Contract_Pricing_Form_47PC0319R0003_2019_05_14.pdf
PDF 22 KB Posted
- Attached to
- General Construction Services for the Puerto Rico Hurricane Recovery Project Federal contract opportunity
- Solicitation number
- Not on record
About this file
Revised Contract Pricing Form dated May 14, 2019
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA Solicitation No. 47PC0319R0003 Puerto Rico Hurricane Recovery Project San Juan, PR May 14, 2019
CONTRACT PRICING FORM
CLIN
ITEM
PRICE
Base Contract
Option 1: Provide new 15,000 gallon fuel tank associated with Degetau Building emergency generator, specified in section 231213 – “Facility Aboveground Fuel-Oil Storage Tanks,” with associated work specified in Division 23 and Division 26. Associated sitework, site drainage relocation, and new parking layout. Locations and details are as indicated on the Volume 1 Drawings, labeled "Option 1".
Option 2: Federico Degetau Federal Building - Modernization of south-east elevators (four passenger) including elevator equipment, cab interior finishes, refurbish call buttons and hall indicators, as specified in section 142123 – “Electric Traction Passenger Elevator”, and 142713 – “Custom Elevator Cabs”. Associated work specified in Division 26 and Division 28. Locations and details are as indicated on the Volume 1 Drawings, labeled "Option 2".
Option 3: Federico Degetau Federal Building - Flooring replacement at basement elevator lobby in Degetau Building, specified in Sections 096513 – “Resilient Base,” and Section 096543 – “Linoleum Flooring.”
Locations and details are as indicated on the Volume 1 Drawings, labeled “Option 3”.
Option 4: Federico Degetau Federal Building – Below-grade exterior wall waterproofing at the Link Building, specified in Section “071326 – Self-Adhering Sheet Waterproofing.” Locations and details are as indicated on Volume 1 Drawings, labeled “Option 4.”
Option No. 5A: Partial flooring replacement throughout Rainforest Kids Childcare Development Center, as specified in Section 096515
– “Resilient Flooring,” and 093013 – “Tiling.” Locations and details are as indicated on Volume 2 Drawings, labeled “Option 5A.”
Option No. 5B: Full flooring replacement throughout Rainforest Kids Childcare Development Center, as specified in Section 096515 – “Resilient Flooring,” and 093013 – “Tiling.” Locations and details are as indicated on Volume 2 Drawings, labeled “Option 5A.”
Option No. 6: Refurbish existing Bahama style shutters at Rainforest Kids Child Development Center, reinstall with refurbished/replaced hardware following installation of new windows. Locations and details are as indicated on the Volume 2 Drawings, labeled “Option 6.”
Option No. 7: Additional Degetau generator building modifications (specified in sections including but not limited to: 031000 - Concrete Forming and Accessories; 032000 - Concrete Reinforcing; 033000 - Cast-In-Place Concrete; 052100 - Steel Joist Framing; 053100 - Steel Decking; 089116 - Operable Wall Louvers; 089119 - Fixed Louvers); additional generator replacement (specified in sections including but not limited to: 263213.15 – Diesel Generator – Degetau); and associated work. Locations and details are as indicated on Volume 1 Drawings, labeled “Option 7.”
GSA Solicitation No. 47PC0319R0003 Puerto Rico Hurricane Recovery Project San Juan, PR May 14, 2019
Total of Options (Sum of 2-7; 9-10)
Total of ALL Options (Sum of 2-6; 8-10)
Total Evaluated Price (Sum of 1-10)
OPTIONAL BID RATES
Contractor’s Overhead Rate for Adjustments %
Contractor’s Profit Rate for Adjustments %
Subcontractor’s Overhead Rate for Adjustments %
Subcontractor’s Profit Rate for Adjustments %
Contractor’s Daily Rate for Compensable Project Delay (Work Day) $
File details come from the government source that posted it.