The Technical Specifications document is part of the Eau Gallie Muck Removal Project for Brevard County, Florida, prepared with the involvement of AtkinsRéalis USA, Inc. The project involves hydraulic dredging, dewatering, and disposal of approximately 182,972 cubic yards of organic sediments from the Eau Gallie Area 1A, with three alternate bid options for additional dredging volumes of 42,007 CY, 34,940 CY, and 31,835 CY. The project will utilize the Florida Inland Navigation District (FIND) Dredge Material Management Area (DMMA) BV-52 site along US Highway 1 for dewatering, with the contractor responsible for site restoration and material disposal. The project has a substantial completion timeline of 2 years (730 days) from the Notice to Proceed, with specific requirements for mobilization, dredging, dewatering, and site restoration.

The project will be awarded based on the total bid cost, with the contractor responsible for obtaining all necessary permits, developing comprehensive plans for review (including a Dredge Materials Management Facility Plan, Dewatering System Management Plan, and environmental protection plans), and complying with federal, state, and local regulations. The contractor must manage turbidity levels, ensure proper dewatering and material disposal, and meet specific environmental protection requirements. The bid includes unit pricing for various project components, with provisions for potential adjustments if actual quantities vary significantly from estimated volumes. The ultimate disposition of the dredged material is at the contractor's discretion, with a preference for public beneficial reuse, though landfill disposal is also an option.

View the file

Other files

File Type Posted
Notice_of_Award_1.pdf PDF
Bid_Tabulation_-_Names_Only_1.pdf PDF
Bid_Tabulation_-_Names_Only_1.pdf PDF
Addendum_3.pdf PDF
Attachment_F_-_REVISED_Price_Sheet_1.xlsx XLSX spreadsheet
Attachment_F_-_REVISED_Price_Sheet_1.xlsx XLSX spreadsheet
Attachment_F_-_REVISED_Price_Sheet_1.xlsx XLSX spreadsheet
Addendum_3.pdf PDF
Addendum_3.pdf PDF
Addendum_2.pdf PDF
Addendum_2.pdf PDF
Addendum_1.pdf PDF
Attachment_E_-_DRAFT_CONTRACTOR_CONTRACT.pdf PDF
B-6-25-24_INV_&_SPECS_1.pdf PDF
C-3_USACE_Permit_Modification.pdf PDF
C-4_USFWS_Letter_for_Permit.pdf PDF
C-5_FDEP_Permit.pdf PDF
D-2_DMMA_BV-52_Groundwater_Well_Map.pdf PDF
D-5_FWC_Standard_Drawings_&_Tech_Specs.pdf PDF
Attachment_A_-Technical_Specifications.pdf PDF
Attachment_F_-_Price_Sheet.xlsx XLSX spreadsheet
C-2_USACE_Permit.pdf PDF
C-6_FDEP_Permit_Modification.pdf PDF
D-1_FIND_Long-Range-Term_Dredged_Material_Management_Plan_Update_Jan._2021.pdf PDF
D-3_Geotechnical_Report.pdf PDF
D-5_FWC_Standard_Drawings_&_Tech_Specs.pdf PDF
D-7_Eau_Gallie_Utility_Crossing_Summary_Report.pdf PDF
Attachment_F_-_Price_Sheet.xlsx XLSX spreadsheet
C-5_FDEP_Permit.pdf PDF
Attachment_F_-_Price_Sheet.xlsx XLSX spreadsheet
C-2_USACE_Permit.pdf PDF
D-3_Geotechnical_Report.pdf PDF
D-4_Dredge_Material_Testing_Report.pdf PDF
D-7_Eau_Gallie_Utility_Crossing_Summary_Report.pdf PDF
D-2_DMMA_BV-52_Groundwater_Well_Map.pdf PDF
D-4_Dredge_Material_Testing_Report.pdf PDF
D-6_Gopher_Tortoise_Initial_Assess._2022.pdf PDF
C-2_USACE_Permit.pdf PDF
C-4_USFWS_Letter_for_Permit.pdf PDF
D-5_FWC_Standard_Drawings_&_Tech_Specs.pdf PDF
D-7_Eau_Gallie_Utility_Crossing_Summary_Report.pdf PDF
Attachment_B_-_Drawings.pdf PDF
C-6_FDEP_Permit_Modification.pdf PDF
D-1_FIND_Long-Range-Term_Dredged_Material_Management_Plan_Update_Jan._2021.pdf PDF
D-6_Gopher_Tortoise_Initial_Assess._2022.pdf PDF
Attachment_B_-_Drawings.pdf PDF
C-3_USACE_Permit_Modification.pdf PDF
Attachment_A_-Technical_Specifications.pdf PDF
C-1_FIND_Lease_Agreement.pdf PDF
D-1_FIND_Long-Range-Term_Dredged_Material_Management_Plan_Update_Jan._2021.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SPECIFICATIONS

00 41 00 Bid Schedule

01 11 00 Summary of Work

01 20 00 Measurement and Payment

01 32 16 Construction Progress Schedule

01 33 00 Submittal Procedures

01 35 05 Environmental Protection

01 45 01 Quality Control Procedures

01 50 02 Temporary Construction Facilities

01 55 26 Maintenance of Traffic

01 71 13 Mobilization/Demobilization

01 77 00 Closeout Procedures

02 21 00 Surveys

31 00 00 Earthwork

31 11 00 Clearing and Grubbing

31 22 19 Finish Grading

31 23 19 Dewatering

31 23 33 Trenching and Backfilling

31 25 00 Erosion and Sedimentation Controls

32 92 19 Hydraulic Seeding

32 92 23 Sodding

35 24 00 Dredging

35 26 00 Effluent Treatment

The engineering material and data contained in the Drawings and Technical Specifications in relationship to the Eau Gallie Muck Removal Project were compiled under the responsible charge of the undersigned, whose seal as registered professional engineer is affixed below:

