DCR 841 Additional Vendor Questions_Final.docx

DOCX document 22 KB Posted

Attached to
DCR 841 Touch-free Parking in Parks and Revenue
Solicitation number
BD-21-1020-DCRCU-DC250-59569
Issued by
Massachusetts

About this file

This document contains additional questions and responses related to Request for Response (RFR) DCR 841 issued by the Commonwealth of Massachusetts Department of Conservation and Recreation (DCR) for a fully developed, hosted, and maintained Software as a Service (SaaS) system/solution for touch-free parking in parks and revenue collection. The RFR covers topics such as passholder types, parking revenue collection breakdown, passholder access, staffing, continuity of operations plans, cellular coverage, vendor response forms, evaluation process details, and formatting requirements. The DCR is seeking to transition to a fully automated parking system and is requesting proposals from vendors to provide the required SaaS solution and services.

The document also includes details on the related state and local contract opportunity, including the project description, the state involved (Massachusetts), and other background information. Vendors are expected to provide detailed responses addressing the technical specifications in Section 3 of the RFR. The DCR anticipates owning all data collected through the proposed solution and encourages vendors to propose authentication protocols, a help desk line, and a client support line as part of their offerings.

View the file

Other files

File Type Posted
Bidder Response Form 2021_03.18.21.docx DOCX document
Commonwealth Terms and Conditions for Information Technology Contracts 7-1-20.pdf PDF
Aprox. Fee Parking Space Totals_03.11.21.pdf PDF
SDP Form1~52.docx DOCX document
DCR Accepted Parking Passes_Summary.pdf PDF
RFR_DCR Touchless fee Collection_Revenue App_Final.docx DOCX document
Space Count and List of Facilities_COMMBUYS_Q and A_03.11.21.docx DOCX document
Standard Contract Form Instructions and Contractor Certifications 7-1-20.pdf PDF
2021 Parking Rev Collection Schedule_3.3.21.pdf PDF
Internet Service_03.18.21.xlsx XLSX spreadsheet
SDP Form2~54.docx DOCX document
SDP Form 3~54.xlsx XLSX spreadsheet
DCR 841 Touch-free Parking in Parks Answers to vendor Questions.docx DOCX document
w-9 form march 2020.pdf PDF
COMMBUYS create-a-quote-v1~4.docx DOCX document
DCR 841 Additional Vendor Questions_03.22.21.docx DOCX document
CASL_Form.rtf RTF text file
DCR_Fee Collection Map.pdf PDF
Bidder Scoring Matrix Appendix.xlsx XLSX spreadsheet
Standard Contract Form 7-1-20.docx DOCX document
promptpaydiscountform.docx DOCX document
eppform~5.docx DOCX document
Updated EFT form.pdf PDF
busreffm.doc DOC document
DCR 841 Additional Vendor Questions_03.19.21.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCR 841 Additional Vendor Questions 14- 36

14 03/17/2021 Proposal Writer/PayByPhone Technologies Inc. Passholders types For the 2019 and 2020 seasons, can you breakdown the number of annual passholders, lifetime passholders, and no fee parkers: o Annual parking passes: o Senior parking passes: o Handicap, purple heart, and disabled veteran registered license plates:

Information is not available. 500,000 day passes were sold in 2019.

15 03/17/2021 Proposal Writer/PayByPhone Technologies Inc. Parking revenue collection breakdown For the 2019 and 2020 seasons, what was the total parking revenue and payment collection breakdown: o Total parking revenue: o Credit card collection revenue: o Cash collection revenue: o Check collection revenue:

This information is not available.

16 03/17/2021 Proposal Writer/PayByPhone Technologies Inc. Passholder access Does the annual pass enable passholders access to all DCR facilities or just one specific park?

The purchase of an annual pass allows patrons access to all DCR facilities, except for the on-street metered locations.

1703/17/2021Proposal Writer/PayByPhone Technologies Inc.
StaffingFor the 2021 season, will each paid parking facility continue to be staffed at the park entrance?

Locations that have been historically staffed at park entrances will continue to operate in a similar manner for the majority of the 2021 season. The goal is to transition to a fully automated system.

18 03/17/2021 Proposal Writer/PayByPhone Technologies Inc.

Continuity of Operations Plan requirement How does the Continuity of Operations Plan requirement apply to mobile payment vendors? For example: A list of the Vendors building location(s) that would be available to serve the Commonwealth during an emergency. A description of the areas of Massachusetts that the Vendor could supply in the event of an emergency (e.g., Entire State, Specific City or Region).

Vendors are required to provide a continuity plan in the event the proposed system becomes unavailable. Please indicate if a specific bullet point is not applicable to the service you provide.

1903/17/2021Proposal Writer/PayByPhone Technologies Inc.
Cellular coverageIn Section 3.3.7 Geographic Service and Delivery Areas, it states that? several locations within the agency’s portfolio have limited cellular coverage which may hinder mobile payment operation.? Can you list these park locations and indicate whether there is hardwired internet and/or Wi-Fi?

Please see document titled “Internet Service” for specifics.

2003/17/2021Sindhu Ranjit/US eDirect
Vendor Response FormPage 33 of the RFP states-" 7.8.2 Vendor Response Form - All specifications of this RFR that are not mandatory such as those specifically identified as ?optional,? ? desirable? or in other terms indicating that the specification is not mandatory must have a response within the Vendor Response Form (or equivalent) provided on COMMBUYS for this Bid in order to be evaluated." QUESTION: We did not find a vendor response form uploaded in COMMBUYS for this RFP. Please clarify and provide the vendor response form if we are expected to provide responses only in that form.

