Attachment_F_-_REVISED_Price_Sheet_1.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Eau Gallie Muck Removal Project Area A1
Solicitation number
B-6-25-24
Issued by
Brevard County, Florida

About this file

The document is a Price Sheet for the Eau Gallie Muck Removal Project, involving Brevard County, Florida, and the Florida Inland Navigation District (FIND). The project encompasses hydraulic dredging of approximately 189,972 cubic yards of organic sediments from the Eau Gallie Dredge Area A1, with three alternate bid items for additional dredging volumes of 42,007 CY, 34,940 CY, and 31,835 CY. The contractor will utilize a Dredge Material Management Area (DMMA) BV-52 provided by the County along US-1 Highway, and will be responsible for dredging, dewatering, material disposal, and DMMA restoration, while complying with all applicable federal, state, and local permits and regulations.

The price sheet presents a comprehensive breakdown of lump sum and estimated measured quantity costs, categorized into base bid and alternate bid sections. While no specific unit prices are filled in, the document outlines cost categories including mobilization, site preparation, environmental protection, dredge material handling, survey work, and effluent treatment. The pricing structure includes provisions for standby time, gopher tortoise burrow grouting, and various dredging activities across different project sections. The bid allows for multiple pricing scenarios, with a summary of total bid options ranging from base bid only to base bid plus all three alternate bids, and includes a contingency line item. The document also includes standard governmental procurement elements such as prompt payment discount opportunities and addendum acknowledgment sections.

View the file

Other files

File Type Posted
Notice_of_Award_1.pdf PDF
Bid_Tabulation_-_Names_Only_1.pdf PDF
Bid_Tabulation_-_Names_Only_1.pdf PDF
Addendum_3.pdf PDF
Addendum_3.pdf PDF
Addendum_3.pdf PDF
Addendum_2.pdf PDF
Addendum_1.pdf PDF
Addendum_1.pdf PDF
Addendum_1.pdf PDF
Attachment_E_-_DRAFT_CONTRACTOR_CONTRACT.pdf PDF
Attachment_E_-_DRAFT_CONTRACTOR_CONTRACT.pdf PDF
Attachment_E_-_DRAFT_CONTRACTOR_CONTRACT.pdf PDF
B-6-25-24_INV_&_SPECS_1.pdf PDF
B-6-25-24_INV_&_SPECS_1.pdf PDF
B-6-25-24_INV_&_SPECS_1.pdf PDF
Attachment_A_-Technical_Specifications.pdf PDF
Attachment_F_-_Price_Sheet.xlsx XLSX spreadsheet
C-2_USACE_Permit.pdf PDF
D-3_Geotechnical_Report.pdf PDF
D-4_Dredge_Material_Testing_Report.pdf PDF
D-7_Eau_Gallie_Utility_Crossing_Summary_Report.pdf PDF
D-2_DMMA_BV-52_Groundwater_Well_Map.pdf PDF
D-4_Dredge_Material_Testing_Report.pdf PDF
D-6_Gopher_Tortoise_Initial_Assess._2022.pdf PDF
C-2_USACE_Permit.pdf PDF
C-4_USFWS_Letter_for_Permit.pdf PDF
D-5_FWC_Standard_Drawings_&_Tech_Specs.pdf PDF
D-7_Eau_Gallie_Utility_Crossing_Summary_Report.pdf PDF
C-1_FIND_Lease_Agreement.pdf PDF
C-1_FIND_Lease_Agreement.pdf PDF
C-4_USFWS_Letter_for_Permit.pdf PDF
C-5_FDEP_Permit.pdf PDF
Attachment_B_-_Drawings.pdf PDF
C-3_USACE_Permit_Modification.pdf PDF
C-6_FDEP_Permit_Modification.pdf PDF
D-2_DMMA_BV-52_Groundwater_Well_Map.pdf PDF
D-3_Geotechnical_Report.pdf PDF
D-6_Gopher_Tortoise_Initial_Assess._2022.pdf PDF
Attachment_B_-_Drawings.pdf PDF
C-6_FDEP_Permit_Modification.pdf PDF
D-1_FIND_Long-Range-Term_Dredged_Material_Management_Plan_Update_Jan._2021.pdf PDF
D-6_Gopher_Tortoise_Initial_Assess._2022.pdf PDF
Attachment_B_-_Drawings.pdf PDF
C-3_USACE_Permit_Modification.pdf PDF
Attachment_A_-Technical_Specifications.pdf PDF
C-1_FIND_Lease_Agreement.pdf PDF
D-1_FIND_Long-Range-Term_Dredged_Material_Management_Plan_Update_Jan._2021.pdf PDF
D-4_Dredge_Material_Testing_Report.pdf PDF
C-3_USACE_Permit_Modification.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