S. Marie Yarbrough, PE Justin Bartusek, PE

Florida Registration No 70748 Florida Registration No 80888

BID NO. B-6-25-24 00 41 00-1 Brevard County Eau Gallie Muck Removal Project

SECTION 00 41 00

BID SCHEDULE

PART 1: GENERAL

1.01 BASIS OF BIDS

A. Lump Sum and Unit Price Schedule

This Contract will be awarded based on the total cost of the bid schedule below. The base project consists of the dredging, placement in the designated DMMA, dewatering, and removal, transportation and disposal of approximately 182,972 cubic yards of sediment from the Eau Gallie Muck Removal Project Area 1A. The project includes bid alternates to dredge additional volumes within Pay Section Z to deeper elevations. The Alternate Bid 1 will be dredged to contour or the -16.5 feet NAVD88, which equates to approximately 42,007 CY of additional muck. Alternate Bid 2 will dredge Pay Section Z to contour or an elevation of -18 feet NAVD88 equating to approximately 34,940 CY of additional muck to be dredged from Pay Section Z. Finally, Alternate Bid 3 will dredge Pay Section Z to -21 feet NAVD88, which equates to approximately 31, 835 CY of additional muck. The project will be awarded based on the lowest responsive total bid amount including all alternate pay sections.

1.02 SCOPE

A. The project consists of the hydraulic dredging, dewatering, and beneficial reuse/disposal of approximately 182,972 CY of muck sediment from the Eau Gallie Muck Removal Project Area 1A. Due to the variability experienced in the actual muck volume in each pay section, it is expected that line-item amounts in the CONTRACTOR's Schedule of Values may be adjusted as needed per Section 01- 20-00 Measurement and Payment for each pay section, however the total project cost of the contract shall not be increased unless authorized by COUNTY through a future change order.

B. If the lowest total bid exceeds the available construction funds, the COUNTY may elect, at their sole discretion, to remove certain Pay Sections to bring the total costs within the available funds. Pay Section Z has been broken out in the bid pricing form to facilitate removal of certain sections if needed. If certain sections are removed from the project in order to meet the anticipated project budget, there will be no adjustments to the fixed and unit-based prices for the remaining sections and bid items.

C. If the actual quantity of the unit-priced dredge quantities and final transportation and disposal items vary by more than 25 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 125 percent or below 75 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, CONTRACTOR may request, in writing with the demand, an extension of time consistent with associated quantity variation. This variation in estimated quantity (VEQ) clause does not apply to all bid items, it only

BID NO. B-6-25-24 00 41 00-2 Brevard County applies to bid items which specifically indicate eligibility under this clause in Section 01 20 00.

D. This bid shall be for a complete project and bid item prices shall include all components necessary for successful completion of the work as designed and specified.

E. This Contract is solicited with bid items. Any bid price for items indicated above which are considered unbalanced in the opinion of the COUNTY may be rejected.

An unbalanced bid is one in which the cost for one or more bid items is considered significantly low and one or more bid items is considered significantly high.

END OF SECTION 00 41 00

BID NO. B-6-25-24 01 11 00-1 Brevard County

SECTION 01 11 00

SUMMARY OF WORK

PART 1: GENERAL

1.01 PROJECT INFORMATION

A. Project Name: Eau Gallie Area 1A (aka Eau Gallie Northeast (NE)) Muck Removal

Project B. Owner: Brevard County Board of County Commissioners (COUNTY) [2725 Judge

Fran Jamieson Way Building A, Room 219 Viera, FL 32940] C. Engineer: The contract documents were prepared for this project by AtkinsRéalis

USA, Inc. (formerly doing business as Atkins North America, Inc (Atkins) who will be managing and overseeing construction operations on behalf of COUNTY.

1.02 WORK COVERED BY CONTRACT DOCUMENTS

A. DESCRIPTION

The COUNTY is soliciting licensed and qualified marine contractors to excavate, dewater, and dispose of approximately 182,972 cubic yards of muck from approximately 86 acres of the Eau Gallie Area A1/NE Muck Removal Project as described herein and depicted by the permitted lines and grades shown in the Drawings. Furthermore, there are three alternate bid items for the dredging of additional material within the dredge template. Bid Alternate 1 shall include the additional dredging of 42,007 CY to contour or a design elevation of -16.5 FT NAVD88 within Pay Section Z. Bid Alternate 2 shall include the additional dredging (not including Bid Alternate 1 volume) of 34,940 CY to a design elevation of -18 FT NAVD88 within Pay Section Z, and Bid Alternate 3 shall include the remaining additional dredging volume of 31,835 CY to a design elevation of -21 feet NAVD 88.

The Florida Inland Navigation District (FIND) property (Dredge Material Management Area) DMMA BV-52 along US Highway 1 has been made available for use as a temporary dewatering site, if desired by the contractor (CONTRACTOR). The COUNTY will provide the CONTRACTOR use of the property following approval of a signed and sealed dewatering plan proposed for use in the project. The dewatering plan is required as part of this bid submittal and will be required to adhere to the requirements found in the FIND lease agreement with the COUNTY. Note that the FIND Lease references a June 1994 Management Plan that has been replaced with the FIND Long-Range Dredge Material Management Plan Update (January 2021). This report can be found in Attachment D. Use of that property will be limited to construction and operation of a dewatering system intended for dewatering of the muck material dredged from the dredge area, and loading of dried material for transport of dredge material to final offsite disposal area. No burning or unauthorized land clearing will be allowed on this property at any time. Trees cannot be removed outside of the restoration limits unless approved by FIND. All dredge material, after dewatering per Section 35-24-00, must be transported to an upland disposal area selected by the CONTRACTOR, and approved by the COUNTY and the ENGINEER prior to use. Use of upland disposal area shall be in accordance with all local, state, and federal regulations.

