This document is a construction contract agreement between the City of Waxahachie, Texas and an unnamed contractor for the North Grove Park project located at 525 E North Grove Boulevard. The project involves constructing a new public park, which includes removing existing infrastructure and installing various amenities such as trails, covered bench seating, a parking lot with signage and striping, pavilions, a decomposed granite mixed-use space, an inclusive playground with poured-in-place surfacing, a restroom enclosure, landscape, irrigation, drinking fountain, site furnishings, a stone-veneered seat wall, hardscape elements, water line extension, storm and drainage elements, site lighting and electrical improvements, and utility connections. The contractor will be responsible for furnishing all labor, materials, and equipment to complete the project according to the civil construction plans.

The contract does not specify the exact contract price, which will be filled in later, but outlines detailed payment procedures including progress payments, retainage, and substantial completion requirements. The contractor will be subject to liquidated damages ranging from $200 to $1,000 per day for unexcused delays, depending on the total contract value. The project includes comprehensive insurance requirements, with the contractor required to carry commercial general liability insurance with limits of $2 million, workers' compensation insurance, automobile liability insurance, and umbrella liability coverage of $4 million. The contract term appears to be for the duration of the project, with completion expected in 2025, and includes provisions for potential changes, termination, and dispute resolution.

View the file

Other files

File Type Posted
North_Grove_Park_-_PreBID_Meeting_10-2-2025_Attendance_Summary.pdf PDF
North_Grove_Park_(Addendum_#1_Revision).pdf PDF
North_Grove_Park_(Addendum_#1_Revision).pdf PDF
NoticeTo_Bidders_-_North_Grove_Park.pdf PDF
NoticeTo_Bidders_-_North_Grove_Park.pdf PDF
2025-09-12_North_Grove_Final_OPCC_(updated_per_market_changes).pdf PDF
2025-09-12_North_Grove_Final_OPCC_(updated_per_market_changes).pdf PDF
2025-09-12_North_Grove_Final_OPCC_(updated_per_market_changes).pdf PDF
Excel_Bid_Form_North_Grove_Park.xlsx XLSX spreadsheet
Excel_Bid_Form_North_Grove_Park.xlsx XLSX spreadsheet
Excel_Bid_Form_North_Grove_Park.xlsx XLSX spreadsheet
Technical_Specifications_-_North_Grove_Park.pdf PDF
Technical_Specifications_-_North_Grove_Park.pdf PDF
Wages_Rates_-_North_Grove_Park.pdf PDF
Wages_Rates_-_North_Grove_Park.pdf PDF
Wages_Rates_-_North_Grove_Park.pdf PDF
Special_Conditions_-_North_Grove_Park.pdf PDF
Special_Conditions_-_North_Grove_Park.pdf PDF
Special_Conditions_-_North_Grove_Park.pdf PDF
Construction_Methods.pdf PDF
Construction_Methods.pdf PDF
Construction_Methods.pdf PDF
General_Provisions_-_North_Grove_Park.pdf PDF
General_Provisions_-_North_Grove_Park.pdf PDF
General_Provisions_-_North_Grove_Park.pdf PDF
Performance_Bond,_Payment_Bond,_Maintenance_Bond.pdf PDF
Performance_Bond,_Payment_Bond,_Maintenance_Bond.pdf PDF
Performance_Bond,_Payment_Bond,_Maintenance_Bond.pdf PDF
Contract_Agreement_-_North_Grove_Park.pdf PDF
Contract_Agreement_-_North_Grove_Park.pdf PDF
Subcontractor_Portion_Response_-_North_Grove_Park.pdf PDF
Subcontractor_Portion_Response_-_North_Grove_Park.pdf PDF
Bidders_Signature_Response_-_North_Grove_Park.pdf PDF
Bidders_Signature_Response_-_North_Grove_Park.pdf PDF
Bidders_Signature_Response_-_North_Grove_Park.pdf PDF
2025-08-21_North_Grove_Park_Pay_Items.pdf PDF
2025-09-03_Bid_Proposal_Form_North_Grove_Park.pdf PDF
2025-09-03_Bid_Proposal_Form_North_Grove_Park.pdf PDF
2025-08-21_North_Grove_Park_Pay_Items.pdf PDF
2025-09-03_Bid_Proposal_Form_North_Grove_Park.pdf PDF
2025-08-21_North_Grove_Park_Pay_Items.pdf PDF
2025-08-29_North_Grove_Final_OPCC.pdf PDF
2025-08-29_North_Grove_Final_OPCC.pdf PDF
2025-08-29_North_Grove_Final_OPCC.pdf PDF
North_Grove_Park_Construction_Documents.pdf PDF
North_Grove_Park_Construction_Documents.pdf PDF
North_Grove_Park_Construction_Documents.pdf PDF
Pay_Items_-_North_Grove_Park.pdf PDF
Pay_Items_-_North_Grove_Park.pdf PDF
Pay_Items_-_North_Grove_Park.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF WAXAHACHIE PARKS DEPT AGREEMENT TM 48572

STATE OF TEXAS § CITY OF WAXAHACHIE, TEXAS

§ NORTH GROVE PARK

CONTRACT AGREEMENT

COUNTY OF ELLIS §

This Agreement is made by and between the City of Waxahachie, Texas ("Owner") and XXXXX (“Contractor”), for the construction of a new parking lot and site improvements as follows:

Furnishing all labor, material and equipment, and performing all work required to remove existing infrastructure and install all necessary paving, grading, drainage, and other improvements associated with the construction of a new public park (further described and shown on the Civil Construction Plans). All work is associated with the North Grove Park, hereinafter termed “Project.”

