Construction Add 3 472_22350.pdf

PDF 1 MB Posted

Attached to
472/22350. MNB; GHCF - BLDG 200 Boiler Replacement
Solicitation number
RFQ - 171 - 240000000186
Issued by
Lenawee County, Michigan

About this file

This document is a Construction Bid Addendum from the Michigan Department of Technology, Management and Budget (DTMB) for the Gus Harrison Correctional Facility Building 200 Boiler and Building 300 HVAC Replacement project, identified as File Number 472_22350.MNB. The project scope focuses on replacing boilers, HVAC equipment, and associated building and controls systems for the two buildings. A mandatory pre-bid walkthrough was held on January 30, 2024, where the project details and contractor expectations were discussed. Bids are due on March 6, 2024, and the contract duration is 455 calendar days for substantial completion and 485 calendar days for final completion. The project includes a base bid for Building 200 and an alternate bid for Building 300, which may or may not be accepted. Bidders are required to provide a unit price for temporary heat, which may be issued as a change order if approved by the State. The three most qualified bidders will be interviewed after bid submission.

The bid pricing includes an allowance of $150,000 for the Building 200 base bid. Bidders must acknowledge all addenda issued. The contract will require performance and payment bonds, and bidders must provide a 5% bid guarantee. The State reserves the right to reject any unit prices that are not in its best interest. The successful contractor will be required to provide daily reports with photos during construction, and work hours will be 7:00 am to 3:30 pm, five days per week.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 10/22)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND

BUDGET

State Facilities Administration Design and Construction Division

CONSTRUCTION BID ADDENDUM NO. 3

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

2/1/2024

PROJECT NAME

Gus Harrison Bldg. 200 Boiler and Bldg. 300 HVAC Replacement

FILE NUMBER

472_22350.MNB

PROFESSIONAL

JoAn Kutylowski Mende

PROJECT DIRECTOR

Chris Bahjet

BID OPENING DATE:

3/6/2024

ADDENDUM ITEMS

Please see attached Addendum 3 details.

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL: DATE: Click to enter date

APPROVED BY:

PROJECT DIRECTOR: Chris Bahjet DATE: 2/1/2024

02/01/2024

MENDE ENGINEERING SOLUTIONS, LLC

1-30-23: Pre-Bid – Gus Harrison HVAC/Boiler Replacement – 472-22350.MNB

PH: (517) 437-6998

www.MendeEngineeringSolutions.com

7430 Marsack Dr Swartz Creek, MI 48473

Addendum 3 Gus Harrison Correctional Facility: HVAC and Boiler Replacement – 472-22350.MNB

On January 30, 2024, 10:00am, a pre-bid walkthrough for the Gus Harrison Correctional Facility, Building 200 Boiler Replacement and Building 300 HVAC Replacement project was completed. The walkthrough was mandatory for all those submitting a bid as a prime contractor. The information below includes discussion recorded during the walkthrough.

1. Pre-Bid/Bidding Discussion:

a. At the beginning of bre-bid meeting, a sign-in sheet was passed around the room. The name and contact information of all individuals present is included Refer to Meeting Attendance Record included in this addendum.

b. The Owner’s Team was introduced:

i. Chris Bahjet, PE is the DTMB Project Director.

ii. Chris Severson is the MDOC Project Manager

iii. Tyler Slamka is the Director of Facilities at Gus Harrison Correctional Facility

iv. Lowell Grimes, HVAC Maintenance, Gus Harrison Correction Facility

v. Elizabeth Seppo is Project Engineer, Mende Engineering Solutions (MES)

vi. JoAn Mende, P.E., is the Principal Project Engineer (MES) for the project. Any questions regarding the bid proposal should be directed to joank@mendeengineeringsolutions.com. Responses to bid questions will not be issued via email. Responses will be issued as addenda, on the SIGMA website.

c. The deadline to submit project questions is 12:00 noon, February 13th. Any questions submitted after this date/time will not receive responses.

d. Project bids are to be submitted as one project which includes the amount for the base bid Building 200 scope and Building 300 add alternate scope. Refer to revised Bid Summary included in this addendum.

e. A unit price for temporary heat shall be included as part of the bid proposal. This will be listed as a line item separate from the project bid provided, and, if approved by the State of Michigan, will be issued to the contractor as a change order. Refer to revised Bid Summary included in this addendum.

f. Construction schedule included in bid documents lists construction schedule as lasting 455 calendar days. This schedule assumes that Alternate 1 is accepted as part of the project.