The CONTRACTOR shall be responsible for the design and construction of the dewatering system and all associated elements needed for successful dewatering as described herein and depicted in the Drawings. The CONTRACTOR shall also be responsible for the design, installation, and maintenance of other site elements, such as construction of internal

BID NO. B-6-25-24 01 11 00-2 Brevard County baffles, polymer injection systems, etc. necessary to support the dewatering and hauling of dredge material. Upon completion of dredging, dewatering, and disposal of the muck material, the CONTRACTOR shall restore the dewatering facility and associated elements as depicted in the Drawings and FIND Lease requirements.

Geotechnical investigations of both the dewatering system site and the muck material have been conducted and the results of these investigations and analyses can be found in Attachment D.

B. Location

The dredge area is located on the east coast of Florida in Brevard County, Florida, located north of the County Road 518 (Eau Gallie Causeway), at approximate location 28° 8'8.75"N, 80°36'48.33"W. A temporary DMMA, FIND (DMMA BV-52), is located on US Highway 1 south of Robert J Conlan Blvd., at approximate location 28° 3'5.28" N, 80°35'24.13" W.

1.03 SUBMITTALS

CONTRACTOR to submit all required documents described within this set of technical specifications. A submittal register shall be generated by the CONTRACTOR and submitted to the ENGINEER for review. CONTRACTOR is responsible for reviewing the Technical Specification to ensure all submittals are accounted for.

1.04 QUALITY ASSURANCE

With an approved testing laboratory, the CONTRACTOR shall coordinate with the testing laboratory and schedule work to permit a reasonable time for testing as the work progresses.

Cost of required testing shall be included in CONTRACTOR’s bid price.

1.05 PERMITS

The CONTRACTOR shall be responsible for obtaining all required, state, local, and environmental permits, including all modifications, not supplied by the COUNTY. It is anticipated that additional permits may be required by the CONTRACTOR for use of an upland final disposal area. All permit(s) and permit modification(s) needed for dewatering purposes must be prepared by CONTRACTOR for the COUNTY and ENGINEER, who will submit the permit or modification request to the appropriate regulatory agencies. The CONTRACTOR shall familiarize himself and his personnel with all building and environmental protection permits issued for this Project and shall comply with all requirements under the terms and conditions set forth therein. Permits shall be displayed in accordance with all federal, state, and local laws.

The COUNTY has obtained the following permits:

A. U.S. Army Corps of Engineers Permit SAJ-2018-02904(SP-AWP)

B. U.S. Army Corps of Engineers Permit Modification SAJ-2018-02904(SP-AWP)

C. US Fish and Wildlife (FWS) Log No. 04 EF1000-2019-I-0051

D. Florida Department of Environmental Protection Permit ERP 0368832-001 EI

BID NO. B-6-25-24 01 11 00-3 Brevard County

E. Florida Department of Environmental Protection Permit Modification ERP 0368832-

002 EM

1.06 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

CONTRACTOR shall commence work within thirty (30) days of receipt of Notice to Proceed. The phrase “commence work” refers to mobilization efforts including submission of preconstruction submittals, surveying, equipment mobilization, drawings, and all items related to permit modifications. CONTRACTOR must prosecute work diligently, without pause, until completion, unless otherwise approved by the COUNTY.

In-water work will be permitted during daylight hours 7 days per weeks, including holidays.

Night operations at the DMMA will conform to minimal noise concerns for adjacent residences. Trucks are not permitted to work at night and will only be permitted to operate between the hours of 7:00 AM to 7:00 PM.

Substantial project completion, including dredging, material disposal, and site restoration must be completed within 2 years (730 days) from Notice to Proceed. Final project completion, including equipment demobilization, as-builts, completed punch list items, etc.

must be completed within sixty (60) days of substantial completion of the project.

A. START OF WORK: Temporary Dewatering Area

1. Field survey and stake the limits of construction.

2. Obtain the COUNTY's approval of the field survey and staking of the limits of construction.

3. Install all silt fences, synthetic hay bales and environmental fencing along the limits of construction as indicated in the Drawings, if needed.

4. Obtain the COUNTY's approval of the installed erosion and sedimentation control measures.

5. Conduct and maintain lawn maintenance of site during project schedule.

6. Initiate construction elements of dewatering system operations including dewatering, staging areas, drying areas, polishing pond, temporary dewatering structure, and drainage ditches.

7. CONTRACTOR shall conduct as-built survey of temporary dewatering facility.

8. Obtain COUNTY’s approval of as-built survey prior to initiation of dredging operations.

B. Prosecution of work: Dredging Operations

1. Installation of pipelines (submerged/floating), booster pumps, and all required safety markings required to reach active dredge area.

2. Conduct before dredge surveys and establish final dredge template.

3. Obtain the COUNTY’s approval of the field survey and final dredge template.

4. Initiate hydraulic dredging of the dredge template approved for construction.

5. Dewatering/drying of muck material.

6. Transportation of dried material to approved offsite disposal area.

7. Discharge of dredge effluent water.

C. Completion of work

1. Demobilization of dredging equipment and pipelines.

2. Demobilization of dewatering system equipment.

3. Site restoration of DMMA BV-52 site, if used, in accordance with Drawings and FIND Lease Restoration Plan.

4. Rehabilitation of the area at the FIND DMMA BV-52 Project Site to design specifications.

5. CONTRACTOR shall conduct final as-built surveys.

BID NO. B-6-25-24 01 11 00-4 Brevard County

6. Obtain COUNTY’s approval of as-built survey prior to final demobilization of site.

1.07 PHYSICAL DATA

A. Physical Conditions

The physical conditions described in the drawings and technical specifications are the result of hydrographic, topographic, and visual surveys and/or core borings representative of conditions existing at the time the data was collected. The data from these site investigations is available for CONTRACTOR’s review.

B. Weather, Water Stage, and Tide Data

CONTRACTOR should investigate for himself the conditions that can be encountered at the project location. It is CONTRACTOR’s responsibility to assess weather, water stage, and tide conditions and schedule for adverse weather in order to meet the schedule described in paragraph 1.06 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK of this section.