ARTICLE I

THE CONTRACT AND THE CONTRACT DOCUMENTS

1.1 The Contract

The Contract between the Owner and the Contractor, of which this Agreement is a part, consists of the Contract Documents. It shall be effective on the date this Agreement is executed by the last party to execute it.

1.2 The Contract Documents

The Contract Documents consist of this Agreement, Invitation to Bid, Requirements and Instructions to Bidders, Specifications, Drawings, Project Manual, all Change Orders and Field Orders issued hereafter, any other amendments hereto executed by the parties hereafter, together with the following (if any): Documents not enumerated in this Paragraph 2 are not Contract Documents and do not form part of this Contract.

1.3 Entire Agreement

This Contract, together with the Contractor's performance and payment bonds for the Project, all General Conditions, Special Conditions, Plans and Specifications, and Addenda attached thereto, constitute the entire and exclusive agreement between the Owner and the Contractor with reference to the Project. Specifically, but without limitation, this Contract supersedes any bid documents and all prior written or oral communications, representations and negotiations, if any, between the Owner and Contractor not expressly made a part hereof. In the event of a conflict between this Contract and any other document pertaining hereto, this Contract shall govern.

1.4 No Privity with Others

Nothing contained in this Contract shall create, or be interpreted to create, privity or any other contractual agreement between the Owner and any person or entity other than the Contractor.

1.5 Intent and Interpretation

A. The intent of this Contract is to require complete, correct and timely execution of the Work.

Any Work that may be required, implied or inferred by the Contract Documents, or any one or more of them, as necessary to produce the intended result shall be provided by the Contractor for the Contract Price.

B. This Contract is intended to be an integral whole and shall be interpreted as internally consistent. What is required by any one Contract Document shall be considered as required by the Contract.

C. When a word, term or phrase is used in this Contract, it shall be interpreted or construed, first, as defined herein; second, if not defined, according to its generally accepted meaning in the construction industry; and third, if there is no generally accepted meaning in the construction industry, according to its common and customary usage.

D. The words "include", "includes", or "including", as used in this Contract, shall be deemed to be followed by the phrase, "without limitation".

E. The specification herein of any act, failure, refusal, omission, event, occurrence or condition as constituting a material breach of this Contract shall not imply that any other, non-specified act, failure, refusal, omission, event, occurrence or condition shall be deemed not to constitute a material breach of this Contract.

F. Words or terms used as nouns in this Contract shall be inclusive of their singular and plural forms, unless the context of their usage clearly requires a contrary meaning.

G. The Contractor shall have a continuing duty to read, carefully study and compare each of the Contract Documents, Shop Drawings, Product Data and any Plans and Specifications.

The Contractor shall give written notice to the Owner of any inconsistency, ambiguity, error or omission which the Contractor may discover with respect to these documents before proceeding with the affected Work. The issuance, or the express or implied approval by the Owner or the Designee of the Contract Documents, Shop Drawings or Product Data shall not relieve the Contractor of the continuing duties imposed hereby, nor shall any such approval be evidence of the Contractor's compliance with this Contract. The Owner has requested the Designee to only prepare documents for the Project, including the Drawings and Specifications for the Project, which are accurate, adequate, consistent, coordinated and sufficient for construction. HOWEVER, THE OWNER MAKES NO

REPRESENTATION OR WARRANTY OF ANY NATURE WHATSOEVER TO THE

CONTRACTOR CONCERNING SUCH DOCUMENTS. By the execution hereof, the Contractor acknowledges and represents that it has received, reviewed and carefully examined such documents, has found them to be complete, accurate, adequate, consistent, coordinated and sufficient for construction, and that the Contractor has not, does not, and will not rely upon any representation or warranties by the Owner concerning such documents as no such representation or warranties have been or are hereby made. Further, the Contractor represents and warrants that it has had a sufficient opportunity to inspect the Project site and assumes any and all responsibility for inadequacies or ambiguities in the plans, drawings or specifications as well as for latent conditions of the site where the work is to be performed.

H. As between numbers and scaled measurements on the Drawings and in the Design, the numbers shall govern, as between larger scale and smaller scale drawings, the larger scale shall govern.

I. Neither the organization of any of the Contract Documents into divisions, sections, paragraphs, articles, (or other categories), nor the organization or arrangement of the Design, shall control the Contractor in dividing the Work or in establishing the extent or scope of the Work to be performed by Subcontractors.

1.6 Ownership of Contract Documents

The Contract Documents, and each of them, shall remain the property of the Owner. The Contractor shall have the right to keep one record set of the Contract Documents upon completion of the Project; provided, however, that in no event shall Contractor use, or permit to be used, any or all of such Contract Documents on other projects without the Owner's prior written authorization.

ARTICLE II

THE WORK

2.1 The Contractor shall perform all of the Work required, implied or reasonably inferable from this Contract.

2.2 Work

A. The term "Work" shall mean whatever is done by or required of the Contractor to perform and complete its duties under this Contract, including the following: construction of the whole or a designated part of the Projects; furnishing of any required bonds and insurance, and the provision or furnishing of labor, supervision, services, materials, supplies, equipment, fixtures, appliances, facilities, tools, transportation, storage, power, permits and licenses required of the Contractor, fuel, heat, light, cooling and all other utilities as required by this Contract. The Work to be performed by the Contractor is generally described as follows:

North Grove Park is located at 525 E North Grove Boulevard in Waxahachie. The park is adjacent to residential homes, future commercial/mixed use development, and North Grove Boulevard.

