.2 BTU/HR
Page52
Fwd Bhd-Passenger Processing area
4 5 18.1 - - - ↔ - - - 18.0 54.0 0.200 ↔ 195.0
Inboard BHD (FWD)-head room 6 65 55.0 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1042.4
Fwd Bhd-Head room 4 65 63.6 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1205.3
Fwd Bhd-P.way 4 5 67.9 - - - ↔ - - - 20.0 52.0 0.354 ↔ 1250.6
Inboard BHD-P.way 6 5 51.6 - - - ↔ - - - 20.0 52.0 0.354 ↔ 949.9
Inboard BHD (FWD)-Freezer 6 65 67.9 - - - ↔ - - - 17.6 54.4 0.200 ↔ 739.2
Inboard BHD-Freezer 6 65 300.1 - - - ↔ - - - 17.6 54.4 0.200 ↔ 3265.5
Aft BHD-Freezer 5 65 67.9 - - - ↔ - - - 17.6 54.4 0.200 ↔ 739.2
Inboard BHD-Freezer 6 65 300.1 - - - ↔ - - - 17.6 54.4 0.200 ↔ 3265.5
Inboard BHD-Crew Ladderwell 6 5 147.1 - - - ↔ - - - 20.0 52.0 0.354 ↔ 2707.1
Fwd Bhd-Passenger Processing area
4 65 27.5 - - - ↔ - - - 18.0 54.0 0.200 ↔ 297.2
Inboard BHD-File cabinet 6 65 3.4 - - - ↔ - - - 18.0 54.0 0.200 ↔ 37.2
Fwd Bhd-File cabinet 4 65 56.8 - - - ↔ - - - 18.0 54.0 0.200 ↔ 613.0
Side shell (p)-solar 3 63 540.9 - - - ↔ - - - 17.6 54.4 0.900 ↔ 26484.4
Side shell (s)-solar 3 63 511.7 - - - ↔ - - - 17.6 54.4 0.900 ↔ 25052.8
Deck over-solar 1 63 1517.8 - - - ↑ - - - 17.6 54.4 0.900 ↓ 74311.5
Deck under-Inner bottom 2 63 1517.8 - - - ↓ - - - 17.6 54.4 0.092 ↑ 7596.3 solar (P) 3 Glass 100.1 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Solar (S) 3 Glass 100.1 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Transmission Sub Total - - - 149752
Lights (L.C=7) 1517.8 10625 0 10624.6
U Q s Q L Q T T O
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
MAIN DECK - HEATING CALCULATIONS
Date:
06-18-24
COOLING SEASON: T =
HEATING SEASON:
T =
SPACE: CARGO SPACES
U QW∆TAdjacent compartment
Load key
Insul key
A T O ∆T
Page53
Equipment 0.0 0 0.0
Personnel (2) 530 670 1200.0
Sensible Heat Sub Total 11155 149752
Latent Heat Sub Total 670
Total Heat (Btu/hr) 11825 149752
Total Heat (kW) 3.5 43.9
SHF= 0.943
Heat Load Total QW = 149752 BTU/hr = 43.9 kW
Required Heater Capacity = 43.9 kW
Notes: Glass solar Load = 160 Btu/hr/ft² x 0 =0 BTU/HR
Boiler requirement
Page54
Fwd Bhd- Solar 4 63 151.4 - - - ↔ - - - 17.6 54.4 0.900 ↔ 7410.6
Fwd Bhd (p)-Solar 4 63 95.4 - - - ↔ - - - 17.6 54.4 0.900 ↔ 4670.4
Fwd Bhd (S)-Solar 4 63 108.3 - - - ↔ - - - 17.6 54.4 0.900 ↔ 5303.6
Shell(p)-Solar 3 63 44.7 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2189.5
Shell (S)-Solar 3 63 44.7 - - - ↔ - - - 17.6 54.4 0.900 ↔ 2189.5
Inboard Bhd(AFT)-Cargo space 6 65 2.6 - - - ↔ - - - 18.0 54.0 0.200 ↔ 27.9
In board(AFT) -T/s 6 5 67.1 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1270.4