Refer to Section 00500 Article 4.

g. We (DTMB) are giving enough time to prepare the bid for you to contact manufacturers and learn of lead times. Ask questions if there are extended lead times. Then, there is another chance of learning of lead times. At the time of submitting shop drawings, if there are delays noted by manufacturers, let us know. We are trying to avoid to reach half the project and learn there are equipment delays. learn there are equipment delays.

h. Should there be any informational discrepancies between verbal conversations during the walk-thru (that is not issued as an addenda), and the construction documents, the construction documents prevail.

i. Following the receipt of bid proposals, the three most qualified bidders will be interviewed.

2. Project Scope Overview:

a. Building 200 construction scope focuses primarily on heating (replacement of boilers and supporting heating hot water equipment), as well as the replacement of AHU coils

MENDE ENGINEERING SOLUTIONS, LLC

517-437-6998

1-30-23: Pre-Bid – Gus Harrison HVAC/Boiler Replacement – 472.22350.MNB

b. Building 300 construction scope focuses primarily on cooling (replacement of rooftop condensing unit and associated refrigerant piping), as well as the replacement of AHU coils

c. Both buildings involve removal of existing pneumatics, and the installation of new DDC controls. The temperature controls integrator is to provide the temperature control valves, and the mechanical is to install.

i. Automated Logic is the controls contractor & will be responsible to submit bid fee to prime contractors bidding the project.

3. Contractor Expectations:

a. During construction, the Prime Contractor awarded the project is expected to create and send daily reports as updates to the project team.

i. Photos are required as part of the daily report; however, there is limited camera access for visitors/contractors onsite. Depending upon camera availability/permissions, the requirement to include photos as part of the daily update may be removed. Daily reports can be gathered and submitted weekly.

b. Working hours will be 7-3:30 (bid to be submitted under the assumptions that trades will work five 8-hour days)

c. Use of tobacco products onsite the facility is not permitted.

4. Walkthrough Locations included the following:

a. Building 200 Mechanical Room; review of boilers, pumps, air handling units

b. Discussion of location of temperature control valves throughout first floor area

c. Building 300 Mechanical Room; review of air handling units

d. Location of rooftop condenser (no interest in visiting roof to observe unit was expressed by attendees)

e. Location of VAV boxes throughout first floor. Review of media center with 1x1 spline ceiling

f. Noted by SOM staff that all other ceilings are acoustical ceiling tiles (drop ceiling).

g. Pictures of the walk-thru areas were taken. Refer to attached pictures in this addendum.

5. Prior to the walkthrough conclusion, group was asked if anyone had interest in returning to the site for a secondary walkthrough. No interest was expressed.

6. Post walk thru revision: Added Paragraph 3.2 Pre-Demolition and Paragraph 3.2 New Work to SECTION 23 05 93. Refer to attached specification section in this addendum.

STATE OF MICHIGAN (OWNER AND CONTRACTOR) BID SUMMARY

MICHSPEC§ DTMB 00120 - 2 (Rev. 02/2018)

SECTION 00300 BID SUMMARY

DTMB-0401M (R 03/21)

BID SUMMARY

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

DESIGN AND CONSTRUCTION DIVISION

3111 W. St. Joseph Street Lansing, Michigan 48917

Bids must be submitted electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService

FILE NUMBER

472-22350.MNB

FUNDING CODE

171CODOC7325 &

ARFMaintProj

DEPARTMENT/AGENCY

472 MICHIGAN DEPARTMENT OF CORRECTIONS

CONTRACT TIME(S)

Contract duration: 455 Calendar Days Substantial Completion;

485 Calendar Days Final Completion

PROJECT NAME

GUS HARRISON CORRECTIONAL FACILITY –

B200 BOILER REPLACEMENT AND

B300 HVAC REPLACEMENT

LOCATION

ADRIAN MICHIGAN

BID OPENING DATE

MARCH 6, 2024 at 2:00 pm ET

FOR AN EXAMINATION OF THE SITE CONTACT:

JoanK@MendeEngineeringSolutions.com

SEE SECTION 00100 INSTRUCTIONS TO BIDDERS AND SECTION 00700 GENERAL CONDITIONS PROVIDED WITH THE BIDDING DOCUMENTS.

BID: WE PROPOSE TO FURNISH, PERFORM AND COMPLETE THE ENTIRE WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS IN

CONSIDERATION OF THE BID PRICE (S) STATED BELOW.

