This document outlines the planned timeline and milestones for the Army's solicitation and award of the ARNORTH CSTA Training Support Services contract. Key details include:

The Army plans to release a final solicitation for ARNORTH CSTA Training Support Services by 15 July 2023 to support a contract award date of 15 January 2024. The incumbent contractor's current contract ends on that date. The solicitation will include evaluation factors for program management, past performance, and cost/price with proposals due approximately 30 days after release. Technical evaluations are scheduled for completion by mid-August 2023 with negotiations with offerors in the competitive range slated to conclude by early September 2023. Revised proposals will be evaluated in late September with an award decision targeted for mid-October 2023. Post-award activities including debriefings and contract transition are outlined through mid-2024. The Army Materiel Command Contracting Command Orlando Contracting Center will manage the solicitation and award process.

View the file

Other files for this federal contract opportunity

Other files attached to ARNORTH CSTA Training Support Services, newest first.
File Type Posted
W900KK24R0023_CSTA_CBRN_Solicitation_CONFORMED_as_of_Amendment_0003.pdf PDF
Attachment_5_CSTA_CBRN_Labor_Pricing_Workbook_Rev5_8_May_2024.xlsx XLSX spreadsheet
Amendment_0003_W900KK24R0023_CSTA_CBRN_Solicitation.pdf PDF
Attachment 5 Labor Pricing Workbook Rev 4_1 May 2024.xlsx XLSX spreadsheet
Attachment 1 PWS_USARNORTH_CSTA_CBRN_Training_3 May 24.docx DOCX document
W900KK24R0023_CSTA_Solicitation_Amendment 0002_Conformed.pdf PDF
W900KK24R0023_CSTA_Solicitation_Amendment 0002.pdf PDF
W900KK24R0023_CSTA_Solicitation_Amendment 0001_Conformed.pdf PDF
CSTA PWS TECHNICAL EXHIBIT D Historical Workload Data_R1.pdf PDF
Attachment 1 PWS_USARNORTH_CSTA_CBRN_Training_19 April 24.docx DOCX document
Attachment 8 CSTA_Price_Workbook rev2 19 Apr 24.xlsx XLSX spreadsheet
W900KK24R0023_CSTA_Solicitation_Amendment 0001.pdf PDF
Attachment 5 Labor Pricing Workbook Rev 3_19 Apr 2024.xlsx XLSX spreadsheet
Attachment 7 Consolidated Question_Comment_Form_R1.xlsx XLSX spreadsheet
CSTA CDRLs Portfolio (1).pdf PDF
CSTA PWS TECHNICAL EXHIBIT C (T and EOs).pdf PDF
CSTA PWS TECHNICAL EXHIBIT A Perf Rqmnts Summary.pdf PDF
Attachment 7 Question_Comment_Form.xlsx XLSX spreadsheet
Attachment 1 PWS_USARNORTH_CSTA_CBRN_Training 1 April 24.pdf PDF
CSTA PWS TECHNICAL EXHIBIT B Deliverables Schedule.pdf PDF
Attachment 4 CTSA_Past_Performance_Rating_Form.pdf PDF
CSTA PWS TECHNICAL EXHIBIT D Historical Workload Data.pdf PDF
CSTA PWS TECHNICAL EXHIBIT F CTECC.pdf PDF
CSTA PWS TECHNICAL EXHIBIT E Incidental Property.pdf PDF
Attachment 5 Labor Pricing Workbook Rev 2_23 Mar 2024.xlsx XLSX spreadsheet
Attachment 2 CSTA DD Form 254.pdf PDF
Attachment 8 CSTA_Price_Workbook rev1 21MAR24.xlsx XLSX spreadsheet
W900KK24R0023_CSTA_Solicitation.pdf PDF
Attachment 3 CSTA_GFP_List.xlsx XLSX spreadsheet
Attachment 6 ARNORTH_CSTA_QASP.pdf PDF
Attachment 9 Cost Pricing Proposal Adequacy Checklist.pdf PDF
ARNORTH_CSTA_Info_Brief.pdf PDF
DRAFT_Solicitation_W900KK_24_R_0023_ARNORTH_CSTA_CBRN_Training_updated_22_Feb_2024.pdf PDF
PWS_USARNORTH_CSTA_CBRN_Training.pdf PDF
QASP_USARNORTH_CSTA_CBRN_Training.pdf PDF
Attachment_6_Labor_Pricing_Workbook_22 Feb 2024.xlsx XLSX spreadsheet
W900KK-24-R-0023.pdf PDF
(Final Draft) USARNORTH CBRN TRNG PLAN EVAL EXER PWS (19 Oct 23).docx DOCX document
DRAFTW900K240023.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milestones