In board(P) -T/s 6 5 57.6 - - - ↔ - - - 18.5 53.5 0.354 ↔ 1091.3
Inboard Bhd(P)-Cargo space 6 65 27.5 - - - ↔ - - - 18.0 54.0 0.200 ↔ 297.2
Inboard Bhd(AFT)-Cargo space 6 65 64.7 - - - ↔ - - - 18.0 54.0 0.200 ↔ 698.9
Inboard Bhd(S)-Crew ladderwell 6 5 86.0 - - - ↔ - - - 20.0 52.0 0.354 ↔ 1583.1
Inboard Bhd(AFT)-Crew ladderwell
6 5 35.3 - - - ↔ - - - 20.0 52.0 0.354 ↔ 649.1
Inboard Bhd(s)-Passageway 6 5 12.9 - - - ↔ - - - 20.0 52.0 0.354 ↔ 237.5
Inboard Bhd(aft)-Passageway 6 5 31.8 - - - ↔ - - - 18.0 54.0 0.354 ↔ 608.3
Inboard Bhd(aft)-files cabinet room
6 65 53.3 - - - ↔ - - - 18.0 54.0 0.200 ↔ 575.9
Deck Under- state room 2 92 374.4 - - - ↑ - - - 18.0 54.0 0.092 ↓ 1859.8
Deck Under- P way 2 92 88.6 - - - ↑ - - - 18.5 53.5 0.092 ↓ 436.2
Deck Over -FWD seating 1 92 520.9 - - - ↓ - - - 18.0 54.0 0.940 ↑ 26440.9 solar (P) 3 Glass 25.9 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Solar (S) 3 Glass 12.9 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Boarding gate Glass (P) 3 Glass 3.6 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
Boarding gate Glass (S) 3 Glass 3.6 - - - ↔ - - - 17.6 54.4 - ↔ 0.0
- - - 57540
U
QW
Project Title:
1277 - RANGER IV
Subject:
MAIN DECK - HEATING CALCULATIONS
Date:
06-18-24
Proj. no:
SPACE: PASSENGER PROCESSING AREA COOLING SEASON: T =
HEATING SEASON:
T =
Adjacent compartment Load key
Insul key
A Q T T O ∆TT O ∆T
U
Q s Q L
Page55
Lights (L.C=7) 7 88.6 576.0 0 576.0
Equipment (Coffee maker, coffee warmer, Ice cube maker, refrigerator (up to 20cu.ft))
8 9330.0 0 9330.0
Personnel (8) 9 2400 2400 4800.0
Sensible Heat Sub Total 12306 57540
Latent Heat Sub Total 2400
Total Heat (Btu/hr) 14706 57540
Total Heat (kW) 4.3 16.9
Heat Load Total QW = 57540 BTU/hr = 16.9 kW
Required Heater Capacity = 16.9 kW
Notes: Glass solar Load = 160 Btu/hr/ft² x 46 =7367 BTU/HR Boiler requirement
Page56
R.R.P CONSULTING ENGINEERS, L.L.C
hvac- VENTILATION CALCULATIONS
REPORT
(RANGER IV)
PROJECT NO. 1277
Rev. 0
06-18-2024
This report, drawing, design, concept, and specification are the intellectual property of Loch
Harbour Group, LLC, and/or R.R.P CONSULTING ENGINEERS, L.L.C and contain information which is proprietary. The rights defined below are reserved by Loch Harbour Group, LLC, and/or R.R.P
CONSULTING ENGINEERS, L.L.C. The United States Government’s rights to use, modify, reproduce, release, perform, display, or disclose these technical data are unrestricted. Any reproduction of technical data or portions thereof marked with this legend must also reproduce the markings.