B-6-25-24 Eau Gallie Muck Removal Project Price Sheet
Lump Sum Fixed Costs - Base Bid
Bid ItemItem DescriptionEst. Qty.UnitUnit CostLump Sum Total
General Conditions
01.01Mobilization/Demobilization - DMMA1LS$ - 0
01.02Mobilization/Demobilization - In Water1LS$ - 0
01.03Pre and Post Construction Videos1LS$ - 0
Dewatering Facility / Site
02.01DMMA - Site Preparation1LS$ - 0
02.02Environmental Protection – DMMA1LS$ - 0
02.03DMMA Restoration1LS$ - 0
02.04DMMA – Perimeter Ditch Restoration1LS$ - 0
SUB TOTAL LUMP SUM FIXED COSTS - BASE BID:$ - 0
Estimated Misc. Measured Quantity Costs - Base Bid
Bid ItemItem DescriptionEst. Qty.UnitUnit CostEstimated Total
Dredge Material Handling
03.01DMMA Management - Dewater, Material Transport, & Disposal182,972CY$ - 0
03.02DMMA - Untreated Raw Water Testing50EA$ - 0
03.03Vacant Gopher Tortoise Burrow Grouting5EA$ - 0
03.04Standby Time - Dredge300Hourly$ - 0
03.05Standby Time – Dewatering300Hourly$ - 0
SUB TOTAL MISC. ESTIMATED MEASURED QUANTITY COSTS - BASE BID:$ - 0
Estimated Measured Quantity Costs - Pay Section X - Shallow Face - Base Bid
Bid ItemItem DescriptionEst. Qty.UnitUnit CostEstimated Total
Dredging
X.01Muck Dredging104,412CY$ - 0
X.02Survey (BD, Progress, AD, As-Built)1LS$ - 0
X.03Environmental Protection1LS$ - 0
A.04Effluent Treatment - Nitrogen1LS$ - 0
A.04.aEffluent Treatment - Nitrogen Deduction1LS0$ - 0
A.05Effluent Treatment - Phosphorus1LS$ - 0$ - 0
A.05.aEffluent Treatment - Phosphorus Deduction1LS$ - 0$ - 0
SUB TOTAL ESTIMATED MEASURED QUANTITY COSTS - BASE BID PAY SECTION X:$ - 0
Estimated Measured Quantity Costs - Pay Section Y - Deep Face East - Base Bid
Bid ItemItem DescriptionEst. Qty.UnitUnit CostEstimated Total
Dredging
Y.01Muck Dredging25,174CY$ - 0
Y.02Survey (BD, Progress, AD, As-Built)1LS$ - 0
Y.03Environmental Protection1LS$ - 0
B.04Effluent Treatment - Nitrogen1LS$ - 0$ - 0
B.04.aEffluent Treatment - Nitrogen Deduction1LS0$ - 0
B.05Effluent Treatment - Phosphorus1LS$ - 0$ - 0
B.05.aEffluent Treatment - Phosphorus Deduction1LS$ - 0$ - 0
SUB TOTAL ESTIMATED MEASURED QUANTITY COSTS - BASE BID PAY SECTION Y:$ - 0
Estimated Measured Quantity Costs - Pay Section Z - Deep Face West - Base Bid to 15ft
Bid ItemItem DescriptionEst. Qty.UnitUnit CostEstimated Total
Dredging
Z.01.00Muck Dredging53,386CY$ - 0
Z.02.00Survey (BD, Progress, AD, As-Built)1LS$ - 0
Z.03.00Environmental Protection1LS$ - 0
C.04Effluent Treatment - Nitrogen1LS$ - 0
C.04.aEffluent Treatment - Nitrogen Deduction1LS0$ - 0
C.05Effluent Treatment - Phosphorus1LS$ - 0$ - 0
C.05.aEffluent Treatment - Phosphorus Deduction1LS$ - 0$ - 0
SUB TOTAL ESTIMATED MEASURED QUANTITY COSTS - BASE BID PAY SECTION Z:$ - 0

