This is a construction cost estimate from EMCOR Services Automated Controls submitted to the Cincinnati/Northern Kentucky International Airport (CVG) for the HVAC Controls and Infrastructure Upgrades project managed by the Kenton County Airport Board. The scope encompasses the provision and installation of control panels with associated power supplies, G5CE controllers, power and communication cabling, and comprehensive system integration services across three facility locations: the Terminal (18 control panels and 18 controllers), Concourse A (13 control panels and 13 controllers), and Concourse B (16 control panels and 16 controllers). The estimate is dated October 7, 2025, and includes programming, graphics generation, drawing and bill of materials updates, technical checkout, commissioning, air-balance support, as-built drawings, operation and maintenance manuals, and one-year warranty. The estimate is based on work performed during standard business hours, Monday through Friday, excluding holidays, with a quotation deadline of 30 days from the proposal date and invoices rendered net fifteen days on a progress basis.
The total construction cost estimate from EMCOR is $542,265.00, comprising Terminal panels at $207,665.00, Concourse A panels at $150,000.00, and Concourse B panels at $184,600.00. The estimate explicitly excludes air balance costs, allowance costs, bonding, variable frequency drives, valve installation, smoke detectors, fire alarm scope, and taxes. General conditions specify that late payment charges of 1% per month (18% annual percentage rate) apply to unpaid balances after 30 days. This estimate serves as the referenced construction cost component within the broader project appropriation of $1,855,000.00, which includes design costs of $150,000.00, construction/installation budgeted at $1,500,000.00, contingency of $150,000.00, construction administration and inspection of $54,000.00, and force labor of $1,000.00, with all work funded through local capital budget sources subject to FAA Title VI civil rights requirements.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEXINGTON
1165 Brock McVey Dr.
Lexington, KY 40509
P: 859.266.5300
CINCINNATI HQ
3976 Southern Ave
Cincinnati, OH 45227
P: 513.527.8040
COLUMBUS
1762 Dividend Dr.
Columbus, OH 43228
P: 614.529.7500
INDIANAPOLIS
3940 Pendleton Way
Indianapolis, IN 46226
P: 317.402.8039
EVANSVILLE
1321 Virginia St.
Evansville, IN 47711
P: 812.475.8665
LOUISVILLE
1833 Taylor Ave.
Louisville, KY 40213
P: 502.368.0454
MEMPHIS
485 E. South St.
Collierville, TN 38017
P: 502.368.0454
October 7, 2025
Todd Beuke
Master Industrial Maintenance Technician
Cincinnati/Northern Kentucky Airport tbeuke@cvgairport.com
RE: MW25-0220 – Master Network Layout Panel Installation
EMCOR is pleased to provide pricing for the equipment and labor as outlined below. This proposal is formatted to be as detailed and complete as possible so that the scope of work is clear and unambiguous. If there are any questions regarding this proposal, please do not hesitate to call.
Scope of Work:
Provide and install control panels for the Terminal:
o Eighteen (18) control panel and associated power supplies o Eighteen (18) G5CE, or equivalent, controller o Power and communication cabling o IP address defined by CVG IT
Provide and install control panels for Concourse A:
o Thirteen (13) control panel and associated power supplies o Thirteen (13) G5CE, or equivalent, controller o Power and communication cabling o IP address defined by CVG IT
Provide and install controls panels for Concourse B:
o Sixteen (16) control panel and associated power supplies o Sixteen(16) G5CE, or equivalent, controller o Power and communication cabling o IP address defined by CVG IT
Programming
Graphics
Drawing/BOM update
Checkout
Alarming
Control system devices/communication bus
Scheduling setup
Trending setup
Alarming setup
Technical checkout
Commissioning
Air-balance support
As-built drawings
O&M manuals
One-year warranty
General Notes & Exceptions:
o No air balance cost included o No allowance cost included o No bond cost included o No VFDs are included o No valve installation is included o No smoke detectors included o No fire alarm scope included o No taxes are included
Quotation:
Total for Terminal panels ...................................................................................... $207,665.00
Total for Concourse A panels ................................................................................ $150,000.00
Total for Concourse B panels ................................................................................. $184,600.00
Total for all .......................................................................................................... $542,265.00
General Conditions:
This proposal is based on all work being performed during normal working hours, Monday through Friday, excluding holidays.
Invoices are net fifteen days and rendered as labor and material progress on the job.
A late payment charge of 1½% per month (annual percentage rate of 18%) shall be added to the unpaid past due balance after 30 days.
This quotation is subject to revision if not accepted within 30 days.
To signify your acceptance, please sign below and return a copy of this proposal with your purchase order.
If you have any questions regarding this proposal, please contact me at (513) 484-4544.
Sincerely, EMCOR Services Automated Controls
Zachary Brown, CEM
Midwest Operations Manager, Controls