Page57
Proj. no:
Date:
06-18-24
BOW THRUSTER ROOM FR 6 TO 14
BOSUN'S STORE FR 6 TO 14
AUX MACHINERY ROOM FWD
(UNASSIGNED STORAGE),
FR 14 TO 23
PASSENGER PROCESSING AREA AND
CARGO SPACES
FR 14 TO 55
BATTERY ROOM FR 23 TO 35 1300 1300
AUX MACHINERY ROOM AFT FR 49 TO 55 2500 2500
ENGINE ROOM FR 55 TO 71 2 X 15000 2 X 15000
ENGINEERS WORKSHOP &
ENGINE CONTROL ROOM
FR 71 TO 79 (P&S) 750 750
CREW ACCOMMODATIONS SPACES &
CL GR LKR
FR 52 TO 54.5 (S) 1250 1250
PILOT HOUSE, IT SPACES, OFFICER
STATE ROOM, LOUNGE SEATING
FR 13 TO 47 2100 2100
LOUNGE SEATING FR 11 TO 55 2100 2100
REMARKS
Project Title:
1277 - RANGER IV
Subject:
DECK WISE - HEATING & AIR CONDITIONING ANALYSIS
DECK SPACE NAME
01 LEVEL
FRAME
Supply Fan capacity
CFM
Exhaust Fan capacity
CFM
2nd DECK
MAIN DECK
TANK PLAN
1000 1000
TANK PLAN
TANK PLAN
500 500
TANK PLAN
2ND DECK
PILOT HOUSE DECK
Page58
1.0 EXTRACTS FROM GENERAL ARRANGEMENT
Aux Machinery Room Length, L 40 ft
Aux Machinery Room Breadth, B 30.5 ft
Aux Machinery Room Depth, D 8.00 ft (Appendix-1)
2.0 CALCULATE MINIMUM SUPPLY FAN CAPACITY
2.1 Minimum Supply Fan Capacity based on Air Changes
Minimum Required air changes for Aux Machinery Room 15 Air changes/hr (Appendix-2)
The quantity of air required for Aux Machinery Room #1, QA = AMRL*AMRB*AMRD*Air changes
= 2440 cfm
2.2 Minimum Supply Fan Capacity based on Evacuation of Heat
2.2.2 Air flow for Evacuation of Heat, Q H
Heat from electrical apparatus, he = 113.74 BTU/min (Approx)
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
VENTILATION CALCULATIONS -
AUX MACH ROOM AFT (Tank Plan)
Date:
06-17-24
QH =
he cfm ρ x C x DT
(As per SNAME Technical and Research Bulletin 4-16 (Table 2-1) Minimum of one air change per 4 minute required for Elev. & Mach. Room)
Page59
Density of air , ρ = 0.0722 lbm /cu.ft
Specific heat of Air , C = 0.24 BTU/lbm- F
Temperature difference, DT = 39.5 O F
Outside Temperature, TO = 73.5 O F
Aux Machinery Room Temperature, TE = 113 O F
Air flow for Evacuation of Heat, QH = 166.2 cfm
a) Where full details are available, heat emission can be taken as sum of individual items b)
3.0 SUPPLY AIR CALCULATION
3.1 Total Intake Air Quantity = 2440 cfm
3.2 Supply fan capacity calculation
Number of fans to be provided = 1
Minimum Capacity of Each Supply Fan = 2500 cfm @ 1" Static Pressure
For conventional ships , heat emission is taken as 20% of rated power of electrical apparatus and lighting that are in use at sea
Note: Heat emission from electrical installations may be assumed in one of the following methods in the decreasing order of preference, Page60
4.0 EXHAUST AIR CALCULATION
4.1 Total Exhaust Air Quantity (108% of mechanical supply)
= 2440 cfm
Total Exhaust Air Quantity 2635.2
4.2 Exhaust fan capacity calculation
Number of fans to be provided = 1
Minimum Capacity of Each Exhaust Fan = 2500 cfm @ 1" Static Pressure
5.0 SUPPLY AIR CLEAR OPENING AREA SIZING
Clear opening area required for supply air = 1.39 sq.ft
Louver cut out size = 2.31 sq.ft
(Assumed 40 % of cutout occupied by louvers and 60% available for clear opening area)
6.0 EXHAUST AIR CLEAR OPENING AREA SIZING
Clear opening area required for exhaust air = 1.39 sq.ft
Louver cut out size = 2.31 sq.ft
(Assumed 40 % of cutout occupied by louvers and 60% available for clear opening area)
Ref:
Appendix-1: VESSEL SPECIFICATION.
Appendix-2: SNAME TECHNICAL AND RESEARCH BULLETIN 4-16.