C. CONTRACTOR Investigation

It is CONTRACTOR’s responsibility to perform their own investigation to confirm information depicted in the project plans and specifications. Any required modifications to achieve the intent of the design by CONTRACTOR should be brought to the attention of COUNTY in accordance with Section 01 45 01

CONTRACTOR QUALITY CONTROL.

D. Maritime Traffic

Marine traffic in the project area consists of commercial, pleasure, and small recreation vessel of all types and sizes.

E. Surveys

Electronic survey files are available for CONTRACTOR review. Survey data is depicted in the Drawings. The following surveys are available:

1. Bathymetric data (Surveys and muck probes), Amec Inc., dated March 2017.

2. Multibeam Bathymetric Survey Two Areas Along the Intracoastal Waterway, Morgan & Eklund, Inc. dated October 7, 2020.

1.08 LAYOUT OF WORK

A. Establish Project Control

Information concerning the location and elevations of the established monuments used for field surveys and additional information regarding project control can be found in the Survey Notes section of the plan sheet.

1.09 DAMAGE TO WORK

During prosecution of work, is obligated to take reasonable precautions and exercise sound construction practices in order to prevent damage to the work or adjacent

BID NO. B-6-25-24 01 11 00-5 Brevard County structures. Any damage as a result of CONTRACTOR’s failure to do so must be repaired at no expense to COUNTY. However, if any part of the project work is damaged due to circumstances beyond the CONTRACTOR’s control, including flood, earthquake, hurricane, or tornado, COUNTY may request CONTRACTOR make the necessary repairs at the applicable contract unit price.

1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

A. In order for COUNTY to grant a time extension for unusually severe weather, the following must be true:

1. The weather experience at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given months.

2. The unusually severe weather must actually cause delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the CONTRACTOR.

3. The determinization of whether conditions were unusually severe will be made based on a comparison of observed weather conditions during the project performed, compared to the 30-year climate normal from the National Oceanic and Atmospheric Administration (NOAA) Climate Data Online website. The Climate Data Online website (http://www.ncdc.noaa.gov/cdo-web/) published by NOAA’s National Centers for Environmental Information (formerly the National Climatic Data Center) in Asheville, North Carolina contains climatological and meteorological data relevant to this region.

Available data includes quality controlled daily, monthly, seasonal, and yearly measurements of temperature, precipitation, wind, and degree days as well as radar data and 30- year climate normal.

B. The CONTRACTOR is responsible for documenting the occurrence of unusually severe weather days on their daily QC reports. In order for a day to be considered an unusually severe weather day, the weather delay must prevent work on critical activities for more than 50 percent of the day and be companied by documentation

– weather reports, craft advisories, or similar.

1.11 DOCUMENT HEIRARCHY

A. Project Specification Hierarchy: Elements under this contract shall be constructed utilizing the following information in the hierarchy listed below:

1. Contractor Agreement between Owner and Contractor

2. Project permits, authorizations, and leases

3. Technical Specifications

4. Project Drawings

Any discrepancies identified between information listed above shall be coordinated and resolved with COUNTY. The more stringent language in any discrepancy shall be followed.

http://www.ncdc.noaa.gov/cdo-web/ http://www.ncdc.noaa.gov/cdo-web/

BID NO. B-6-25-24 01 11 00-6 Brevard County

PART 2: PRODUCTS – NOT USED

PART 3: EXECUTION – NOT USED

END OF SECTION 01 11 00

BID NO. B-6-25-24 01 20 00-1 Brevard County

SECTION 01 20 00

MEASUREMENT AND PAYMENT

PART 1: GENERAL

1.01 SUMMARY

A. This section describes how Line Items will be measured and paid for when making progress and final payments. Work to be measured and applicable measurement procedures are described in their respective Technical Specification Sections. For work that does not have a specific Line Item such as, but not restricted to, quality control, safety, and environmental monitoring, allocate costs proportionally across appropriate Line Items.

B. All work completed under the Contract will be measured by COUNTY based on observed and/or measured progress of each item specified on the schedule of values.

C. The lump sum and unit prices specified in the Bid SCHEDULE shall include all costs necessary for the complete and successful completion of the project, including equipment, labor, direct charges, indirect charges, profit, incidental cost, taxes, and/or any other cost associated with that item, whether or not it is specifically identified in the plans or specifications. All appropriate costs shall be applied to the closest applicable item.

D. The method of measurement and computations to be used in determination of quantities of material furnished and of work performed under the Contract are identified in the description for each bid item.

E. The term "lump sum," when used as an item of payment, will mean complete payment for the work described for that item. Some lump sum line items require a percentage of the lump sum be paid based on percentage of work completed.

F. The term "unit price," when used as an item of payment, will mean complete payment for the work described for that item.

G. An inspector designated by COUNTY will observe all work. The inspector shall confirm that work has been completed in accordance with the contract documents and all work has been completed to the satisfaction of COUNTY.

H. CONTRACTOR is responsible for all work until it is inspected and accepted by COUNTY. This includes replacing or repairing damages from wind, waves, and storms to the satisfaction of the Engineer.

I. All allowable payable percentages listed in the following bid item descriptions do not account for retainage.

1.02 VARIATION IN ESTIMATED QUANTITIES (VEQ)

A. All unit-priced items in this contract are estimated quantities. If the actual quantity of any unit-priced items varies more than twenty-five percent (25%) above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 125% or below 75% of the estimated design quantity.

BID NO. B-6-25-24 01 20 00-2 Brevard County

B. If the quantity variation is such as to cause an increase in the time necessary for completion, CONTRACTOR may request in writing, an extension of time, to be received by COUNTY within 10 days from the beginning of the delay. Upon the receipt of a written request for an extension, COUNTY shall ascertain the facts and make an adjustment for extending the completion date if, in the judgement of COUNTY, such extension is justified.

