DFS1FD 00 03 25A AIA A101 OWNER CONTRACTOR AGREEMENT 072226DR.pdf

PDF 274 KB Posted

Attached to
removal and installation of fuel storage tank, dispenser and related accessories
Solicitation number
BD-27-2246-DFD3-DFD3-131596
Issued by
Bristol County, Massachusetts

About this file

This is an AIA Document A101-2007 Standard Form of Agreement Between Owner and Contractor executed by Dartmouth Fire District #3 in Massachusetts for the removal and installation of fuel storage tank systems. The project involves the selective removal of an existing underground fuel storage tank and accessories, coupled with the installation of a new above-ground fuel storage tank, fuel dispenser, and related piping and accessories. The contract is structured as a stipulated sum agreement with the contract sum and specific dates of commencement and substantial completion to be filled in by the parties. The work shall commence on the date of the agreement, with substantial completion dates and adjustments to contract time as outlined in the referenced AIA Document A201-2007 General Conditions. The contract documents include the agreement itself, general conditions, supplementary conditions, specifications, drawings, addenda, bid forms, bonds, certificates of compliance, prevailing wage rates documentation, and various Commonwealth of Massachusetts certifications related to non-collusion, conflict of interest, non-debarment, EEO/AA/SDO compliance, and state tax matters.

The contract is based on a stipulated sum payment structure with progress payments computed monthly, provided applications for payment are submitted to the architect by the fifth of each month, with payment due by the twentieth of that month. A five percent retainage is withheld from progress payments, with final payment constituted by the entire unpaid balance upon completion of work and issuance of a final certificate of payment, due no later than thirty days after certification. The estimated project value is One Hundred Eighty-Six Thousand Dollars ($186,000.00). Dispute resolution is designated as litigation in a court of competent jurisdiction rather than arbitration. The contractor must maintain insurance and provide performance and payment bonds as specified in the AIA Document A201-2007 General Conditions. Payments due and unpaid shall bear interest at the legal rate prevailing at the project location.

View the file

Other files

File Type Posted
DFS1FD 00 00 20 INVITATION TO BID 072226DR - pdf~1.pdf PDF
DFS1FD 00 09 00A LABOR STANDARDS 072226SR - pdf.pdf PDF
DFS1FD 00 00 01 TABLE OF CONTENTS 072226DR - pdf.pdf PDF
DFS1FD 01 60 00 PRODUCT REQUIREMENTS 072226DR - pdf.pdf PDF
DFS1FD 00 03 25B AIA A201 GENERAL CONDITIONS 072226DR.pdf PDF
DFS1FD 00 03 25C AIA A310 BID BOND 072226DR.pdf PDF
DFS1FD 00 03 25D AIA A312 PERFORMANCE BOND 072226DR.pdf PDF
DFS1FD 03 30 00 CAST-IN-PLACE CONCRETE 072226DR - pdf.pdf PDF
DFS1FD 09 91 13 PAINTING 072226DR - pdf.pdf PDF
DFS1FD 00 03 00 FORM FOR GENERAL BID 072226DR - pdf.pdf PDF
DFS1FD 01 33 00 SUBMITTAL PROCEDURES 072226DR - pdf.pdf PDF
DFS1FD 02 60 00 UST EXCAVATION AND REMOVAL 072226DR - pdf.pdf PDF
DFS1FD 01 10 00 SUPPLEMENTARY REQUIREMENTS 072226DR - pdf.pdf PDF
DFS1FD 01 50 00 TEMPORARY FACILITIES AND CONTROLS 072226DR - pdf.pdf PDF
DFS1FD 01 00 00 GENERAL REQUIREMENTS 072226DR - pdf.pdf PDF
DFS1FD 31 22 70 SEDIMENTATION AND EROSION CONTROL 072226DR - pdf.pdf PDF
DFS1FD 01 78 39 PROJECT RECORD DOCUMENTS 0072226DR - pdf.pdf PDF
DFS1FD 00 08 00A SUPPLEMENTARY GENERAL CONDITIONS PART 1 072226DR - pdf.pdf PDF
DFS1FD 32 55 40 FUEL STORAGE TANK AND EQUIPMENT 072226DR - pdf.pdf PDF
DFS1FD 01 77 00 CONTRACT CLOSEOUT PROCEDURES 072226DR - pdf.pdf PDF
DFS1FD 01 26 00 CONTRACT MODIFICATION PROCEDURES 072226DR - pdf.pdf PDF
DFS1FD 00 08 00B SUPPLEMENTARY GENERAL CONDITIONS PART 2 072226DR - pdf.pdf PDF
DFS1FD 31 20 00 EARTHWORK 072226DR - pdf.pdf PDF
DFS1FD 00 00 03 LIST OF DRAWINGS 072226DR - pdf.pdf PDF
DFS1FD 00 01 00 INSTRUCTIONS TO BIDDERS 072226DR - pdf.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AIA