Total Supply air
Page61
Battery room Length, L 24 ft
Battery room Breadth, B 24.8 ft
Battery room Depth, D 8.30 ft (Appendix-1)
2.0 CALCULATE MINIMUM SUPPLY FAN CAPACITY
2.1 Minimum Supply Fan Capacity based on Air Changes
Minimum Required air changes for Battery Room 15 Air changes/hr (Appendix-2)
The quantity of air required for Battery Room, QA = SSRL*SSRB*SSRD*Air changes
= 1235 cfm
2.2 Minimum Supply Fan Capacity based on Evacuation of Heat
2.2.2 Air flow for Evacuation of Heat, Q H
Heat from electrical apparatus, he = 90.99 BTU/min (Estimated)
Density of air , ρ = 0.0722 lbm /cu.ft
(As per SNAME Technical and Research Bulletin 4-16 (Table 2-1) Minimum of one air change per 4 minute required for Battery Room)
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
VENTILATION CALCULATIONS - BATTERY ROOM (Tank Plan) Date:
06-18-24
QH =
he cfm ρ x C x DT
Page62
Specific heat of Air , C = 0.24 BTU/lbm- F
Temperature difference, DT = 27 O F
Outside Temperature, TO = 86 O F (Estimated)
Battery Room Temperature, TE = 113 O F (Estimated)
Air flow for Evacuation of Heat, QH = 194.51 cfm
a) Where full details are available, heat emission can be taken as sum of individual items b)
3.0 SUPPLY AIR CALCULATION
3.1 Total Intake Air Quantity = 1235 cfm
3.2 Supply fan capacity calculation
Number of fans to be provided = 1 (Estimated)
Minimum Capacity of Each Supply Fan = 1300 cfm @ 1" Static Pressure
4.0 EXHAUST AIR CALCULATION
4.1 Total Exhaust Air Quantity (108% of mechanical supply)
Total Supply air = 1235 cfm
Total Exhaust Air Quantity = 1333.8 cfm
Note: Heat emission from electrical installations may be assumed in one of the following methods in the decreasing order of preference, For conventional ships , heat emission is taken as 20% of rated power of electrical apparatus and lighting that are in use at sea
Page63
4.2 Exhaust fan capacity calculation
Number of fans to be provided = 1 (Estimated)
Minimum Capacity of Each Exhaust Fan = 1300 cfm @ 1" Static Pressure
5.0 SUPPLY AIR CLEAR OPENING AREA SIZING
Clear opening area required for supply air = 0.72 sq.ft
Louver cut out size = 1.20 sq.ft
(Assumed 40 % of cutout occupied by louvers and 60% available for clear opening area)
6.0 EXHAUST AIR CLEAR OPENING AREA SIZING
Clear opening area required for exhaust air = 0.72 sq.ft
Louver cut out size = 1.20 sq.ft
(Assumed 40 % of cutout occupied by louvers and 60% available for clear opening area)
Ref:
Appendix-1: VESSEL SPECIFICATION.
Appendix-2: SNAME TECHNICAL AND RESEARCH BULLETIN 4-16.
Page64
AUX MACH Room Length, L 18 ft Tank Plan
AUX MACH Room Breadth, B 16.83 ft Tank Plan
AUX MACH Room Depth, D 8.00 ft Tank Plan (Appendix-1)
Passenger Processing Area Room Length, L 18 ft Main Deck
Passenger Processing Area Room Breadth, B 26.50 ft Main Deck
Passenger Processing Area Room Depth, D 8.50 ft Main Deck
Cargo spaces (walkway) Length, L 61 ft Main Deck
Cargo spaces (walkway) Breadth, B 6.60 ft Main Deck
Cargo spaces (walkway) Depth, D 8.50 ft Main Deck
2.0 CALCULATE MINIMUM SUPPLY FAN CAPACITY
2.1 Minimum Supply Fan Capacity based on Air Changes
Minimum Required air changes for rooms 6 Air changes/hr (Appendix-2)
The quantity of air required for Room, QA = BTRL*BTRB*BTRD*Air changes
= 989.94 cfm
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
VENTILATION CALCULATIONS -
AUX MACHINERY ROOM FWD, PASSENGER PROCESSING AREA
& CARGO SPACES
Date:
06-18-24
(As per SNAME Technical and Research Bulletin 4-16 (Table 2-1) Minimum of one air change per 10 minute required for Bonded stores)
Page65
2.2 Minimum Supply Fan Capacity based on Evacuation of Heat
2.2.2 Air flow for Evacuation of Heat, Q H
Heat from electrical apparatus, he = 176.30 Btu/min (Estimated)
Density of air , ρ = 0.0722 lbm /cu.ft
Specific heat of Air , C = 0.24 BTU/lbm- F
Temperature difference, DT = 27 O F
Outside Temperature, TO = 86 O F (Estimated)
Room Temperature, TE = 113 O F (Estimated)
Air flow for Evacuation of Heat, QH = 376.87 cfm
a) Where full details are available, heat emission can be taken as sum of individual items b)
3.0 SUPPLY AIR CALCULATION
3.1 Total Intake Air Quantity = 989.94 cfm
For conventional ships , heat emission is taken as 20% of rated power of electrical apparatus and lighting that are in use at sea
QH =
he cfm ρ x C x DT
Note: Heat emission from electrical installations may be assumed in one of the following methods in the decreasing order of preference, Page66
3.2 Supply fan capacity calculation
Minimum Capacity of Each Supply Fan = 1000 cfm @ 1" Static Pressure
4.0 EXHAUST AIR CALCULATION
4.1 Total Exhaust Air Quantity (108% of mechanical supply)
Total Supply air = 989.94 cfm
Total Exhaust Air Quantity = 1069.1 cfm
4.2 Exhaust fan capacity calculation
Number of fans to be provided = 1 (Estimated)
Minimum Capacity of Each Exhaust Fan = 1000 cfm @ 1" Static Pressure
5.0 SUPPLY AIR CLEAR OPENING AREA SIZING
Clear opening area required for supply air = 0.56 sq.ft
Louver cut out size = 0.93 sq.ft
(Assumed 40 % of cutout occupied by louvers and 60% available for clear opening area)
6.0 EXHAUST AIR CLEAR OPENING AREA SIZING
Clear opening area required for exhaust air = 0.56 sq.ft
Louver cut out size = 0.93 sq.ft
(Assumed 40 % of cutout occupied by louvers and 60% available for clear opening area)
Ref:
Appendix-1: VESSEL SPECIFICATION.
