Amendment_2_-_47PC0319R0003.pdf
PDF 46 KB Posted
- Attached to
- General Construction Services for the Puerto Rico Hurricane Recovery Project Federal contract opportunity
- Solicitation number
- Not on record
About this file
Amendment 2
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2PQC
Winnie Eng, Senior Contracting Officer
Please see attached.
General Services Administration Public Buildings Service One World Trade Center, 55th Floor New York, NY 10007
General Services Administration Public Buildings Service One World Trade Center, 55th Floor New York, NY 10007
47PC0319R0003
1 3
04/24/2019
04/11/2019
PUERTO RICO HURRICANE RECOVERY PROJECT
SAN JUAN, PR GSA-PBS, REGION 2
SOLICITATION NO. 47PC0319R0003
AMENDMENT NO. 2
Amendment No. 2 is hereby issued as follows:
1. The drawings for Rainforest Kids Child Development Center are hereby incorporated.
2. The following drawings are to be removed from the Construction Package I, Volume 2 Rainforest Kids drawing set:
HZ-1
HZ-2
3. There is no space for material storage on site. All materials required for the project must be brought on site as needed.
4. Add the following paragraph to Specification 017320, Section 3.3: Contractor is responsible for all removal and relocation of furniture to a bonded, humidity-controlled (per GSA P100) warehouse to be stored during the construction period. Contractor is also responsible for return and replacement of furniture in previous locations at completion of construction activities (with concurrence from GSA COR).
5. Add the following verbiage to Note 4 on Sheet AD-133 of Construction Package 1, Volume 1 of 2: Contractor is responsible for all removal and relocation of furniture to a bonded, humidity-controlled (per GSA P100) warehouse to be stored during the construction period. Contractor is also responsible for return and replacement of furniture in previous locations at completion of construction activities (with concurrence from GSA COR).
6. Section III.B of the “Solicitation GC PR Hurricane Recovery” shall be replaced with the following (changes in red):
III.B. Requests for Clarification or Interpretation The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 7 calendar days. Prospective Offerors should make such requests not less than 7 calendar days prior to the date set for receipt of offers.
PUERTO RICO HURRICANE RECOVERY PROJECT
SAN JUAN, PR GSA-PBS, REGION 2
SOLICITATION NO. 47PC0319R0003
AMENDMENT NO. 2
7. For reference, the Period of Performance is as follows:
The Contractor shall achieve Substantial Completion of the Work no later than 541 calendar days from issuance of Notice to Proceed (NTP).
Scope Substantial Completion / Duration
(Calendar Days)
(1) Replace Roof of Nazario Courthouse
(2) Replace Roof of Child Care Center
(3) Install generator of Degetau FOB w/ Extension of Generator Room
(4) Install New Generator at Child Care Center
(5) Ins Basement Foundation Wall Leak
(Option #3) Exterior below grade waterproofing at Link
(Option #4) Install additional generator of Degetau FOB
351 Days from Base NTP
(1) Parking PV Connections
(2) Water Well Installation
421 Days from Base NTP
(1) Hurricane Resistant Fence Installation
(2) Degetau - NW Elevators & Freight Elevators
(3) Nazario - Judges Elevator
(4) Nazario Courthouse Millwork
(5) Child Care - Interior Paint, Façade Repair & Replace Exterior windows and Doors
(Option #1) 15000 gal fuel tank
(Option #2) SE elevators
(Option #5) Replace Vinyl Flooring - partial flooring replacement
(Option #6) Replace Vinyl Flooring - full flooring replacement
(Option #7) Shutter Refurb
(Option #8) Degetau flooring replacement at basement
541 Days from Base NTP
The date and time for receipt of proposals remains unchanged.
END OF AMENDMENT NO. 2