This is Addendum No. 3 to a Request for Qualifications issued by the Franklin County Board of Commissioners, Ohio, for professional engineering services related to the S. Grener Avenue, Emmit Avenue, Mix Avenue, and Sullivant Avenue (GEMS) Water Main Replacement Project. The RFQ solicits qualifications from engineering firms to provide design services for water main replacement across four streets in Franklin County. The project encompasses water main replacement on S. Grener Avenue from Sullivant to Stiles, Mix Avenue from Sullivant to Bunker, Emmit Avenue from Stiles to Bunker, and Sullivant Avenue from S. Grener to Emmit. The submittal deadline remains April 24, 2025, at 2:00 PM EST. The anticipated design phase will take eight months from contract award, with construction bidding expected to commence in mid-February 2026 and conclude in late May 2026, leading to a construction award by late May 2026. Construction is anticipated to commence by the end of June 2026.

The construction phase will be jointly funded by the Water Supply Loan Repayment Assistance (WSLRA) program and the Ohio Public Works Commission (OPWC). Per OPWC requirements, construction must commence by the end of June 2026, establishing a firm deadline for project initiation. Respondents must submit single-sided PDFs on flash drives and return the signed signature page of the Addendum with their qualifications submission. All addenda and updates are available on the Franklin County Purchasing Department website at https://bids.franklincountyohio.gov/.

View the file

Other files

File Type Posted
E13134B7-AC80-2A6B-17903505A1365FE4.pdf PDF
7D243EA3-FAAD-CF0C-AFFD3FFE55D5912C.pdf PDF
B867E43E-FCA2-ABC6-686473D3D551080B.docx DOCX document
9124AC45-D403-5860-A4635A70C618C298.pdf PDF
1FF6D412-D5CF-E3DA-42373990EB63A4DE.docx DOCX document
48C4F0C3-D2EA-9DD6-943661FD67266514.pdf PDF
1FF81613-C943-E907-903208614AFFB273.pdf PDF
48C51FFE-B1BA-D9DA-11337A7B04016CA4.pdf PDF
1FF79148-03D3-7B1B-77CF64FD687ECA4C.pdf PDF
8F33C1D9-B606-E1D0-F77CFF24E442EF1B.pdf PDF
1FF834AF-CB60-B607-A9DD3103FF766EDA.pdf PDF
47ADF7AD-983F-9719-2E5C720D20F03E5A.xlsx XLSX spreadsheet
8BD45E27-AD3D-2A81-9DC34421F6415618.pdf PDF
98B00E89-F3C2-2215-1B6B7A585EA6B903.pdf PDF
4ADBDA30-A10A-65AC-2585EBF3396EC49F.pdf PDF
4540076D-DA44-888C-413CAB868FEC6141.xlsx XLSX spreadsheet
600B382B-92C2-EE01-36E3171A1CE23381.pdf PDF
9188FC82-07E6-2A24-E7927A56369C067A.pdf PDF
441C7CE8-FE79-FFAD-86876E5C9E330E9F.pdf PDF
477EEBB5-9B64-4073-39F4D92B43E61BB0.pdf PDF
A3F924CA-A2E1-A38A-2E6F296BD4EAE5D4.pdf PDF
1FF70774-E56E-EAC8-88A7694DAF5EB82C.pdf PDF
48C71F36-F14E-8501-2A85945F358C6068.xlsx XLSX spreadsheet
8B00ECA9-D368-AD09-80DA20EDC1915543.pdf PDF
47A070EA-AA3B-485A-6C240303241C99D2.pdf PDF
D1C78A42-D40E-4E7A-6D1A7D2FA849B7AF.pdf PDF
441CC2FC-B00B-E914-728A3B9F6E284C71.pdf PDF
1FF7330C-CAC3-999B-9E6EF28469A04621.pdf PDF
4ADC54F2-C74F-3F02-B4900398FFBEE5A5.xlsx XLSX spreadsheet
3CA5BBE9-A618-9D6F-45A1FE1B6F58F0BF.pdf PDF
47411393-E3B2-7F55-0865EAB909BEF818.xlsx XLSX spreadsheet
1FF76D77-0146-31BD-B70AC2B9310C078F.pdf PDF
6A9BE711-E1B2-9B67-147E88484CF79F1A.pdf PDF
1FF7D8D0-C608-E689-8D121B0F5CC22DA9.pdf PDF
47413282-9830-5BA4-96685E7F9A28C371.xlsx XLSX spreadsheet
A4692B9C-E659-F33F-532C87A025A11AC2.pdf PDF
9D5C4E27-A2A7-EBA2-2714B42F829186DC.pdf PDF
3D557BC1-D80F-2E25-C9390E0BF5A59073.pdf PDF
E93EE438-A2D2-AF8E-6F5941F303D00F6A.pdf PDF
9705A9CE-B76B-3514-2AB6D46F5013FD96.pdf PDF
A46910BC-E967-DD22-10B71BADEA153824.docx DOCX document
451D7EC8-9FAF-B01F-15E5F86D68AB3D4B.xlsx XLSX spreadsheet
BCCA0BAC-C5BA-CDB6-49D2EFF559EDAF11.pdf PDF
340E518F-B0A2-92CD-5CE67BE8C5C74ADC.pdf PDF
BCDA75E7-EC2E-694E-CB30EC7B8D89F683.pdf PDF
C4A97C2F-E431-1D38-75E6D603401030C8.pdf PDF
5FEA932D-A443-F834-C369AEC7AD13A552.pdf PDF
4ADC0CC3-B76B-A18D-C62DDED0F769FB5E.xlsx XLSX spreadsheet
D1C75C4E-ACBE-A700-94A3260C246A50BF.pdf PDF
490005E7-0009-0FD7-0E92BD0F4BF1B987.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 146 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