Refer to construction documents for limits of work, existing conditions, designated elements for removal, erosion control protection and installation, grading improvements, and tree fencing protection. The proposed project includes amenities such as trails, covered bench seating along trails, parking lot with signage and striping, pavilions, decomposed granite mixed use space, inclusive playground with poured in place surfacing, restroom enclosure, landscape, irrigation, drinking fountain, site furnishings, stone veneered seat wall, hardscape elements, water line extension, storm and drainage elements, site lighting and electrical improvements, and utility connections and improvements. Furnishing all labor, material and equipment, and performing all work required to remove existing infrastructure and install all amenities at North Grove Park (further described and shown per the Civil Construction Plans).

B. The Contractor shall be responsible for paying for and procuring all materials and labor and furnishing all services necessary or appropriate for the full performance of the Work and the for the full completion of the Projects. All materials shall be new and materials and workmanship shall be of good quality. Upon request, the Contractor shall furnish satisfactory proof of the type, kind, and quality of materials.

ARTICLE III

CONTRACT TIME

3.1 Time and Liquidated Damages

A. The Contractor shall commence the Work on a Project within ten (10) days of receipt of a written Notice to Proceed, and shall achieve Substantial Completion of the Work no later than any Substantial Completion date specified in the Notice to Proceed. The parties acknowledge that time is of the essence in the performance of the terms of this Contract.

The term “calendar days” shall mean any and all days of the week or month, no days being excepted. It is contemplated by the parties that the progress of the Work may be delayed by certain conditions beyond the control of the parties; these delays have been contemplated by the parties and considered in the time allotted for performance specified herein and includes, but is not limited to delays occasioned on account of adverse weather, temporary unavailability of materials, shipment delays, and the presence and potential interference of other contractors who may be performing work at the Project site unrelated to this agreement.

The number of calendar days from the date on which the Work is permitted to proceed, through the date set forth for Substantial Completion, shall constitute the "Contract Time" for a particular Project.

B. The Contractor shall pay the Owner liquidated damages based on the overall contract value for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the date set forth in a Notice to Proceed for Substantial Completion of the Work.

a. Less than 25,000.00 - $200 Per Day

b. 25,000.00 to 99,999.99 - $350 Per Day

c. 100,000.00 to 999,999.99 - $500 Per Day

d. More than 1,000,000.00 - $1,000 Per Day

Any sums due and payable hereunder by the Contractor shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the Owner, estimated at or before the time of executing this Contract. When the Owner reasonably believes that Substantial Completion will be inexcusably delayed, the Owner shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the Owner to be adequate to recover liquidated damages applicable to such delays. If and when the Contractor overcomes the delay in achieving Substantial Completion, or any part thereof, for which the Owner has withheld payment, the Owner shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.

C. In the event that the Contractor achieves certification of substantial completion prior to the scheduled completion date, the Owner shall pay to the Contractor the sum of $0.00 per day for each calendar day that substantial completion is certified in advance of the scheduled completion date for a particular Project.

D. No claim shall be made by the Contractor to the Owner, and no damages, costs or extra compensation shall be allowed or paid by the Owner to the Contractor for any delay or hindrance from any cause in the progress or completion of the Work for a particular Project or this Contract. The Contractor’s sole remedy in the event of any delay or hindrance shall be to request time extensions by written change orders as provided for hereinafter. Should the Contractor be delayed by an act of the Owner, or should the Owner order a stoppage of the Work for sufficient cause, an extension of time shall be granted by the Owner by written authorization upon written application, which extension shall not be unreasonably denied, to compensate for the delay.

E. The Owner shall have the authority to suspend the Work for any Project wholly or in part for such period or periods of time as it may deem appropriate due to unsuitable conditions considered unfavorable for the proper prosecution of the Work or for the failure of the Contractor to carry out instructions from the Owner or Owner’s representative. During any period in which the Work is stopped or during which any of the Work is not actively in progress for any reason, Contractor shall properly protect the site and the Work from damage, loss or harm.

3.2 Substantial Completion

A. "Substantial Completion" shall mean that stage in the progression of the Work for a particular Project when the Work is sufficiently complete in accordance with this Contract that the Owner can enjoy beneficial use or occupancy of the Work and can utilize the Work for its intended purpose, even though minor miscellaneous work and/or adjustment may be required.

3.3 Time is of the Essence

All limitations of time set forth in the Contract Documents are of the essence of this Contract.

ARTICLE IV

CONTRACT PRICE

The Owner shall pay, and the Contractor shall accept, as full and complete payment for all of the Work required herein, the fixed-rate sum of $______________. The sum set forth in this Paragraph shall constitute the Contract Price which shall not be modified except by written Change Order as provided in this Contract.

ARTICLE V

PAYMENT OF THE CONTRACT PRICE

5.1 Schedule of Values

Within ten (10) calendar days of the effective date hereof, the Contractor shall submit to the Owner and to the Designee a Schedule of Values allocating the Contract Price to the various portions of the Work and the per unit price for any supplies or materials to be charged to Owner to complete the Work. The Contractor's Schedule of Values shall be prepared in such form, with such detail, and supported by such data as the Owner may require to substantiate its accuracy. The Contractor shall not imbalance it’s Schedule of Values nor artificially inflate any element thereof.

The violation of this provision by the Contractor shall constitute a material breach of this Contract.

The Schedule of Values shall be used only as a basis for the Contractor's Applications for Payment and shall only constitute such basis after it has been acknowledged and accepted in writing by the Owner.

5.2 Payment Procedure

The Owner shall pay the Contract Price to the Contractor as provided below.