SUB TOTAL BASE BID: $ - 0

Estimated Measured Quantity Costs - Pay Section Z - Deep Face West Alt Bid 1 15ft to 16.5ft
Bid ItemItem DescriptionEst. Qty.UnitUnit CostEstimated Total
Dredging
Z.01.01Muck Dredging42,007CY$ - 0
Z.02.01DMMA Management - Dewater, Material Transport, & Disposal42,007CY$ - 0
Z.03.01Survey (BD, Progress, AD, As-Built)1LS$ - 0
Z.04.01Environmental Protection1LS$ - 0
D.04Effluent Treatment - Nitrogen1LS$ - 0
D.04.aEffluent Treatment - Nitrogen Deduction1LS0$ - 0
D.05Effluent Treatment - Phosphorus1LS$ - 0$ - 0
D.05.aEffluent Treatment - Phosphorus Deduction1LS0$ - 0

SUB TOTAL ESTIMATED COSTS - PAY SECTION Z ALT BID 1: $ - 0

Estimated Measured Quantity Costs - Pay Section Z - Deep Face West Alt Bid 2 16.5ft to 18ft
Bid ItemItem DescriptionEst. Qty.UnitUnit CostEstimated Total
Dredging
Z.01.02Muck Dredging34,940CY$ - 0
Z.02.02DMMA Management - Dewater, Material Transport, & Disposal34,940CY$ - 0
Z.03.02Survey (BD, Progress, AD, As-Built)1LS$ - 0
Z.04.02Environmental Protection1LS$ - 0
D.04Effluent Treatment - Nitrogen1LS$ - 0
D.04.aEffluent Treatment - Nitrogen Deduction1LS0$ - 0
D.05Effluent Treatment - Phosphorus1LS$ - 0$ - 0
D.05.aEffluent Treatment - Phosphorus Deduction1LS0$ - 0

SUB TOTAL ESTIMATED COSTS - PAY SECTION Z ALT BID 2: $ - 0

Estimated Measured Quantity Costs - Pay Section Z - Deep Face West Alt Bid 3 18ft to 21ft
Bid ItemItem DescriptionEst. Qty.UnitUnit CostEstimated Total
Dredging
Z.01.03Muck Dredging31,835CY$ - 0
Z.02.03DMMA Management - Dewater, Material Transport, & Disposal31,835CY$ - 0
Z.03.03Survey (BD, Progress, AD, As-Built)1LS$ - 0
Z.04.03Environmental Protection1LS$ - 0
D.05Effluent Treatment - Nitrogen1LS$ - 0$ - 0
D.06Effluent Treatment - Nitrogen Deduction1LS0$ - 0
D.07Effluent Treatment - Phosphorus1LS$ - 0$ - 0
D.08Effluent Treatment - Phosphorus Deduction1LS0$ - 0

SUB TOTAL ESTIMATED COSTS - PAY SECTION Z ALT BID 3: $ - 0

SUMMARY OF BID TOTALS

TOTAL BASE BID ONLY : $ - 0

TOTAL BASE BID + ALT BID 1: $ - 0

TOTAL BASE BID + ALT BID 1 + ALT BID 2: $ - 0

TOTAL BASE BID + ALT BID 1 + ALT BID 2 + ALT BID 3:$ - 0
Contingency (15%)ERROR:#REF!
TOTAL ESTIMATEERROR:#REF!

ACH PAYMENTS

tc={68EDA1A9-0B41-4CCD-8EB6-60CB54FCC44D}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Delete from cost estimate form. Replace with a cost estimate qualification statement or disclaimer.

Does your company accept ACH Payment Method? _____Yes / _____ No

PROMPT PAYMENT DISCOUNT
Brevard County shall remit payment in accordance with the Florida Prompt Payment Act, Florida Statutes section 218.70. Contractors may offer cash discounts for prompt payment but they will not be considered in determination of award. If a Contractor offers a discount, it is understood that the discount time will be from the date of satisfactory delivery, at the place of acceptance, and receipt of correct invoice, at the office specified, whichever occurs last.

* If Prompt Payment Discount is offered, please state discount and terms:

ADDENDUM ACKNOWLEDGMENT
Contractor acknowledges receipt of amendments by indicating amendment number and date of issue.

Add. No.________ Dated_______________ // Add. No.________ Dated_______________

Add. No.________ Dated_______________ // Add. No.________ Dated_______________

I hereby acknowledge that I have read, understand, and agree to all terms, conditions, insurance, scope of work, specifications and pricing for Bid #/Bid Title.

COMPANY NAME_____________________________________________________________
ADDRESS___________________________________________________________________
AUTHORIZED SIGNATURE_______________________________________________________
PRINTED SIGNATURE_________________________________DATE_____________________
TELEPHONE #__________________________________FAX #__________________________
EMAIL______________________________________________________________________

File details come from the government source that posted it. Updated .