US ARNORTH CSTA Training Support Services
Program:US ARNORTH CSTA Training Support Services (supported through PEO STRI)PANORL 23-P-0000 000569
MilestonesEstimatedStartComp.RevisedFurther Revised*ORG
LengthDateDateStartComp.StartComp.Code
PRESOLICITATION
1Team Bailey notified of requirement111/2/22RA / PM
2PMO submits:
DRAFT PWS6211/2/221/3/23RA / PM
DRAFT Questions for Industry151/3/231/18/23RA / PM
Suggested NAICS and PSC1/10/23RA / PM
3ACC-ORL Provides Feedback on:
DRAFT PWS281/3/231/31/23ACC-O
DRAFT Questions for Industry1/31/23ACC-O
Suggested NAICS and PSC1/31/23ACC-O
4SSN drafted1/31/232/27/23ACC-O / RA / PM
5Small Business Review of DRAFT SSN12/27/232/27/23ACC-O
6Submit FINAL DRAFT PWS for inclusion in SSN381/31/233/10/23RA / PM
7SSN PANORL-23-P-0000 000569 finalized and issued to industry73/10/233/17/23ACC-O
8Initial SSN closed (approx 20 days) and responses submitted203/17/234/6/23Industry
9Evaluate Responses and update requirements documents104/10/234/20/235/3/23RA / PM
10Requirement Change - Issue supplemental SSN (if needed)
11SSN closed
12Evaluate Responses and update requirements documents
13Program Office submits final documents in support of solicitation:
Results of SSN response evaluation14/20/234/21/2312/31/99RA / PM
CHESS ITAS Approval/Waiver (applicable to IT only)
CHESS Statement of NonAvailability (applicable to IT only)
Market Research Report463/6/234/21/23RA / PM
Combined AP/SAS3/6/234/21/23RA / PM
DRAFT Evaluation Criteria3/6/234/21/23RA / PM
FINAL PWS154/21/235/6/23RA / PM
Signed AT/OPSEC Coversheet4/21/235/6/23RA / PM
Final QASP (ACC-O template)4/21/235/6/23RA / PM
Final CDRL FORM DD 1423 (word version)4/21/235/6/23RA / PM
Signed Independent Government Estimate (IGE)4/21/235/6/23RA / PM
Signed DRAFT DD 2544/21/235/6/23RA / PM
GFP Justification Letter4/21/235/6/23RA / PM
GFP Attachment submitted in PIEE4/21/235/6/23RA / PM
Signed Request for Services Contract Approval (RSCA) form4/21/235/6/23RA / PM
Funds Assurance Letter/Promissory Note4/21/235/6/23RA / PM
Signed Requirements Package Checklist4/21/235/6/23RA / PM
14Program Office submits Final Requirements Package4/21/235/6/23RA / PM
15Contracting Office Accepts Requirement Package15/6/235/6/23ACC-O
16GFP Justification Letter Approved/Signed5/6/23ACC-O
17GFP Attachment Approved in PIEE5/6/23ACC-O
18Market Research Report Approved5/6/23ACC-O
19Combined AP/SAS Approved5/6/23ACC-O
20SBA Offer / Acceptance Correspondence [8(a) acquisition]5/6/23ACC-O / SBA
21Small Business Coordination DD2579 Signed5/6/23ACC-O
22Prepare D&F - inclusion and evaluation of options5/6/23ACC-O
23Prepare D&F - contract type (if applicable)5/6/23ACC-O
SOLICITATION AND EVALUATION
24Develop RFP/RFQ Including Section L&M4/21/235/6/23ACC-O / RA / PMIn Process
25PCO review of RFP/RFQ
26Release DRAFT RFP/RFQ (Optional)1/29/24
27DRAFT RFP/RFQ Closes (Optional)2/2/24
28Review Industry input / Q&A received in response to DRAFT RFP/RFQ and Modify/Finalize RFP/RFQ based on industry Q&A on the DRAFT RFP/RFQ and any changes based on Program Requirements (Optional)2/9/24
29PCO review of Final RFP/RFQ05/6/235/11/232/18/24ACC-O
30Legal Review of RFP/RFQ5/6/235/11/232/20/24
31Solicitation Review Board305/11/236/10/2310/31/232/27/24ACC-O
32Release Final RFP/RFQ16/10/236/10/233/1/24ACC-O
33Proposal Submission306/10/237/10/234/1/24Industry
34Proposal Compliance Checklist - Proposals verified as meeting submission requirements; issues identified and evaluated for potential elimination from competition27/10/237/13/234/4/24ACC-O
35Source Selection Training27/13/237/15/234/22/24ACC-O / RA / PM
36Technical/Cost/Past Performance Evaluation (Concurrent)307/15/238/14/235/10/24ACC-O / RA / PM
37Technical/Cost/Past Performance Evaluation (Concurrent) Review by PCO and Legal58/14/238/19/235/20/24ACC-O
38Finalize Technical/Cost/Past Performance Evaluations58/19/238/24/235/24/24ACC-O / RA / PM