A. Progress Payments. Based upon the Contractor's Applications for Payment submitted to the Designee and upon Certificates for Payment subsequently issued to the Owner by the Designee, the Owner shall make progress payments to the Contractor on account of the Contract Price.

B. On or before the 25th day of each month after commencement of the Work for a particular Project, the Contractor shall submit an Application for Payment for the period ending the 15th day of the month to the Owner in such form and manner, and with such supporting data and content, as the Owner may require. Therein, the Contractor may request payment for ninety percent (90%) of that portion of the Contract Price properly allocable to Contract requirements properly provided, labor, materials and equipment properly incorporated in the Work, less the total amount of previous payments received from the Owner. Such Application for Payment shall be signed by the Contractor and shall constitute the Contractor's representation that the Work has progressed to the level for which payment is requested in accordance with the Schedule of Values, that the Work has been properly installed or performed in full compliance with this Contract and that the Contractor knows of no reason why payment should not be made as requested.

Thereafter, the Owner will review the Application for Payment and may also review the Work at the Project site or elsewhere to determine whether the quantity and quality of the Work is as represented in the Application for Payment and is as required by this Contract. The Owner shall make partial payments on account of the Contract Price to the Contractor within thirty (30) days following the Owner’s receipt and approval of each Application for Payment. The amount of each partial payment shall be the amount certified for payment by the Owner less such amounts, if any, otherwise owing by the Contractor to the Owner or which the Owner shall have the right to withhold as authorized by this Contract. The Owner's certification of the Contractor's Application for Payment shall not preclude the Owner from the exercise of any of its rights as set forth in Paragraph 5.3 herein below.

C. The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an Application for Payment, all Work for which payments have been received from the Owner shall be free and clear of liens, claims, security interest or other encumbrances in favor of the Contractor or any other person or entity whatsoever.

D. The Contractor shall promptly pay each Subcontractor out of the amount paid to the Contractor on account of such Subcontractor's Work, the amount to which such Subcontractor is entitled. In the event the Owner becomes informed that the Contractor has not paid a Subcontractor as herein provided, the Owner shall have the right, but not the duty, to issue future checks in payment to the Contractor of amounts otherwise due hereunder naming the Contractor and such Subcontractor as joint payees. Such joint check procedure, if employed by the Owner, shall create no rights in favor of any person or entity beyond the right of the named payees to payment of the check and shall not be deemed to commit the Owner to repeat the procedure in the future.

E. No progress payment, nor any use or occupancy of a Project by the Owner, shall be interpreted to constitute an acceptance of any Work not in strict accordance with this Contract.

F. Retainage: For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold five percent (5%) of the amount included within that period’s pay application.

5.3 Withheld Payment

The Owner may decline to make payment, may withhold funds, and, if necessary, may demand the return of some or all of the amounts previously paid to the Contractor, to protect the Owner from loss because of:

(i) Defective Work not remedied by the Contractor nor, in the opinion of the Owner, likely to be remedied by the Contractor;

(ii) claims of third parties against the Owner or the Owner's property;

(iii) failure by the Contractor to pay Subcontractors or others in a prompt and proper fashion;

(iv) evidence that the balance of the Work cannot be completed in accordance with the

Contract for the unpaid balance of the Contract Price,

(v) evidence that the Work will not be completed in the time required for substantial or final completion;

(vi) persistent failure to carry out the Work in accordance with the Contract;

(vii) damage to the Owner or a third party to whom the Owner is, or may be, liable.

In the event that the Owner makes written demand upon the Contractor for amounts previously paid by the Owner as contemplated in this Subparagraph 5.3.1, the Contractor shall promptly comply with such demand. The Owner shall have no duty to third parties to withhold payment to the Contractor and shall incur no liability for a failure to withhold funds.

5.4 Unexcused Failure to Pay

If within fifteen (15) days after the date established herein for payment to the Contractor by the Owner, the Owner, without cause or basis hereunder, fails to pay the Contractor any amount then due and payable to the Contractor, then the Contractor may after ten (10) additional days' written notice to the Owner and without prejudice to any other available rights or remedies it may have, stop the Work until payment of those amounts due from the Owner have been received. Late payments shall not accrue interest or other late charge.

5.5 Substantial Completion

When the Contractor believes that the Work is substantially complete, the Contractor shall submit to the Owner a list of items to be completed or corrected. When the Owner on the basis of an inspection determines that the Work is in fact substantially complete, it will prepare a Certificate of Substantial Completion which shall establish the date of Substantial Completion, shall state the responsibilities of the Owner and the Contractor for Project security, maintenance, heat, utilities, damage to the Work, and insurance, and shall fix the time within which the Contractor shall complete the items listed therein. Guarantees required by the Contract shall commence on the date of Substantial Completion of the Work. The Certificate of Substantial Completion shall be submitted to the Owner and the Contractor for their written acceptance of the responsibilities assigned to them in such certificate.

Upon Substantial Completion of the Work, and execution by both the Owner and the Contractor of the Certificate of Substantial Completion, the Owner shall pay the Contractor an amount sufficient to increase total payments to the Contractor to one hundred percent (100%) of the Contract Price less three hundred percent (300%) of the reasonable cost as determined by the Owner for completing all incomplete Work, correcting and bringing into conformance all defective and nonconforming Work, and handling all unsettled claims.