Document A101TM – 2007

Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:38:53 on

06/23/2016 under Order No.7525767281_1 which expires on 05/31/2017, and is not for resale.

User Notes: (1397241155)

ADDITIONS AND DELETIONS:

The author of this document has added information needed for its completion.

The author may also have revised the text of the original AIA standard form.

An Additions and Deletions

Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an attorney is encouraged with respect to its completion or modification.

AIA Document A201™–2007, General Conditions of the

Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

AGREEMENT made as of the « » day of « » in the year « »

(In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address and other information) and the Contractor:

(Name, legal status, address and other information) for the following Project:

(Name, location and detailed description)

The Architect:

(Name, legal status, address and other information)

The Owner and Contractor agree as follows.

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:38:53 on

06/23/2016 under Order No.7525767281_1 which expires on 05/31/2017, and is not for resale.

User Notes: (1397241155)

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 THE WORK OF THIS CONTRACT

3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

4 CONTRACT SUM

5 PAYMENTS

6 DISPUTE RESOLUTION

7 TERMINATION OR SUSPENSION

8 MISCELLANEOUS PROVISIONS

9 ENUMERATION OF CONTRACT DOCUMENTS

10 INSURANCE AND BONDS

ARTICLE 1 THE CONTRACT DOCUMENTS

The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other

Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in

Article 9.

ARTICLE 2 THE WORK OF THIS CONTRACT

The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.

ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 3.1 The date of commencement of the Work shall be the date of this Agreement.

§ 3.2 The Contract Time shall be measured from the date of commencement.

§ 3.3 The Contractor shall achieve Substantial Completion of the entire Work as follows:

Portion of Work Substantial Completion Date

, subject to adjustments of this Contract Time as provided in the Contract Documents.

Liquidated damages relating to failure to achieve Substantial Completion on time shall be assessed per Article 8.4 of the General Conditions of the Contract.

ARTICLE 4 CONTRACT SUM

§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the

Contract. The Contract Sum shall be « » ($ « » ), subject to additions and deductions as provided in the Contract Documents.

§ 4.2 The Contract Sum is based upon the following alternates, if any, which are described in the Contract

Documents and are hereby accepted by the Owner:

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:38:53 on

06/23/2016 under Order No.7525767281_1 which expires on 05/31/2017, and is not for resale.

User Notes: (1397241155)

(State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the

Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)

SEE ATTACHED BID FORM

§ 4.3 Unit prices, if any:

(Identify and state the unit price; state quantity limitations, if any, to which the unit price will be applicable.)

SEE ATTACHED BID FORM

§ 4.4 Allowances included in the Contract Sum, if any:

(Identify allowance and state exclusions, if any, from the allowance price.)

SEE ATTACHED BID FORM

ARTICLE 5 PAYMENTS

§ 5.1 PROGRESS PAYMENTS

§ 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for

Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the

Contractor as provided below and elsewhere in the Contract Documents.

§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month.

§ 5.1.3 Provided that an Application for Payment and all required pre-requisite documentation is received by the

Architect not later than the 5th day of a month, the Owner shall make payment of the certified amount to the

Contractor not later than the 20th day of the same month. If an Application for Payment is received by the Architect after the application date fixed above, payment shall be made by the Owner not later than 30 (thirty) days after the

Architect receives the Application for Payment and all required pre-requisite documentation.

§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the

Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract

Sum among the various portions of the Work. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the

Architect, shall be used as a basis for reviewing the Contractor’s Applications for Payment.

§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.

§ 5.1.6 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

.1 Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Contract Sum allocated to that portion of the Work in the schedule of values, less retainage of five percent (5%).

.2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less retainage of five percent (5%);

.3 Subtract the aggregate of previous payments made by the Owner; and

.4 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Section 9.5 of AIA Document A201–2007.