Appendix-2: SNAME TECHNICAL AND RESEARCH BULLETIN 4-16.
Page67
Bow Thruster Room Length, L 16 ft
Bow Thruster Room Breadth, B 7.20 ft
Bow Thruster Room Depth, D 8.00 ft (Appendix-1)
BOSUN'S STORE Room Length, L 16 ft
BOSUN'S STORE Room Breadth, B 13.00 ft
BOSUN'S STORE Room Depth, D 7.60 ft
2.0 CALCULATE MINIMUM SUPPLY FAN CAPACITY
2.1 Minimum Supply Fan Capacity based on Air Changes
Minimum Required air changes for Bow Thruster Room 10 Air changes/hr (Appendix-2)
The quantity of air required for Bow Thruster Room, QA = BTRL*BTRB*BTRD*Air changes
= 417.07 cfm
2.2 Minimum Supply Fan Capacity based on Evacuation of Heat
2.2.2 Air flow for Evacuation of Heat, Q H
(As per SNAME Technical and Research Bulletin 4-16 (Table 2-1) Minimum of one air change per 6 minute required for Bow Thruster Room)
Project Title:
1277 - RANGER IV
Proj. no:
Subject:
VENTILATION CALCULATIONS -
BOW THRUSTER ROOM & BOSUN'S STORE ROOM
Date:
06-18-24
2ND DECK
TANK PLAN
TANK PLAN
TANK PLAN
2ND DECK
2ND DECK
Page68
Heat from electrical apparatus, he = 176.30 Btu/min (Approx)
Specific heat of Air , C = 0.24 BTU/lbm- F
Temperature difference, DT = 27 O F
Outside Temperature, TO = 86 O F (Estimated)
Bow Thruster Room Temperature, TE = 113 O F (Estimated)
Air flow for Evacuation of Heat, QH = 376.87 cfm
a) Where full details are available, heat emission can be taken as sum of individual items b)
3.0 SUPPLY AIR CALCULATION
3.1 Total Intake Air Quantity = 417.07 cfm
3.2 Supply fan capacity calculation
Number of fans to be provided = 1 (Estimated)
Minimum Capacity of Each Supply Fan = 500 cfm @ 1" Static Pressure
For conventional ships , heat emission is taken as 20% of rated power of electrical apparatus and lighting that are in use at sea
QH =
he cfm ρ x C x DT
Note: Heat emission from electrical installations may be assumed in one of the following methods in the decreasing order of preference, Page69
4.1 Total Exhaust Air Quantity (108% of mechanical supply)
Total Supply air = 417.07 cfm
Total Exhaust Air Quantity = 450.43 cfm
4.2 Exhaust fan capacity calculation
Number of fans to be provided = 1 (Estimated)
Minimum Capacity of Each Exhaust Fan = 500 cfm @ 1" Static Pressure
5.0 SUPPLY AIR CLEAR OPENING AREA SIZING
Clear opening area required for supply air = 0.28 sq.ft
Louver cut out size = 0.46 sq.ft
(Assumed 40 % of cutout occupied by louvers and 60% available for clear opening area)
6.0 EXHAUST AIR CLEAR OPENING AREA SIZING
Clear opening area required for exhaust air = 0.28 sq.ft
Louver cut out size = 0.46…