5.6 Completion and Final Payment

A. When all of the Work for a particular Project is finally complete and the Contractor is ready for a final inspection, it shall notify the Owner thereof in writing. Thereupon, the Owner will make final inspection of the Work and, if the Work is complete in full accordance with this Contract and this Contract has been fully performed, the Owner will promptly issue a final Certificate for Payment certifying to the Owner that the Project is complete and the Contractor is entitled to the remainder of the unpaid Contract Price, less any amount withheld pursuant to this Contract. If the Owner is unable to issue its final Certificate for Payment and is required to repeat its final inspection of the Work, the Contractor shall bear the cost of such repeat final inspection(s) which cost may be deducted by the Owner from the Contractor's final payment.

B. If the Contractor fails to achieve final completion within the time fixed therefor by the Owner in its Certificate of Substantial Completion, the Contractor shall pay the Owner the sum set forth hereinabove as liquidated damages per day for each and every calendar day of unexcused delay in achieving final completion beyond the date set forth herein for final completion of the Work. Any sums due and payable hereunder by the Contractor shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the Owner, estimated at or before the time of executing this Contract. When the Owner reasonably believes that final completion will be inexcusably delayed, the Owner shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the Owner to be adequate to recover liquidated damages applicable to such delays. If and when the Contractor overcomes the delay in achieving final completion, or any part thereof, for which the Owner has withheld payment, the Owner shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.

C. The Contractor shall not be entitled to final payment for a particular Project unless and until it submits to the Owner its affidavit that all payrolls, invoices for materials and equipment, and other liabilities connected with the Work for which the Owner, or the Owner's property might be responsible, have been fully paid or otherwise satisfied; releases and waivers of lien from all Subcontractors of the Contractor and of any and all other parties required by the Owner; consent of Surety, if any, to final payment. If any third party fails or refuses to provide a release of claim or waiver of lien as required by the Owner, the Contractor shall furnish a bond satisfactory to the Owner to discharge any such lien or indemnify the Owner from liability.

D. The Owner shall make final payment of all sums due the Contractor within ten (10) days of the Owner's execution of a final Certificate for Payment.

E. Acceptance of final payment shall constitute a waiver of all claims against the Owner by the Contractor except for those claims previously made in writing against the Owner by the Contractor, pending at the time of final payment, and identified in writing by the Contractor as unsettled at the time of its request for final payment.

F. Under no circumstance shall Contractor be entitled to receive interest on any payments or monies due Contractor by the Owner, whether the amount on which the interest may accrue is timely, late, wrongfully withheld, or an assessment of damages of any kind.

ARTICLE VI

THE OWNER

6.1 Information, Services and Things Required from Owner

A. The Owner shall furnish to the Contractor, at the time of executing this Contract, any and all written and tangible material in its possession concerning conditions below ground at the site of a particular Project.

B. Such written and tangible material is furnished to the Contractor only in order to make complete disclosure of such material and for no other purpose. By furnishing such material, the Owner does not represent, warrant, or guarantee its accuracy either in whole, in part, implicitly or explicitly, or at all, and shall have no liability therefor. The Owner shall also furnish surveys, legal limitations and utility locations (if known), and a legal description of the Project site.

C. Excluding permits and fees normally the responsibility of the Contractor, the Owner shall obtain all approvals, easements, and the like required for construction and shall pay for necessary assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities.

D. The Owner shall furnish the Contractor, free of charge, one copy of the Contract Documents for execution of the Work.

6.2 Right to Stop Work

If the Contractor persistently fails or refuses to perform the Work for any Project in accordance with this Contract, or if the best interests of the public health, safety or welfare so require, the Owner may order the Contractor to stop the Work, or any described portion thereof, until the cause for stoppage has been corrected, no longer exists, or the Owner orders that Work be resumed. In such event, the Contractor shall immediately obey such order.

6.3 Owner's Right to Perform Work

If the Contractor's Work on any Project is stopped by the Owner under Paragraph 6.2, and the Contractor fails within seven (7) days of such stoppage to provide adequate assurance to the Owner that the cause of such stoppage will be eliminated or corrected, then the Owner may, without prejudice to any other rights or remedies the Owner may have against the Contractor, proceed to carry out the subject Work. In such a situation, an appropriate Change Order shall be issued deducting from the Contract Price the cost of correcting the subject deficiencies, plus compensation for the Owner's additional services and expenses necessitated thereby, if any. If the unpaid portion of the Contract Price is insufficient to cover the amount due the Owner, the Contractor shall pay the difference to the Owner.

ARTICLE VII

THE CONTRACTOR

7.1 The Contractor is again reminded of its continuing duty set forth in Subparagraph 1.5.G.

The Contractor shall perform no part of the Work for a Project at any time without adequate Contract Documents or, as appropriate, approved Shop Drawings, Product Data or Samples for such portion of the Work. If the Contractor performs any of the Work knowing it involves a recognized error, inconsistency or omission in the Contract Documents without such notice to the Owner, the Contractor shall bear responsibility for such performance and shall bear the cost of correction.

7.2 The Contractor shall perform all Work strictly in accordance with this Contract.

7.3 The Contractor shall supervise and direct the Work using the Contractor's best skill, effort and attention. The Contractor shall be responsible to the Owner for any and all acts or omissions of the Contractor, its employees and others engaged in the Work on behalf of the Contractor.

A. The Contractor shall give adequate attention to the faithful prosecution of the Work and the timely completion of this Contract, with authority to determine the manner and means of performing such Work, so long as such methods insure timely completion and proper performance.

B. The Contractor shall exercise all appropriate means and measures to insure a safe and secure jobsite in order to avoid and prevent injury, damage or loss to persons or property.