§ 5.1.7 The progress payment amount determined in accordance with Section 5.1.6 shall be further modified under the following circumstances:

.1 Add, upon Substantial Completion of the Work, a sum sufficient to increase the total payments to the full amount of the Contract Sum, less such amounts as the Architect shall determine for incomplete

Work, retainage applicable to such work and unsettled claims; and

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:38:53 on

06/23/2016 under Order No.7525767281_1 which expires on 05/31/2017, and is not for resale.

User Notes: (1397241155)

.2 Add, if final completion of the Work is thereafter materially delayed through no fault of the

Contractor, any additional amounts payable in accordance with Section 9.10 of AIA Document

A201–2007.

§ 5.1.8 Reduction or limitation of retainage, if any, shall be in accordance with the Contract Documents and MGL c.

30, §39K.

§ 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.

§ 5.2 FINAL PAYMENT

§ 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the

Contractor when

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct

Work as provided in Article 12 of AIA Document A201–2007, and to satisfy other requirements, if any, which extend beyond final payment; and

.2 a final Certificate for Payment has been issued by the Architect.

§ 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the

Architect’s final Certificate for Payment.

ARTICLE 6 DISPUTE RESOLUTION

§ 6.1 INITIAL DECISION MAKER

The Architect will serve as Initial Decision Maker pursuant to Section 15.2 of AIA Document A201–2007, unless the parties appoint below another individual, not a party to this Agreement, to serve as Initial Decision Maker.

§ 6.2 BINDING DISPUTE RESOLUTION

For any Claim not resolved by Article 15 of AIA Document A201–2007, the method of binding dispute resolution shall be as follows:

[ ] Arbitration pursuant to Section 15.4 of AIA Document A201–2007

[X] Litigation in a court of competent jurisdiction

[ ] Other (Specify)

ARTICLE 7 TERMINATION OR SUSPENSION

§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document

A201–2007.

§ 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2007.

ARTICLE 8 MISCELLANEOUS PROVISIONS

§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2007 or another Contract

Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract

Documents.

§ 8.2 Payments due and unpaid under the Contract shall bear interest from the date payment is due, at the legal rate prevailing from time to time at the place where the Project is located.

§ 8.3 The Owner’s representative:

§ 8.4 The Contractor’s representative:

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:38:53 on

06/23/2016 under Order No.7525767281_1 which expires on 05/31/2017, and is not for resale.

User Notes: (1397241155)

(Name, address and other information)

§ 8.5 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days written notice to the other party.

ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS

§ 9.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated in the sections below.

§ 9.1.1 The Agreement is this executed AIA Document A101–2007, Standard Form of Agreement Between Owner and Contractor.

§ 9.1.2 The General Conditions are AIA Document A201–2007, General Conditions of the Contract for

Construction.

§ 9.1.3 The Supplementary and other Conditions of the Contract:

Document Title Date Pages

§ 9.1.4 The Specifications:

(Either list the Specifications here or refer to an exhibit attached to this Agreement.)

Section Title Date Pages

§ 9.1.5 The Drawings:

(Either list the Drawings here or refer to an exhibit attached to this Agreement.)

Number Title Date

§ 9.1.6 The Addenda, if any:

Number Date Pages

Portions of Addenda relating to bidding requirements are not part of the Contract Documents unless the bidding requirements are also enumerated in this Article 9.

§ 9.1.7 Additional documents, if any, forming part of the Contract Documents:

.1 Other documents, if any, listed below:

Invitation to Bid

Instructions to Bidders

Form for General Bid

Bid Security Form

Performance Bond

Payment Bond

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 by The

American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:38:53 on

06/23/2016 under Order No.7525767281_1 which expires on 05/31/2017, and is not for resale.

User Notes: (1397241155)

Supplementary General Conditions

Commonwealth of Massachusetts Prevailing Wage Rates

Certificate of Non-Collusion

Conflict of Interest Certification

Certificate of Vote

Certificate of Compliance with M.G.L. c.151b

Certificate of Non-Debarment

State Taxes Certification

Certificate of Compliance with Applicable EEO/AA/SDO Provisions

ARTICLE 10 INSURANCE AND BONDS

The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 11 of AIA Document

A201–2007.

This Agreement entered into as of the day and year first written above.

OWNER (Signature) CONTRACTOR (Signature)

(Printed name and title) (Printed name and title)

File details come from the government source that posted it. Updated .