C. If COUNTY deems it necessary, CONTRACTOR shall provide justification for any equitable adjustments requested by CONTRACTOR.

1.03 BID ITEMS

JOB PAYMENT ITEMS

Item 01.01 Mobilization/Demobilization – DMMA

This bid item shall include all costs associated with the mobilization and demobilization of men and equipment for performance of the work at the dewatering site and disposal site. In addition, the cost of bonds and required insurance, required plans and submittals, and any other pre-construction expenses necessary for the start of work (excluding the cost of construction materials) or post-construction expenses necessary for closeout shall also be included in this section. The cost of any items or work not included under a specific lump sum or unit price bid on the Bid Pricing Form shall be included as part of the lump sum price for Mobilization and Demobilization. The combined price for Bid Items 01.01 and 01.02 shall not exceed 10% of the Total Bid price.

The work specified under this section shall be paid for at the Contract lump sum price with 60% allowable at the completion of the mobilization effort, as defined below, and the remaining 40% allowable at the completion of the project.

Item 01.02 Mobilization/Demobilization – In Water

This bid item shall include all costs associated with the preparatory work and operations necessary in mobilizing, demobilizing, and relocation, based on direction from COUNTY for the dredge, dredge support equipment, booster pumps, boats, dredge pipeline, and equipment for the hydraulic dredging component of the project. The combined price for Bid Items 01.01 and

01.02 shall not exceed 10% of the Total Bid price.

The work specified under this section shall be paid for at the Contract lump sum price with 60% allowable at the commencement of dredging, which is defined as 24 hours of dredging at the production rates estimated in the work plan, and the remaining 40% allowable at the completion of the project.

Item 01.03 Pre and Post Construction Video

This bid item shall include all costs associated with georeferenced videography of the entire project area and adjacent shorelines prior to and after construction at both the area of the dredge template and DMMA site. The pipeline corridor and structures within 100-FT of the corridor shall also be documented.

The work specified under this section shall be paid for at the Contract lump sum price with 50% payable upon acceptance of the pre-construction video and the remaining 50% payable after acceptance of the post construction video.

BID NO. B-6-25-24 01 20 00-3 Brevard County

Item 02.01 DMMA – Site Preparation

This bid item shall include all costs associated with fixed (non-quantity dependent) costs associate with the DMMA. Costs may include, but are not limited to, property acquisition, design, permitting, and site preparation which includes pre- and post- construction topographic surveys, material testing, fencing repairs, weir board repairs/replacement, and sound dampening equipment. Variable costs associated with the disposal of the dredge material shall be covered under bid line item 03.01 DMMA Management – Material Transport and Disposal.

The work specified under this section shall be paid for at the Contract lump sum price based on the percent complete status of the dewatering site construction, A maximum of 75% will be payable prior to acceptance of the as-builts, with the remaining 25% payable after acceptance of the as-builts.

Item 02.02 Environmental Protection – DMMA

This bid item shall include all costs associated with environmental protection measures associated with DMMA activities. This may include, but is not limited to, turbidity monitoring, spill prevention, the installation, maintenance, and removal of turbidity curtains, silt fences, and erosion control BMPs, installation and maintenance of sampling valves, and installation and maintenance of flow and density meters.

The work specified under this section shall be paid for at the Contract lump sum price with 50% payable upon installation of the items described above and the remaining 50% payable after acceptance of completion of final DMMA restoration.

Item 02.03 DMMA Restoration

This bid item shall include all costs associated with fixed (non-quantity dependent) costs associate with the complete restoration of the dewatering site. Costs may include, but are not limited to deconstruction, debris removal, regrading, hydroseeding, planting, post-construction surveys, material testing, fencing repairs, site closeout, and any other pertinent Site restoration activities listed in Attachment C – FIND Lease Agreement.

The work specified under this section shall be paid for at the Contract lump sum price based on the percent complete status of the dewatering site construction, A maximum of 75% will be payable prior to acceptance of the as-builts, with the remaining 25% payable after final acceptance of site closeout.

Item 02.04 DMMA – Perimeter Ditch Restoration

This bid item shall include all costs associated with clearing, excavation, embankment, fill, grading, and conditions described per FIND lease agreement associated with the restoration of the perimeter stormwater ditch located along the north and west limits of the DMMA BV-52

The work specified under this section shall be paid for at the Contract lump sum price based on the percent complete of the work covered under this bid item. A maximum of 75% will be payable once the perimeter ditch has received final grade, with the remaining 25% payable after any applicable close out requirements have been satisfied.

UNIT PRICE PAYMENT ITEMS

Item 03.01 DMMA Management – Dewater, Material Transport, &Disposal

BID NO. B-6-25-24 01 20 00-4 Brevard County

This bid item shall include all quantity-based costs associated with the dewatering, transportation, and beneficial reuse or disposal of the dewatered dredge material. Costs may include, but are not limited to, excavation, site maintenance, grading, hauling, handling, and disposal of material.

The work specified under this section shall be paid for at the Contract unit price. Truck haul tickets will be used to estimate the total yardage hauled from the DMMA for the purpose of progress payment only. Based on previous projects, typical organic material is expected to weight approximately 0.758 tons per cubic yard. In no case shall the final material transport and disposal volume exceed the cumulative total dredge volume as determined by comparison of the pre and post-construction surveys. If amendments or bulking materials are brought onsite to aid in dewatering, these materials will not be included in the final quantities for payment. Final payments will utilize the cumulative quantity/volume based on the dredge Items X.01, Y.01, and Z.01 quantities.

This Pay Item is eligible for adjustments due to variations in estimated quantities as described in Specification Section 00 41 00. Adjustments may only be made to the pay section in which the quantity varied above 125% or below 75% of the estimated quantity for that pay section.

Item 03.02 DMMA – Untreated Raw Water Testing

This bid item shall include all quantity-based costs associated with the testing of dredge slurry entering the DMMA, as requested by COUNTY. The slurry will be considered “raw water” and be collected prior to any treatment process. Costs may include, but are not limited to, labor, materials, sample collection, and costs associated with testing of samples.

