This is a construction cost estimate from EMCOR Services Automated Controls submitted to the Cincinnati/Northern Kentucky International Airport (CVG) for the HVAC Controls and Infrastructure Upgrades project managed by the Kenton County Airport Board. The scope encompasses the provision and installation of control panels with associated power supplies, G5CE controllers, power and communication cabling, and comprehensive system integration services across three facility locations: the Terminal (18 control panels and 18 controllers), Concourse A (13 control panels and 13 controllers), and Concourse B (16 control panels and 16 controllers). The estimate is dated October 7, 2025, and includes programming, graphics generation, drawing and bill of materials updates, technical checkout, commissioning, air-balance support, as-built drawings, operation and maintenance manuals, and one-year warranty. The estimate is based on work performed during standard business hours, Monday through Friday, excluding holidays, with a quotation deadline of 30 days from the proposal date and invoices rendered net fifteen days on a progress basis.

The total construction cost estimate from EMCOR is $542,265.00, comprising Terminal panels at $207,665.00, Concourse A panels at $150,000.00, and Concourse B panels at $184,600.00. The estimate explicitly excludes air balance costs, allowance costs, bonding, variable frequency drives, valve installation, smoke detectors, fire alarm scope, and taxes. General conditions specify that late payment charges of 1% per month (18% annual percentage rate) apply to unpaid balances after 30 days. This estimate serves as the referenced construction cost component within the broader project appropriation of $1,855,000.00, which includes design costs of $150,000.00, construction/installation budgeted at $1,500,000.00, contingency of $150,000.00, construction administration and inspection of $54,000.00, and force labor of $1,000.00, with all work funded through local capital budget sources subject to FAA Title VI civil rights requirements.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LEXINGTON

1165 Brock McVey Dr.

Lexington, KY 40509

P: 859.266.5300

CINCINNATI HQ

3976 Southern Ave

Cincinnati, OH 45227

P: 513.527.8040

COLUMBUS

1762 Dividend Dr.

Columbus, OH 43228

P: 614.529.7500

INDIANAPOLIS

3940 Pendleton Way

Indianapolis, IN 46226

P: 317.402.8039

EVANSVILLE

1321 Virginia St.

Evansville, IN 47711

P: 812.475.8665

LOUISVILLE

1833 Taylor Ave.

Louisville, KY 40213

P: 502.368.0454

MEMPHIS

485 E. South St.

Collierville, TN 38017

P: 502.368.0454

October 7, 2025

Todd Beuke

Master Industrial Maintenance Technician

Cincinnati/Northern Kentucky Airport tbeuke@cvgairport.com

RE: MW25-0220 – Master Network Layout Panel Installation

EMCOR is pleased to provide pricing for the equipment and labor as outlined below. This proposal is formatted to be as detailed and complete as possible so that the scope of work is clear and unambiguous. If there are any questions regarding this proposal, please do not hesitate to call.

Scope of Work:

Provide and install control panels for the Terminal:

o Eighteen (18) control panel and associated power supplies o Eighteen (18) G5CE, or equivalent, controller o Power and communication cabling o IP address defined by CVG IT

Provide and install control panels for Concourse A:

o Thirteen (13) control panel and associated power supplies o Thirteen (13) G5CE, or equivalent, controller o Power and communication cabling o IP address defined by CVG IT

Provide and install controls panels for Concourse B:

o Sixteen (16) control panel and associated power supplies o Sixteen(16) G5CE, or equivalent, controller o Power and communication cabling o IP address defined by CVG IT

Programming

Graphics

Drawing/BOM update

Checkout

Alarming

Control system devices/communication bus

Scheduling setup

Trending setup

Alarming setup

Technical checkout

Commissioning

Air-balance support

As-built drawings

O&M manuals

One-year warranty

General Notes & Exceptions:

o No air balance cost included o No allowance cost included o No bond cost included o No VFDs are included o No valve installation is included o No smoke detectors included o No fire alarm scope included o No taxes are included

Quotation:

Total for Terminal panels ...................................................................................... $207,665.00

Total for Concourse A panels ................................................................................ $150,000.00

Total for Concourse B panels ................................................................................. $184,600.00

Total for all .......................................................................................................... $542,265.00

General Conditions:

This proposal is based on all work being performed during normal working hours, Monday through Friday, excluding holidays.

Invoices are net fifteen days and rendered as labor and material progress on the job.

A late payment charge of 1½% per month (annual percentage rate of 18%) shall be added to the unpaid past due balance after 30 days.

This quotation is subject to revision if not accepted within 30 days.

To signify your acceptance, please sign below and return a copy of this proposal with your purchase order.

If you have any questions regarding this proposal, please contact me at (513) 484-4544.

Sincerely, EMCOR Services Automated Controls

Zachary Brown, CEM

Midwest Operations Manager, Controls