7.4 Warranty

The Contractor warrants to the Owner that all labor furnished to progress the Work under this Contract will be competent to perform the tasks undertaken, that the product of such labor will yield only first-class results, that materials and equipment furnished will be of good quality and new unless otherwise permitted by this Contract, and that the Work will be of good quality, free from faults and defects and in strict conformance with this Contract. All Work not conforming to these requirements may be considered defective.

7.5 The Contractor shall obtain and pay for all permits, fees and licenses necessary and ordinary for the Work. The Contractor shall comply with all lawful requirements applicable to the Work and shall give and maintain any and all notices required by applicable law pertaining to the Work.

7.6 Supervision

A. The Contractor shall employ and maintain at the Project site only competent supervisory personnel. Absent written instruction from the Contractor to the contrary, the superintendent shall be deemed the Contractor's authorized representative at the site and shall be authorized to receive and accept any and all communications from the Owner.

B. Key supervisory personnel assigned by the Contractor to these Projects are as follows:

Name Function

_________________ Project Manager _________________ Excavation Supervisor _________________ Lead Operator

So long as the individuals named above remain actively employed or retained by the Contractor, they shall perform the functions indicated next to their names unless the Owner agrees to the contrary in writing. In the event one or more individuals not listed above subsequently assume one or more of those functions listed above, the Contractor shall be bound by the provisions of this Subparagraph 7.6.B as though such individuals had been listed above.7.7 The Contractor, within fifteen (15) days of commencing the Work on any Project, shall submit to the Owner for its information, the Contractor's schedule for completing the Work. The Contractor's schedule shall be revised no less frequently than monthly (unless the parties otherwise agree in writing) and shall be revised to reflect conditions encountered from time to time and shall be related to the entire Project. Each such revision shall be furnished to the Owner. Failure by the Contractor to strictly comply with the provisions of this Paragraph 7.7 shall constitute a material breach of this Contract.

7.8 The Contractor shall continuously maintain at the site, for the benefit of the Owner, one record copy of this Contract marked to record on a current basis changes, selections and modifications made during construction. Additionally, the Contractor shall maintain at the site for the Owner the approved Shop Drawings, Product Data, Samples and other similar required submittals. Upon final completion of the Work, all of these record documents shall be delivered to the Owner.

7.9 Shop Drawings, Product Data and Samples

A. Shop Drawings, Product Data, Samples and other submittals from the Contractor do not constitute Contract Documents. Their purpose is merely to demonstrate the manner in which the Contractor intends to implement the Work in conformance with information received from the Contract Documents.

B. The Contractor shall not perform any portion of the Work requiring submittal and review of Shop Drawings, Product Data or Samples unless and until such submittal shall have been approved by the Designee. Approval by the Owner, however, shall not be evidence that Work installed pursuant thereto conforms with the requirements of this Contract.

7.10 Cleaning the Site and the Project

The Contractor shall keep the site reasonably clean during performance of the Work. Upon final completion of the Work, the Contractor shall clean the site and the Project and remove all waste, rubbish, temporary structures, and other materials together with all of the Contractor's property therefrom. Contractor shall dispose of all refuse at a Texas Natural Resource Conservation Commission approved landfill. The Contractor shall further restore all property damaged during the prosecution of the Work and shall leave the site in a clean and presentable condition. No additional payment shall be made by the Owner for this work, the compensation having been considered and included in the contract price.

7.11 Access to Work and Inspections

The Owner shall have access to the Work at all times from commencement of the Work through final completion. The Contractor shall take whatever steps necessary to provide access when requested. When reasonably requested by the Owner, the Contractor shall perform or cause to be performed such testing as may be necessary or appropriate to insure suitability of the jobsite or the Work’s compliance with the Contract requirements.

7.12 Indemnity and Disclaimer

A. OWNER SHALL NOT BE LIABLE OR RESPONSIBLE FOR, AND SHALL

BE INDEMNIFIED, DEFENDED, HELD HARMLESS AND RELEASED BY

CONTRACTOR FROM AND AGAINST ANY AND ALL SUITS, ACTIONS,

LOSSES, DAMAGES, CLAIMS, OR LIABILITY OF ANY CHARACTER,

TYPE, OR DESCRIPTION, INCLUDING ALL EXPENSES OF

LITIGATION, COURT COSTS, AND ATTORNEY'S FEES FOR INJURY

OR DEATH TO ANY PERSON, OR INJURY OR LOSS TO ANY

PROPERTY, RECEIVED OR SUSTAINED BY ANY PERSON OR

PERSONS, INCLUDING THE CONTRACTOR, OR PROPERTY, ARISING

OUT OF, OR OCCASIONED BY, DIRECTLY OR INDIRECTLY, THE

PERFORMANCE OF CONTRACTOR UNDER THIS AGREEMENT,

INCLUDING CLAIMS AND DAMAGES ARISING IN WHOLE OR IN

PART FROM THE NEGLIGENCE OF OWNER, WITHOUT, HOWEVER,

WAIVING ANY GOVERN-MENTAL IMMUNITY AVAILABLE TO THE

OWNER UNDER TEXAS LAW AND WITHOUT WAIVING ANY

DEFENSES OF THE PARTIES UNDER TEXAS LAW. THE PROVISIONS

OF THIS INDEMNI-FICATION ARE SOLELY FOR THE BENEFIT OF

THE PARTIES HERETO AND NOT INTENDED TO CREATE OR GRANT

ANY RIGHTS, CONTRACTUAL OR OTHERWISE, TO ANY OTHER

PERSON OR ENTITY. IT IS THE EXPRESSED INTENT OF THE

PARTIES TO THIS AGREEMENT THAT THE INDEMNITY PROVIDED

FOR IN THIS CONTRACT IS AN INDEMNITY EXTENDED BY

CONTRACTOR TO INDEMNIFY AND PROTECT OWNER FROM THE

CONSEQUENCES OF THE CONTRACTOR’S AS WELL AS THE

OWNER'S NEGLIGENCE, WHETHER SUCH NEGLIGENCE IS THE

SOLE OR PARTIAL CAUSE OF ANY SUCH INJURY, DEATH, OR

DAMAGE.