The work specified under this section shall be paid for at the Contract unit price. Payment will be made for the total number of sample tests performed and provided to COUNTY. The number of tests in the bid schedule of values is provided for bidding purposes only and payment will be determined on actual tests performed. Variation in Estimated Quantity described in paragraph 1.02 does not apply to this line item.

Item 03.03 Vacant Gopher Tortoise Burrow Grouting

This bid item shall include all quantity-based costs associated with the material, clearing, fill, and grading associated with the grouting of vacant gopher tortoise burrows along the embankments of the containment levee at FIND BV-52 DMMA.

The work specified under this section shall be paid for at the Contract unit price. Variation in Estimated Quantity described in paragraph 1.02 does not apply to this line item.

Item 03.04 Stand-by Time – Dredge

This bid item shall include all quantity-based costs associated with the stand-by of dredge operations initiated by COUNTY. Time will be measured to the nearest half hour that the plant is not in operation by request of COUNTY. Tracking of standby time directed by COUNTY shall be reported on CONTRACTOR’s daily QC reports.

Standby time for dredging operations will be paid for each hour or partial hour that the plant is not in operation by request of COUNTY at the Contract hourly rate. The hourly rate shall include all costs associated with or incidental to standby of the dredge plant only upon implementation of this line item. The time in the bid schedule is provided for bidding purposes only and will be determined on actual standby time implemented. Variation in Estimated Quantity described in paragraph 1.02 does not apply to this line item.

Item 03.05 Stand-by Time – Dewatering

BID NO. B-6-25-24 01 20 00-5 Brevard County

This bid item shall include all quantity-based costs associated with the stand-by of Dewatering operations initiated by COUNTY. Time will be measured to the nearest half hour that the plant is not in operation by request of COUNTY. Tracking of standby time directed by COUNTY shall be reported on CONTRACTOR’s daily QC reports.

Standby time for dewatering operations will be paid for each hour or partial hour that the plant is not in operation by request of COUNTY at the Contract hourly rate. The hourly rate shall include all costs associated with or incidental to standby of the dewatering plant only upon implementation of this line item. The time in the bid schedule is provided for bidding purposes only and will be determined on actual standby time implemented. Variation in Estimated Quantity described in paragraph 1.02 does not apply to this line item.

Dredging

Items X.01, Y.01, Z.01, Z.01.01, Z.02.01, and Z03.01 Dredging

This bid item shall include all quantity-based costs associated with the hydraulic dredging and transportation of material to the dewatering site. Material identified within the lines and grades depicted in the Drawings will be considered payable.

The work specified under this section shall be paid for at the Contract unit price for each pay section. Payment quantities and acceptance will be determined by one After Dredge (AD) survey performed following completion of dredging in each pay section. Each pay section may be divided into multiple acceptance sections upon agreement with COUNTY at the request of

CONTRACTOR. The request shall include the stationing limits of the requested acceptance section, and those limits shall be no less than one-hundred FT from the dredge cut face. Once a pay section has been approved, final payment quantities for each acceptance section will be determined by calculating the quantity of material removed between the Before Dredge (BD) and AD surveys within the horizontal and vertical limits of the pay template. Progress payments may be paid based on quantities estimated from progress surveys. Volumes outside the dredge limits in the open water area will not be calculated. Sloughing may be encountered due to unconsolidated material. See Section 35-24-00 for sloughing conditions and what is considered payable.

This Pay Item is eligible for adjustments due to variations in estimated quantities as described in Technical Specification Section 00 41 00. Adjustments may only be made to the pay section in which the quantity varied above 125% or below 75% of the estimated quantity for that pay section.

Items X.02, Y.02, Z.02, Z.03.01, Z.03.02, and Z.03.03 Survey (BD, Progress, AD, & As-Builts)

This bid item shall include all costs associated with all dredge associated surveys for the purposes of establishing the pre-dredge bathymetry and muck depths, setting the dredge templates, evaluating progress, determining pay quantities, and providing a record of post-dredge bathymetry. The work specified under this section shall be paid for at the Contract lump sum price for each pay section based on the estimated percent complete of that section. A maximum of 60% will be payable prior to acceptance of the final as-builts for each pay section, with the remaining 40% payable after acceptance of the final as-builts for each pay section.

Items X.03, Y.03, Z.03, Z.04.01, Z.04.02, and Z.04.03 Environmental Protection

This bid item shall include all costs associated with environmental protection measures associated with dredging. This may include, but not be limited to, turbidity curtains, turbidity monitoring, endangered species observation, and spill prevention. The work specified under this section shall be paid for at the Contract lump sum price for each pay section based on the

BID NO. B-6-25-24 01 20 00-6 Brevard County estimated percent complete of that section. A maximum of 75% will be payable, with the remaining 25% payable after any applicable project close out requirements have been satisfied.

Item Z.02.01, Z.02.02, and Z.02.03 DMMA Management – Dewater, Material Transport, & Disposal

This bid item shall include all quantity-based costs associated with the dewatering, transportation, and beneficial reuse or disposal of the dewatered dredge material. Costs may include, but are not limited to, excavation, site maintenance, grading, hauling, handling, and disposal of material.

The work specified under this section shall be paid for at the Contract unit price. Truck haul tickets will be used to estimate the total yardage hauled from the DMMA for the purpose of progress payment only. In no case shall the final material transport and disposal volume exceed the cumulative total dredge volume. If amendments or bulking materials are brought onsite to aid in dewatering, these materials will not be included in the final quantities for payment. Final payments will utilize the cumulative quantity/volume based on the dredge Items Z.01.01, Z.01.02, and Z.01.03 quantities.

This Pay Item is eligible for adjustments due to variations in estimated quantities as described in Specification Section 00 41 00. Adjustments may only be made to the pay section in which the quantity varied above 125% or below 75% of the estimated quantity for that pay section.