FIRM NAME AND COMPLETE ADDRESS TELEPHONE NUMBER and E-MAIL ADDRESS

! Qualified Disabled Veteran

SIGMA VENDOR NUMBER

(protected information required for processing payments)

BIDDER'S SIGNATURE AND TITLE DATE WITNESS' SIGNATURE DATE

By signing this bid above, bidder certifies their enclosed Qualified Disabled Veteran and Michigan-Based Business Certifications.

BASE BID FROM BID SCHEDULE :

____________________________________________________________________________Dollars $____________________ (use words) (in figures)

Alternate1: (Add) FROM BID SCHEDULE:

___________________________________________________________________________ Dollars $ ____________________ (use words) (in figures)

TOTAL AMOUNT (BASE BID FROM BID SCHEDULE + ADD ALT 1 FROM SCHEDULE) :

____________________________________________________________________________Dollars $____________________ (use words) (in figures)

A PERFORMANCE BOND AND A PAYMENT BOND ARE REQUIRED FOR ALL BIDS OVER $50,000.00. EACH BID MUST BE ACCOMPANIED BY A FIVE (5) PERCENT BID GUARANTEE. BUILDERS RISK INSURANCE IS REQUIRED TO BE PROVIDED BY THE CONTRACTOR UNLESS

OTHERWISE INDICATED IN THE BID DOCUMENTS.

MICHSPEC§ DTMB 00300 ! BID SUMMARY (R 03/22)

BIDDERS ARE ALSO CAUTIONED TO FAMILIARIZE THEMSELVES WITH ALL OF THE OTHER CONDITIONS OF THE CONTRACT.

Project Scope of Work:: REFER TO SECTION 011000 SUMMARY OF WORK AND PROJECT DRAWINGS FOR COMPLETE SCOPE.

INFORMATION IN THE SPECIFICATIONS AND DRAWINGS ARE COMPLIMENTARY. PROJECT INCLUDES DEMOLITION OF BOILERS, AIR COOLED CONDENSERS, PUMPS, AHU COILS, PNEUMATIC CONTROLS AND ASSOCIATED ELECTRICAL SERVICE, AND REPLACEMENT OF BOILERS, AIR COOLED CONDENSERS, PUMPS, AHU COILS, DIRECT DIGITAL CONTROLS

AND ASSOCIATED ELECTRICAL SERVICE.

The Bidder must figure its Base Bid on the specified, or Addendum-approved, materials and equipment only. No “or equal” or substitution proposals will be permitted after Bid opening, except as provided in the General Conditions.

Addenda: Bidder acknowledges receipt of Addenda: No. ___ dated: ________, No. ___ dated: ________ No. ___ dated: ________

SECTION 00300 BID FORM

PROFESSIONAL ! MENDE ENGINEERING SOLUTIONS, LLC

WORK ! GUS HARRISON CORRECTIONAL FACILITY - B200 BOILER REPLACEMENT & B300 HVAC REPLACEMENT

AGENCY No. ! 472 MICHIGAN DEPARTMENT OF CORRECTIONS

FILE No. ! 472-22350.MNB

TABLE OF CONTENTS

PAGE

BID SUMMARY i

1 THIS BID IS SUBMITTED TO 1

2 THE BIDDER'S REPRESENTATIONS 1

3 TIME OF COMPLETION 2

4 ATTACHMENTS INCLUDED WITH THIS BID 2

5 DEFINED TERMS 2

6 BID SCHEDULE 3

7 SCHEDULE OF CHANGE ORDER PRICES __

8 BID SUBMITTED __

ARTICLE 1 THIS BID IS SUBMITTED TO THE STATE OF

MICHIGAN ("the Owner").

1.1. The undersigned Bidder proposes and agrees, if this Bid

is accepted, to enter into an agreement with the Owner on the form in Section 00500 Agreement and to furnish and perform the Work as specified or indicated in the Bidding Documents for the Bid prices in the "Bid Schedule" on this Section 00300 Bid Form, within the Contract Times specified in Section 00500 Agreement, and in accordance with all other provisions and terms and conditions of the Bidding Documents, including, without limitation, those dealing with the disposition of the Bid Security.

1.2. The undersigned Bidder agrees to hold this Bid open for

acceptance by the Owner for the period OF SIXTY (60) DAYS.