B. The Contractor will secure and maintain Contractual Liability insurance to cover this indemnification agreement that will be primary and non-contributory as to any insurance maintained by the Owner for its own benefit, including self-insurance. In addition, Contractor shall obtain and file with Owner a Standard Certificate of Insurance evidencing the required coverage.

C. In claims against any person or entity indemnified under this Paragraph 7.12 by an employee of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligation under this Paragraph 7.12 shall not be limited by a limitation on amount or type of damages, compensation or benefits payable by or for the Contractor or a Subcontractor under workers' compensation acts, disability benefit acts or other employee benefit acts.

7.13 Nondiscrimination

The Contractor shall not discriminate in any way against any person, employee or job applicant on the basis of race, color, creed, national original, religion, age, sex, or disability where reasonable accommodations can be effected to enable the person to perform the essential functions of the job. The Contractor shall further insure that the foregoing nondiscrimination requirement shall be made a part and requirement of each subcontract on any Project.

7.14 Job Site Safety Precautions

The Contractor shall at all times exercise reasonable precautions for the safety of its employees, laborers, subcontractors, mechanics, workmen and others on and near the jobsite and shall comply with all laws, ordinances, regulations, and standards of federal, state and local safety laws and regulations. The Contractor shall provide such machinery guards, safe walk-ways, ladders, bridges, and other safety devices as may be necessary or appropriate to insure a safe and secure jobsite and shall require its subcontractors to comply with this requirement. The Contractor shall immediately comply with any and all safety requirements imposed by the Owner during the progress of any Work.

7.15 Warning Devices and Barricades

The Contractor shall furnish and maintain such warning devices, barricades, lights, signs, pavement markings, and other devices as may be necessary or appropriate or required by the Owner to protect persons or property in, near or adjacent to the jobsite, including . No separate compensation shall be paid to the Contractor for such measures. Where Work is being conducted in, upon or near streets, alleys, sidewalks, or other rights-of-way, the Contractor shall insure the placement, maintenance and operation of any and all such warning devices as may be required by the City of Waxahachie and shall do so until no longer required by the City. Such devices shall be in compliance with and conform to the manual and specifications for the uniform system of traffic control devices adopted by the Texas Department of Transportation.

7.16 Protection of Utilities and Other Contractors

A. The Contractor shall use best efforts to leave undisturbed and uninterrupted all utilities and utility services provided to the jobsite or which presently exists at, above or beneath the location where any Work is to be performed. In the event that any utility or utility service is disturbed or damaged during the progress of the Work, the Contractor shall forthwith repair, remedy or restore the utility at Contractor’s sole expense.

B. The Contractor understands and acknowledges that other contractors of the Owner or of other entities may be present at the jobsite performing other work unrelated to the Project.

The Contractor shall use best efforts to work around other contractors without impeding the work of others while still adhering to the completion date established herein. In the event that the Contractor’s work is or may be delayed by any other person, the Contractor shall immediately give notice thereof to the Owner and shall request a written Change Order in accordance with the procedures set forth by this Contract. The Contractor’s failure to provide such notice and to request such Change Order shall constitute a waiver of any and all claims associated therewith.

ARTICLE VIII

CONTRACT ADMINISTRATION

8.1 The Owner or Owner’s Designee

The Owner may administer this Contract itself or appoint a Designee to administer this Contract. The Owner’s Designee (“Designee”) may be an employee of the Owner or may be retained by the Owner as an independent contractor but, in either event, the Designee’s duties and authority shall be as set forth hereinafter. The Contractor understands and agrees that it shall abide by the decisions and instructions of the Owner’s Designee notwithstanding the contractual relationship between the Owner and Designee. All of the Owner’s instructions to the Contractor shall be through the Designee unless otherwise provided by Owner.

In the event the Owner should find it necessary or convenient to replace its Designee, the Owner shall retain a replacement Designee and the status of the replacement Designee shall be that of the former Designee.

8.2 Designee’s Administration

A. The Designee, unless otherwise directed by the Owner in writing, will perform those duties and discharge those responsibilities allocated to the Designee as set forth in this Contract.

The Designee shall be the Owner's representative from the effective date of this Contract until final payment has been made.

B. The Owner and the Contractor shall communicate with each other in the first instance through the Designee.

C. The Designee shall be the initial interpreter of the requirements of the drawings and specifications and the judge of the performance thereunder by the Contractor. The

Designee shall render written or graphic interpretations necessary for the proper execution or progress of the Work with reasonable promptness on request of the Contractor.

D. The Designee will review the Contractor's Applications for Payment and will certify to the Owner for payment to the Contractor, those amounts then due the Contractor as provided in this Contract.

E. The Designee shall have authority to reject Work which is defective or does not conform to the requirements of this Contract. If the Designee deems it necessary or advisable, the Designee shall have authority to require additional inspection or testing of the Work for compliance with Contract requirements.

F. The Designee will review and approve, or take other appropriate action as necessary, concerning the Contractor's submittals including Shop Drawings, Product Data and Samples. Such review, approval or other action shall be for the sole purpose of determining conformance with the design concept and information given through the Contract Documents.