END OF SECTION 01 20 00

BID NO. B-6-25-24 01 32-16-1 Brevard County

SECTION 01 32 16

CONSTRUCTION PROGRESS SCHEDULE

PART 1: GENERAL

1.01 SUBMITTALS

A. Within fifteen (15) days of Notice to Proceed, CONTRACTOR shall prepare and submit to the COUNTY for review and acceptance a Construction Progress Schedule in the form of a Bar Chart Schedule.

B. The schedule shall include all mobilization/demobilizations and anticipated work schedule for dredging, dewatering, and hauling of material in accordance with all regulatory permit restrictions, as well as construction and restoration of the dewatering site and offsite disposal area.

1.02 ACCEPTANCE

The acceptance of a Baseline Construction Schedule is a condition precedent to:

1. CONTRACTOR starting work on the construction stages of the contract.

2. Processing CONTRACTOR's invoice(s) for construction activities/items of work.

3. Review of any schedule updates.

B. Submittal of the Construction Progress Schedule and subsequent schedule updates, must be understood to be the CONTRACTOR's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the CONTRACTOR' s plan on how the work must be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced.

1.03 SCHEDULE FORMAT

A. Bar Chart Schedule

The Bar Chart must show work activities, submittals, COUNTY review periods, material/equipment deliveries, active dewatering system and site construction, dredging sections, dewatering, dredged material removal and disposal/reuse, inspections and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet or scheduling program.

B. Schedule Submittals and Procedures

Submit Bar Chart Schedules and updates in hard copy and digital format to COUNTY and ENGINEER. Submit digital copy of the Construction Progress Schedule in a format that is acceptable to COUNTY.

BID NO. B-6-25-24 01 32-16-2 Brevard County

1.04 WEEKLY SCHEDULE UPDATES

A. Update the Construction Progress Schedule and submit to COUNTY and ENGINEER at the weekly Construction Meetings or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining Work. With each updated schedule submitted the COUNTRACTOR shall provide the following:

1. Narrative Report: Provide a concise report with schedule updates. Identify and justify:

a. Progress made in each area of the Project;

b. Critical path;

c. Date/time constraints other than those required in the Contract;

d. Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones planned sequence of operations and critical path;

e. Status of Contract Completion Date and interim milestones;

f. Current and anticipated delays (describe cause of delay and corrective action(s)and mitigation measures to minimize); and

g. Description of current and future schedule problem areas.

1.05 2-WEEK LOOK AHEAD SCHEDULE

The CONTRACTOR must prepare and issue a 2-Week Look Ahead Schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Progress Schedule. The Look Ahead Schedule must be delivered in coordination with the Weekly Construction Progress Meeting.

1.06 WEEKLY PROGRESS MEETINGS

The CONTRACTOR shall prepare for and participate in a weekly progress meeting with COUNTY for the purpose of jointly reviewing the actual progress as compared to the planned progress, and to review planned activities for current week and the upcoming two weeks. Use the current approved schedule update for the purpose of this meeting.

PART 2: PRODUCTS

(Not Used)

PART 3: EXECUTION

(Not Used)

END OF SECTION 01 32 16

BID NO. B-6-25-24 01 33 00-1 Brevard County

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1: GENERAL

1.01 SUMMARY

The COUNTY may request submittals in addition to those specified when deemed necessary to adequately describe the Work covered in the respective sections.

Units of weights and measures used in all submittals are to be the same as those used in the Drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with the Contract requirements.

CONTRACTOR's Quality Control Manager is to check and approve all items prior to submittal and stamp, sign, and date indicating the action taken. Proposed deviations from the Contract requirements are to be clearly identified. Include within submittals items such as: CONTRACTOR's, manufacturer's or fabricator's drawings; descriptive literature including but not limited to catalog cuts, diagrams, operating charts of curves; test reports, samples; certifications; and other such required submittals.

Submittals requiring COUNTY/ENGINEER review are to be scheduled and made prior to the acquisition of the item covered thereby. Pickup and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

COUNTY or ENGINEER may develop a project teamsite to more efficiently track the project submittals. If developed, CONTRACTOR shall use the teamsite to submit project deliverables.

CONTRACTOR is responsible for scheduling submittals with sufficient time for COUNTY and ENGINEER to review prior to delivery, mobilization, or execution of applicable work. If any work is performed prior to written notification of review with no further comment(s) by the COUNTY or their ENGINEER of the respective submittal, CONTRACTOR assumes any risk associated with that work. CONTRACTOR should allow up to 15 calendar days for submittals requiring COUNTY review.

1.02 SUBMITTALS

A. Construction Progress Schedule

See Section 01 32 16 Construction Project Schedule

B. Submittal Register

CONTRACTOR shall provide, for review by the COUNTY or ENGINEER, a Submittal Register, consisting of all submittals required by CONTRACTOR to COUNTY, as part of the preconstruction submittal package.

C. Transmittal Form

BID NO. B-6-25-24 01 33 00-2 Brevard County

CONTRACTOR shall submit a sample transmittal form to use for submittals to

COUNTY/ENGINEER.

D. Weekly Progress Schedule Updates

See Section 01 32 16 Construction Project Schedule

E. Daily Progress Reports

Daily QC Logs will be submitted to COUNTY/ENGINEER within 24 hours of the day the report is documenting. The QC report will contain information regarding dredge and DMMA activity with the following information:

1. Project Name and Date of Report

2. Field notes of all surveys;

3. Basic production details for dredging

a. Dredge Location – Station

b. Daily and Total Dredge Volume (Cubic Yards)

c. Dredge Operating Hours and Downtime

4. Basic production details at DMMA

a. Daily and Total Volume Discharge from DMMA

b. Daily Minimum Freeboard at DMMA

5. Personnel on Dredge and/or DMMA Site

6. Equipment at Dredge and/or DMMA Site

7. Condition of all navigation aids (i.e., warning signs, lighted marker buoys) and any repairs performed on them;

8. Weather and Sea Conditions (adverse weather day, wind speed and direction, temperature, wave height, precipitation, etc.)

