This is a Utility Crossing Summary Report prepared by Taylor Engineering, Inc. for Brevard County, Florida regarding Project C2018-029-02, the Eau Gallie Muck Removal project. The report documents the results of utility coordination efforts conducted in May and June 2021, identifying all utilities that cross or are located near the Eau Gallie Causeway and adjacent areas where dredging operations will occur. Key utilities contacted include FPL (electric and subaqueous), Florida City Gas, Charter Communications, Centurylink, AT&T, MCI Fiber Communications, the City of Cocoa, City of Melbourne (sewer, water, and electric), City of Palm Bay (sewer and water), Brevard County Water Resources, and NextEra Energy. The coordination process involved phone calls, emails, and direct contact with utility representatives between May 18 and June 2, 2021, to confirm utility locations and obtain clearance for construction activities. Most utilities responded positively and confirmed they were either clear of the project area or had utilities attached to the causeway that would not interfere with dredging operations. Notable findings include a buried water main under US-1 Highway maintained by Palm Bay, pipeline landing infrastructure in place, and an 8-inch buried gas line near Eau Gallie Causeway operated by NextEra Energy.
The report confirms that substantially all utilities have been cleared for the project, with only FPL's Joel Bray providing no response to multiple contact attempts via email and phone on May 26 and June 1-2, 2021. The utility coordination process was essential for project planning purposes, as identified in the final status designation "For Bidding Purposes Only," ensuring that contractors bidding on the estimated $18.5 million Eau Gallie dredging project would have accurate information regarding subsurface infrastructure. The structured coordination effort, led by Taylor Engineering and Brevard County contact Roy Hawthorne, demonstrates comprehensive pre-bidding due diligence to mitigate construction risks and ensure compliance with utility easements and service requirements during the 730-day substantial completion timeline specified in the project contract.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Taylor Engineering, Inc.
10151 Deerwood Park Blvd; Bldg 300, Suite 300 Jacksonville, FL 32256 Phone: 904-731-7040
Client Name:
Project Name:
Project Number: C2018-029-02
CROSSING UTILITY Contact Notes Dino Farruggio Any utilities are attached to causeway 561-683-2729 Clear
Roy Hawthorne Positive Response on 5/19/21 Roy.Hawthorne@brevardfl.gov Clear; No utilities
1-877-366-8344 Positive response on 5/18/21; phone response 5/26/21 Randy Newman Any utilities are attached to causeway 321-544-2214 Clear
Jerrold Kaiser Phone repsonse 5/27/21 321-338-1928 Any utilities are attached to causeway 321-757-6503 Clear
George Toler Phone repsonse 5/27/21 321-433-8797 Clear
Ruben Rosado Positive Response 5/19/21 and 5/27/21 321-608-5106 Clear
Ruben Rosado Positive Response 5/19/21 and 5/27/21 321-608-5106 Clear
Scott Arnold Positive Response 5/19/21 321-608-7360 Clear; No Utilities
Tim Roberts Positive response on 5/18/21 Tim.Roberts@palmbayflorida.org Burried water main under US-1
Pipeline landing infrastructure in place
Holly Coombs Phone and email 5/26/21 and 6/1/21 321-638-3419 Response on 6/2/21 holly.coombs@nexteraenergy.com 8" burried gas line near Eau Gallie Causeway
Joel Bray Emailed on 5/26/21 and 6/1/21 386-586-6403 Phone call on 5/26/21 and 6/2/21 joel.bray@fpl.com No Response
Joel Bray Emailed on 5/26/21 and 6/1/21 386-586-6403 Phone call on 5/26/21 and 6/2/21 joel.bray@fpl.com No Response
National Fiber Security Dept. Phone response 5/26/21 1-800-624-9675 Conjunction with AT&T
Clear; No utilities
9a FPL - Subaqueous
Brevard County Brevard County Eau Gallie Muck Removal
4 Charter Communications
Centurylink3
1 AT&T
2 Brevard County Water Resources
9b FPL - Electric
10 MCI - Fiber Comms
5 City of Cocoa
6a City of Melbourne - Sewer
6b City of Melbourne - Water
6c City of Melbourne - Electric
7 City of Palm Bay - Sewer/Water
8 Florida City Gas
For Bidding Purposes OnlyFor Bidding Purposes Only mailto:Roy.Hawthorne@brevardfl.gov mailto:Tim.Roberts@palmbayflorida.org mailto:holly.coombs@nexteraenergy.com mailto:joel.bray@fpl.com mailto:joel.bray@fpl.com
FINAL