G. The Designee will prepare Change Orders and may authorize minor changes in the Work by Field Order as provided elsewhere herein.

H. The Designee shall, upon written request from the Contractor, conduct inspections to determine the date of Substantial Completion and the date of final completion, will receive and forward to the Owner for the Owner's review and records, written warranties and related documents required by this Contract and will issue a final Certificate for Payment upon compliance with the requirements of this Contract.

I. The Designee’s decisions in matters relating to aesthetic effect shall be final if consistent with the intent of this Contract.

8.3 Claims by the Contractor

A. The Designee shall determine all claims and matters in dispute between the Contractor and Owner with regard to the execution, progress, or sufficiency of the Work or the interpretation of the Contract Documents, including but not limited to the plans and specifications. Any dispute shall be submitted in writing to the Designee within seven (7) days of the event or occurrence or the first appearance of the condition giving rise to the claim or dispute who shall render a written decision within a reasonable time thereafter.

The Designee’s decisions shall be final and binding on the parties. In the event that either party objects to the Designee’s determination as to any submitted dispute, that party shall submit a written objection to the Designee and the opposing party within ten (10) days of receipt of the Designee’s written determination in order to preserve the objection. Failure to so object shall constitute a waiver of the objection for all purposes.

B. Pending final resolution of any claim of the Contractor, the Contractor shall diligently proceed with performance of this Contract and the Owner shall continue to make payments to the Contractor in accordance with this Contract.

C. Claims for Concealed, Latent or Unknown Conditions. The Contractor expressly represents that it has been provided with an adequate opportunity to inspect all Project sites and thoroughly review the Contract Documents and plans and specifications prior to submission of its bid and the Owner’s acceptance of the bid. Subject to the conditions hereof, Contractor assumes full responsibility and risk for any concealed, latent or unknown condition which may affect the Work. No claims for extra work or additional compensation shall be made by Contractor in connection with concealed, latent or unknown conditions except as expressly provided herein. Should concealed, latent or unknown conditions encountered in the performance of any Work (a) below the surface of the ground or (b) in an existing structure be at variance with the conditions indicated by this Contract, or should unknown conditions of an unusual nature differing materially from those ordinarily encountered in the area and generally recognized as inherent in Work of the character provided for in this Contract, be encountered, the Contract Price shall be equitably adjusted by Change Order upon the written notice and claim by either party made within seven (7) days after the first observance of the condition. As a condition precedent to the Owner having any liability to the Contractor for concealed or unknown conditions, the Contractor must give the Owner and the Designee written notice of and an opportunity to observe, the condition prior to disturbing it. The failure by the Contractor to make the written notice and claim as provided in this Subparagraph shall constitute a waiver by the Contractor of any claim arising out of or relating to such concealed, latent or unknown condition and the Contractor thereby assumes all risks and additional costs associated therewith.

D. Claims for Additional Costs. If the Contractor wishes to make a claim for an increase in the Contract Price, as a condition precedent to any liability of the Owner therefore, the Contractor shall give the Designee written notice of such claim within seven (7) days after the occurrence of the event, or the first appearance of the condition, giving rise to such claim. Such notice shall be given by the Contractor before proceeding to execute any additional or changed Work. The failure by the Contractor to give such notice and to give such notice prior to executing any Work shall constitute a waiver of any claim for additional compensation.

E. In connection with any claim by the Contractor against the Owner for compensation in excess of the Contract Price, any liability of the Owner for the Contractor's costs shall be strictly limited to direct costs incurred by the Contractor and shall in no event include indirect costs or consequential damages of the Contractor. The Owner shall not be liable to the Contractor for claims of third parties, including Subcontractors. The Owner shall not be liable to the Contractor for any claims based upon delay to the Contractor for any reason whatsoever including any act or neglect on the part of the Owner.

F. Claims for Additional Time. If the Contractor is delayed in progressing any task which at the time of the delay is then critical or which during the delay becomes critical, as the sole result of any act or neglect to act by the Owner or someone acting in the Owner's behalf, or by changes ordered in any Work, unusual delay in transportation, unusually adverse weather conditions not reasonably anticipated, fire or any causes beyond the Contractor's control, then the date for achieving Substantial Completion of the Work shall be extended upon the written notice and claim of the Contractor to the Owner and the Designee, for such reasonable time as the Designee may determine. Any notice and claim for an extension of time by the Contractor shall be made not more than seven (7) days after the occurrence of the event or the first appearance of the condition giving rise to the claim and shall set forth in detail the Contractor's basis for requiring additional time in which to complete the Project. In the event the delay to the Contractor is a continuing one, only one notice and claim for additional time shall be necessary. If the Contractor fails to make such claim as required in this Subparagraph, any claim for an extension of time shall be waived.

The procedures and remedies provided by this provision shall be the sole remedy of Contractor and Contractor shall not assert nor be entitled to any additional delays or damages associated therewith.

8.4 Field Orders

The Designee shall have authority to order minor changes in any Work not involving a change in the Contract Price or in Contract Time and not inconsistent with the intent of the Contract. Such changes shall be effected by Field Order and shall be binding upon the Contractor.

The Contractor shall carry out such Field Orders promptly.

8.5 Mediation

A. In the event that a dispute arises under the terms of this Contract, following an adverse determination by the Designee and proper preservation of the issue as required herein, the parties agree to submit to mediation. In such event, the parties shall agree to a designated person to serve as mediator and each party shall be responsible for payment of one-half of the total mediation fees. The parties shall submit the dispute to mediation as soon as practical and in no event later than one (1) year after the Designee’s written decision on the matter.