9. The amount of time lost to severe weather, personnel injury, turbidity violations, encounters with threatened or endangered species, etc

10. Notes regarding compliance with the Progress Schedule;

11. Standby Time (Daily and Total) – As directed by COUNTY

12. Time daily pipeline inspection was completed.

13. Notes/Comments

14. Visitor log

15. Copy of leverman’s log

A template of Contractor’s Daily Progress Report shall be submitted to COUNTY at least 14 days prior to the Pre-Construction Conference. Daily progress reports shall be submitted to the ENGINEER within 24 hours of the day the report is documenting in a digital format (Adobe Acrobat® Format or approved equal). The typical form for Daily Progress Reports shall be developed by Contractor and incorporated into the Work Plan.

F. Dredge Material Management Facility Plan

CONTRACTOR shall submit a Dredge Material Management Facility Plan (DMMF) to COUNTY for review at least fourteen (14) days prior to the Pre-Construction Conference. CONTRACTOR shall acknowledge that the plan is consistent with the Drawings, Specifications and FIND Lease requirements.

The plan will include:

1. Timelines for the construction of the dewatering site and for the commencement of dredging activities and completion of the Project, BID NO. B-6-25-24 01 33 00-3 Brevard County

2. If CONTRACTOR elects to use another DMMA besides the BV-52 site.

3. CONTRACTOR shall acknowledge and take measures for the control and abatement of noise, vibration, and odor impacts on surrounding properties, that are consistent with the Drawings, Specifications and FIND Lease requirements.

4. Discussion of the general operating procedures of the dredging and dredged material placement operations that show that these operating procedures (free board, ponding depth, water control structure, etc.) are consistent with the Drawings, Specifications, FIND Lease, and FIND Long Range Dredged Material Management Plan Update.

5. A pre- and post-construction topographic survey plan of the DMMA Facility that provides the conditions of the site overlain on the DMMA BV-52 As- Built (in plan and cross-section view) and that provides a detailed comparison of pre-dredging and post-dredging topographic survey conditions. Survey will include access ramps, access roads, placement and elevation of internal and external berms, surface drainage, seepage drainage, and erosion control features, etc. This submittal will include AutoCAD files of the site plan with detailed 3-D terrain model to demonstrate the quantity of dredged material placed and subsequently removed from the site.

6. A narrative detailing the means and methods for a proposed active dewatering system. The narrative shall include a detailed plan for loading and unloading the facility, dewatering and segregation of dredged materials, and stormwater releases. This plan shall outline the site's management activities before, during, and after dredging activities and will assure establishment and maintenance of a vegetative cover, safety, and adequate post-dredging operations. This submittal should include discussion of activities within the pipeline corridor. This submittal should include discussion on the grouting of gopher tortoise holes located on the FIND BV-52 DMMA.

7. Supplemental information and documentation as necessary for regulatory approval and permit modification.

G. Dewatering Facility As-Builts

1. A signed and sealed as-built topographic survey of the completed dewatering facility to be provided to COUNTY. Survey will include access roads, surface drainage, seepage drainage, erosion control features, dewatering equipment, etc. This submittal will include AutoCAD files of the site plan with detailed 3- D terrain model.

H. Dredge Material Management Plan

CONTRACTOR shall prepare and submit no less than fourteen (14) days prior to the commencement of dredge activities to COUNTY and ENGINEER a dredge plan that identifies CONTRACTOR’s order of execution of the dredging operations. Plan shall also discribe the approach and methodologies for the before dredge survey and after dredge survey.

I. Pipeline Plan

BID NO. B-6-25-24 01 33 00-4 Brevard County

CONTRACTOR shall prepare and submit no less than fourteen (14) days prior to the Pre-Construction Conference to COUNTY a pipeline plan for review.

1. The plan shall include the following:

a. Delineation of the pipeline placement within the dredge area to the pipeline corridor as reflected on the Drawings.

b. Pipeline installation details including pipeline anchoring method and survey of pipeline once installed

c. Indication of whether pipeline is floating or submerged

d. Proposed lighting/marker details on pipeline.

e. Location of proposed booster pump(s)

f. Details for daily pipeline inspection.

J. Dredged Material Removal Plan

CONTRACTOR shall submit a Dredged Material Removal Plan (DMRP) to COUNTY/ENGINEER at least fourteen (14) days prior to the pre-construction meeting for its review until no further comment(s) by COUNTY. This plan will describe: the means and methods of hauling and disposal of the decanted material and how these relate to ongoing operations and geotechnical stability of the Facility; the timeline for the commencement and completion of the removal of dredged material from the DMMA; the estimated number of trips per day; the truck haul route to and from the DMMA and the disposal site, the primary and backup disposal sites for the dredged materials; a written contract with the owner or operator of the primary disposal site agreeing to accept the dredged material; any land alterations or permits by regulatory agencies; and the measures to keep the streets used free from spilled materials and to repair any damage to the streets.

CONTRACTOR shall acknowledge that the plan is consistent with the Drawings, Specifications, and the FIND Lease requirements.

K. Material Testing Results

CONTRACTOR shall submit test results as specified in Section 31 00 00 Earthwork.

L. Maintenance of Traffic Plan

CONTRACTOR shall submit a maintenance of traffic plan as specified in Section 01 55 26 Maintenance of Traffic, on the plans, and in accordance with the Florida Department of Transportation to COUNTY for review at least fourteen (14) days prior to the pre-construction meeting.

M. Hurricane and Severe Storm Plan

CONTRACTOR shall develop and maintain a written Hurricane and Severe Storm Plan. The Plan shall include, but not be limited to, the following:

BID NO. B-6-25-24 01 33 00-5 Brevard County