The Vendor Response Form has been posted.

2103/18/2021Kristin Gatter/PassportParking
RFR Number DCR 841 (Evaluation)Which individuals/departments will be involved in the evaluation process?

The Finance, IT and Operations department will participate in the evaluation process.

22 03/18/2021 Kristin Gatter/PassportParking RFR Number DCR 841 (Evaluation) Can the DCR please detail the scoring rubric that will be used to evaluate the proposal and pricing?

Please review the document titled “Bidder Scoring Matrix”.

23 03/18/2021 Kristin Gatter/PassportParking RFR Number DCR 841 (Formatting) Section 7.6.1 provides naming conventions for the files to be uploaded. Can the DCR provide a naming convention for the vendors Statement of Qualification and Scope of Service Narrative as requested in 7.5.1?

Please upload the Statement of Qualification and Narrative according to the following naming convention:

RFR Section or Quote Component Description Enter in COMMBUYS during upload File Name Assign when creating files

Statement of Qualification
[Company Name] Qualification
[CompanyName]_Qualification.pdf
Scope of Service Narrative
[Company Name] Narrative
[CompanyName]_Narrative.pdf
2403/18/2021Kristin Gatter/PassportParking
RFR Number DCR 841 (Formatting)Section 7.6.1 states that the organization chart, marketing materials, and implementation plan should all be separate document uploads. These items are also included in section RFR 3 SPECIFICATIONS. Should they be uploaded separately and included in the Vendors Statement of Qualification and Scope of Service Narrative as requested in 7.5.1?

Yes

2503/18/2021Kristin Gatter/PassportParking
RFR Number DCR 841 (Formatting)Does the DCR have a preferred naming convention for the remaining requirements outside of the organization chart, marketing materials, and implementation plan?

No, but you may use Section 7.6.1 as a guide.

26 03/18/2021 Kristin Gatter/PassportParking RFR Number DCR 841 (Formatting) Should the forms be submitted as a separate document or included with the Vendors full narrative response? If separate, what should the naming convention be?

The forms listed in section 7.6.1 should be submitted separately.

2703/18/2021Kristin Gatter/PassportParking
RFR Number DCR 841 (Formatting)Section 7.8.2 references a? Vendor Response Form? can the DCR provide this form to Vendors? Or is the Vendors Statement of Qualification and Scope of Service Narrative as requested in 7.5.1 the? vendor Response Form??

Vendor Response Form has been uploaded.

2803/18/2021Kristin Gatter/PassportParking
RFR Number DCR 841 (Formatting)Section 7.8.2 states that the SST does not want and will not read, consider, or evaluate a line by line response to this RFR. However, Section 7.5.1 says Vendors must respond to all requirements detailed in RFR 3 SPECIFICATIONS. Can the DCR please clarify if each requirement within Section 3. Specifications needs to be answered individually.

Vendors must address the requirements listed in Section 3.

2903/18/2021Kristin Gatter/PassportParking
RFR Number DCR 841 (Formatting)Are Vendors required to respond to each of the requirements listed within? Appendix 1 - Scope of Services and Deliverables? in their responses? Or is this simply a reference to what is expected of Vendors with regard to their phased implementation approaches?

Appendix 1 details the scope and deliverables for the project and can be used as a reference. Vendors are not required to respond to Appendix 1.

30. Is it the Agency?s expectation to own all data stored in the proposed solution?

DCR anticipates owning all data collected from the proposed solution.

31. Do you wish to utilize the Commonwealth’s SAML provided for authentication of agency personnel, or would you prefer to utilize the vendor’s authentication protocol?

DCR encourage vendors to propose their own authentication protocols in their proposal with technical specifications. Proposed solutions should consider a SAML base system.

32. Page 13: Quality - Vendor to provide access to a live customer service representative 24 hours a day. Is this the public sales line for consumers or the Help Desk line?

This is an error. The statement refers to a Help Desk line based on operating hours.

33. Customer Service - The agency requires a highly professional customer service support Do the operational hours for the public sales line differ from the Help Desk? And can DCR clarify the operational hours for the sales line?

DCR requires a Help Desk line to assist customers should they have questions about the proposed system, including, but not limited, questions relating to transaction processing and account maintenance. The help desk line is based on operating hours. Please see document titled “2021 Parking Rev. Collection Schedule” for location hours. Additionally, DCR requires a client support line.

34. Is this a request for a separate Consumer Support line, and if so what are the operational hours?

DCR requires a Help Desk line to assist customers should they have questions about the proposed system, including, but not limited, questions relating to transaction processing and account maintenance. The help desk line is based on operating hours. Please see document titled “2021 Parking Rev. Collection Schedule” for location hours. Additionally, DCR requires Client Support line.

35. To help provide some context, can the DCR provide a historical transactional breakdown of Day Use Passes, Annual Passes, and Senior Passes by year?

Information is not available. 500,000 day passes were sold in 2019.

36. . In addition to completing all of Section 3 (Specifications) and the entire Statement of Work beginning in Section 3.3.9, is it the DCR’s intent that bidders also provide responses to Section 6 and Appendix 1? The RFR submission requirements only mention Section 3 as the required technical portion. b. Alternatively, since large portions of Section 6 and Appendix 1 repeat the same/similar criteria as listed in Section 3, is the intent of Section 6 and Appendix 1 to provide context to Section 3; or does DCR intend Section 6 and Appendix 1 to be completed and returned as part of the required components?

Vendors will be evaluated based on Section 3 (Specifications). Appendix 1 details the scope and deliverables for the project, while Section 6 provides an overview of the evaluation criteria. Both Section 6 and Appendix 1 can be used as a reference.