STATE OF MICHIGAN MODEL

Developed from FORMSPEC§ Michigan Model

1.3. The Bidder will provide a signed original of Section

00500 Agreement, the executed Section 00610 Performance Bond, the executed Section 00620 Payment Bond, and appropriate evidence of insurance within the times and in the manner specified in the Bidding Documents.

ARTICLE 2 THE BIDDER'S REPRESENTATIONS

2.1. The Bidder has examined the Bidding Documents, including the Addenda acknowledged in the table below. The Bidder has verified that the Addenda acknowledged below include all issued Addenda. Except for Addenda, which solely revise the date of Bid, opening, failure by the Bidder to acknowledge receipt of all Addenda correctly, by either failing to complete or incorrectly completing the table below, shall justify the Owner's refusal to read the Bid and automatically disqualify the Bidder from any consideration for award of the Contract.

No. ___ Dated _____________ No. ___ Dated __________

No. ___ Dated _____________ No. ___ Dated __________

No. ___ Dated _____________ No. ___ Dated __________

2.2. The Bidder has taken those steps that are reasonably

necessary to (a) ascertain and become familiar with the Work, site, and locality; (b) account for all applicable federal, state, and other local Laws and all general, local, and prevailing conditions that may in any manner affect cost, schedule, progress, performance or furnishing of the Work; and (c) study and account for the terms and

MICHSPEC§ DTMB 00300 ! 2 (R 03/22)

conditions of the Bidding Documents. The Bidder has carefully correlated the Bidder's observations with the Bidding Documents.

2.3. The Bidder has studied carefully all reports concerning

subsurface conditions and drawings of physical conditions of existing surface and subsurface facilities that have been used by the Professional and all documents of physical conditions of existing Underground Utilities facilities that have been used by the Professional ! in both cases as identified in Section 00210 Information for bidders. The Bidder assumes responsibility for carefully and accurately locating existing Underground Utilities in a manner consistent with paragraph 10.3 of Section 00700 General Conditions and as required by 1974 PA 53, as amended, MCL

460.701 et seq. The Bidder accepts the determinations set forth in the Bidding Documents as to the extent of such Authorized Technical Data and Underground Utilities information and data contained in those reports, drawings, documents, or the Bidding Documents, as applicable, upon which the Bidder may rely.

2.4. To the extent Additional Technical Data has been

considered by the Bidder as necessary for determining the Bid in Article 6 Bid Schedule, and the Owner, upon request, did not have the necessary Additional Technical Data, the Bidder assumes responsibility for having undertaken or undertaking reasonable examinations of the site and any other pertinent available information and data. The Bidder agrees to perform and furnish the Work affected by the conditions involved, at no increase in Contract Price and Contract Time, to the extent the information and data necessary for determining the Bid could have been discovered through reasonable examinations of the site and any other pertinent information and data available (including, but not limited to the information and data designated in Section 00210 Information for Bidders).

2.5. The Bidder has carefully correlated the results of its

observations, examinations, and studies of those reports of explorations and all that information and data in studies, drawings, and specifications, referred to in paragraphs 2.3 and 2.4, with the terms and conditions of the Bidding Documents.

2.6. The Bidder has examined all information and data shown

or indicated in the Bidding Documents concerning other work, including, but not limited to provisions in Section 00700 General Conditions. The Bidder assumes responsibility for all reasonably foreseeable terms, conditions and consequences resulting from other work that may in any manner affect cost, schedule, progress, performance or furnishing of the Work.

2.7. The Bidder has carefully examined the terms and

conditions of the Bidding Documents concerning Delay, Activity Float times and early completion. The Bidder agrees that increases in Contract Price and/or Contract Time for Delay shall be as provided in Section 00700 General Conditions. The Bidder has correlated those terms and conditions with the Bidder's schedule for the Work and its Base Bid and Alternates.

2.8. The Bidder represents that each unit price covering

Specified or Contingent Unit Price Work, whether bid on Article 6 !

Bid Schedule or on Article 7 ! Schedule of Change Order Prices, includes sufficient amounts to cover (a) all labor costs, Subcontractor costs, material and equipment costs, construction equipment costs and general conditions costs, and (b) all administrative costs and home office overhead), and (c) profit. The Owner reserves the right to reject any unit prices bid on paragraph 6.2 Schedule of Alternates or in Article 7 Schedule of Change Order Prices, which, in the Owner’s sole discretion, are not in the Owner’s best interest.