cleanwater.franklincountyohio.gov

April 18, 2025

FRANKLIN COUNTY BOARD OF COMMISSIONERS

REQUEST FOR QUALIFICATIONS 2025-09-03

PROVISION OF PROFESSIONAL ENGINEERING SERVICES FOR S.GRENER AVENUE, EMMIT

AVENUE, MIX AVENUE, AND SULLIVANT AVENUE (GEMS) WATER MAIN REPLACEMENT

PROJECT

373 South High Street, 25th Floor Purchasing Department Columbus, Ohio 43215

Franklin County

Addendum No. 3

TO ALL BIDDERS:

This Addendum supplements and amends the original Request for Qualifications and shall be taken into account in preparing submissions. When returning your statement of qualifications, please sign and return the signature page of the Addendum with your response.

Company name and signature of authorized company representative Date

Provision of Professional Engineering Services for S. Grener Avenue, Emmit Avenue, Mix Avenue, and

Sullivant Avenue (GEMS) Water Main Replacement Project

RFQ 2025-09-03

Addendum No. 3

April 18, 2025

1. The Submittal Deadline Date/Time shall remain the same: April 24, 2025, at 2:00 PM (EST).

2. Question 1: What is the anticipated schedule for bidding of this project?

Response 1: Per Response 2 (below), the project should be ready for bid around mid-February 2026.

Bidding is anticipated to take 3 months, which makes the award for construction in late-May 2026.

3. Question 2: What is FCSE’s desired date of design completion for this project?

Response 2: The County anticipates Design will take 8 months from the Award of Contract to Bidding.

4. Question 3: For the flash drives requested for the GEMS Project, do you want single-sided PDF for ease of copying, rather than the double-sided we are using for our spiral-bound submittals?

Response 3: Please submit single-sided PDFs on the flash drives.

5. Question 4: I had trouble with my audio for the meeting. It seems pretty short, so I assume there were no changes/addendums to the requirements originally published.

Response 4: Please see the Purchasing Department’s website (https://bids.franklincountyohio.gov/) for all addenda published related to this RFQ.

6. Question 5: We understand that this is funding dependent, but is the intent to begin construction in 2026?

Response 5: Yes. The County would like to start construction by end of June 2026.

7. Question 6: Could you please confirm the extents of the water main replacement for each street?

From the exhibit included in the RFQ it appears that the project limits are:

• S. Grener from Sullivant to Stiles

• Mix from Sullivant to Bunker

• Emmit from Stiles to Bunker

• Sullivant from S. Grener to Emmit

Response 6: The extents listed above are correct.

https://bids.franklincountyohio.gov/

8. Question 7: Has funding been established for the construction phase of this project? If so, are there any constraints placed on the construction schedule due the funding source(s)?

Response 7: The construction phase of this project will be jointly funded by WSLRA and OPWC. Per the requirements of OPWC, construction is to commence by the end of June 2026.

ATTACHMENTS:

None.

END OF ADDENDUM