39Idenitify most highly rated responses, draft competitive range determination, and idenetify items for discussions (i.e. negotiations)58/24/238/29/235/24/24ACC-O / RA / PM
40Competitive Range Approved and Legal Review of Negotiation Topics58/29/239/3/235/31/24ACC-O
41Vendor notifications of exclusion from competitive range / debriefs59/3/239/8/236/3/24ACC-O / RA / PM
42Enter Negotiations with offerors in competitive range (Discussions per FAR Part 15)9/3/239/8/236/4/24ACC-O / RA / PM
43Revised Proposals Submitted159/8/239/23/236/14/24Industry
44Technical/Cost/Past Performance Evaluation (Concurrent)159/23/2310/8/236/19/24ACC-O / RA / PM
45Technical/Cost/Past Performance Evaluation (Concurrent) Review by PCO and Legal510/8/2310/13/236/21/24ACC-O
46Source Selection Decision Document completed and reviewed by PCO and Legal510/13/2310/18/236/21/24ACC-O
47Prepare Contract in (PD2)510/18/2310/23/236/14/24ACC-O
48Receive Final DD 254510/23/2310/28/236/14/24RA / PM
49Receive Certified Funds510/28/2311/2/236/1/24RA / PM
50ACC Contract Review Board3011/2/2312/2/236/25/24ACC-O
AWARD
51Congressional Notification Letter >$15M (See FAR 17.108 Congressional notification. | Acquisition.GOV)12/1/235/31/247/1/24ACC-O
52EEO Clearance Request >$10M (See 22.805 Procedures. | Acquisition.GOV)12/1/237/1/24ACC-O
53Final 8(a) award verification with SB12/1/236/2/24ACC-O / SBA
54Execute Contract Award (Final execution of award, FPDSN-G, etc)-112/2/2312/1/237/1/24ACC-O / Industry
POSTAWARD
55Post Award Debrief Preparations and Post Award Debriefs Scheduled12/2/2312/1/23PM / ACC-O / Industry
56Post Award Conference Slides for Awardee Prepared12/2/2312/1/237/1/24PM / ACC-O / Industry
57Post Award Conference Complete (# days after award per Contract)512/1/2312/6/237/15/24PM / ACC-O / Industry
58Post Award Debriefs Concluded for Unsuccessful Awardees12/1/237/9/24PM / ACC-O / Industry
59Verified nominated COR has required training minimums and conduct:12/1/236/15/24ACC-O / RA
COR Phase I training12/1/236/15/24ACC-O / RA
COR Phase II training12/1/236/15/24ACC-O / RA
60COR appointment JAM (Requires award to be in EDA)12/1/237/2/24ACC-O / Industry
61Contract Registration in CPARS12/1/23ACC-O
62Transition of Support Services (Transition In Period of new contract)301/15/242/14/248/1/24Customer / Industry
PROTEST / PROTEST CORRECTIVE ACTION
1Technical, Past Performance, and Cost Re-Evaluation (Concurrent)
2Technical Consensus Meeting
3Technical Consensus Memo, Past Performance, and Cost Evaluations for Review
4PCO and Legal Review of Evaluation Documents
5Development of Discussion Points inclusive of Legal Review
6Discussions
7Amendment to Competitive Range Determination resulting from Discussions
8Proposal Revisions for Offerors Remaining in the Competitive Range
9Technical, Past Performance, and Cost Evaluation Revised Proposals (Concurrent)
10Finalization of Tech, Past Performance, and Cost Evaluation Documents inclusive of Legal Review
11Develop Source Selection Recommendation
12Source Selection Decision PCO
13Legal Review of Source Selection Decision
14Business Clearance Memorandum
15COR appointment in CORT Tool
16EEO Compliance Request
17Prepare Contract in PRISM
18PCO/Legal review of award documents
19Contract Award
20Post Award Conference
21Transition of Support Services
Total Length
Team MembersSignature/ApprovalDate
Program Management
Contracts Specialist
Contracts Team Lead
Contracts Branch Chief / Contracting Officer
Legal Counsel
What is the current PoP End Date for current CSTA Arnorth Contract

Current PALT Standard is 270 Days from Release of Final Solicitation. To meet your timeline of 15 Jan 2024, we would need to release the final soliciation by 15 Jul 2023 which is unrealistic, given our current workload of competing acquisitions that MUST be awarded by the end of the fiscal year (MTCCS II, ATROMS).