2.9. The Bidder has given the Professional written notice of

all conflicts, ambiguities, errors, or omissions the Bidder has discovered in the Bidding Documents, and the written resolution given by the Professional is acceptable to the Bidder.

2.10. This Bid is genuine, is not made in the interest of or on behalf of any undisclosed person and is not submitted in conformity with any agreement or rules of any group, association, organization, or corporation. To induce the Owner into consideration of this Bid, the Bidder reiterates and makes each of the representations made by the Bidder in Section 00320 Non-collusion Affidavit attached to this Section 00300 Bid Form.

2.11. The Bidder is aware of the Owner's requirements for

business owned by minorities, women, and persons with physical or mental disabilities, and assumes responsibility for all conditions and consequences that may result from meeting those requirements and that may in any manner affect cost, schedule, progress, performance and furnishing of the Work.

2.12. The Bidder has read and studied each provision of the

Bidding Documents. The Bidder has no expectations different from the terms and conditions of the Bidding Documents.

ARTICLE 3 TIME OF COMPLETION

3.1. The Contract Times are specified in paragraph 4.1 of

Section 00500 Agreement. The Bidder has carefully correlated the provisions in paragraph 4.1 of Section 00500 Agreement with the other terms and conditions of the Bidding Documents and unequivocally accepts the Contract Times for the Work, and any other designated parts of the Work, as specified.

3.2. The Bidder unequivocally accepts the liquidated damage

provisions specified in paragraph 4.2 of Section 00500 Agreement in the event of any failure, neglect, or refusal to complete the Work, or designated part of the Work, within the corresponding Contract Times specified in paragraph 4.1 of Section 00500 Agreement.

ARTICLE 4 ATTACHMENTS INCLUDED WITH THIS BID

4.1. Attachments to this Section 00300 Bid Form and made a

condition of this Bid are:

4.1.1. Evidence of Authority to Sign the Bid.

4.1.2. Section 00310 Bid Bond, with the attached certified

copy of Power of Attorney, or

Alternate Bid Security.

4.1.3. Section 00320 Non-collusion Affidavit.

TO BE PROVIDED POST BID WITH SECTION 00400

SUBMITTALS:

4.1.5 Current EMR Rating

MICHSPEC§ DTMB 00300 ! 2 (R 03/22)

4.1.6 Identification of the proposed project superintendent

with a resume or list of similar projects handled by that individual.

4.1.7 A list of at least three (3) projects completed within

the last three (3) years of similar size and complexity, with contact information for references for each.

4.2. Bidder-provided documents, made a condition of this Bid, are as required in the following Section(s) of the Bidding Documents:

ARTICLE 5 DEFINED TERMS

5.1. Section 00020 Glossary assigns specific intent and

meanings to capitalized terms and to other defined terms used in (a) this Section 00300 Bid Form, (b) Section 00310 Bid Bond and Section 00320 Non-collusion Affidavit), and (c) Section 00410 Bid Breakdown, Section 00420 Questionnaire, Section 00430 List of Subcontractors and Section 00440 Schedule of Materials and Equipment.

MICHSPEC§ DTMB 00300 ! 3 (R 03/22)

ARTICLE 6 BID SCHEDULE

6.1 Base Bid Schedule - The Bidder will complete the Work and accept in full payment, for the Work items listed, the following unit prices and/or Bid Prices, as applicable:

Base Bid Item No.

Bid Quantity

Description Unit Price

Item Bid Price

1 Building 200 Boiler Replacement, associated heating and cooling systems, electrical, building trades and temperature controls as described in Section 011000 Summary of Work and

Drawings

NOT APPLICABLE

ALLOWANCE AMOUNT: $150,000.00

TOTAL (This amount should equal the Base Bid amount on the Bid Summary Form) $

Base Bid (Sum of Bid Prices for all Base Bid Items):

________________________________________________________________ Dollars and No/Cents $__________________________ (use words) (in figures)

Name of the Bidder _________________________________________ Agency No. ________

Funding Code: 171CODOC7325 & ARFMaintProj File No. 472-22350.MNB

Date _________________________

SIGMA VENDOR NUMBER _________________________________

Telephone No. _______________________

MICHSPEC§ DTMB 00300 ! 4 (R 03/22)

6.2 Schedule of Alternates - The Bidder will complete the parts of the Work designated by the Alternates that follow and accept in full payment for those parts of the Work the following Bid Prices:

Alternate Item No.

Bid Quantity

Description Unit Price

Item Bid Price

1 Building 300 HVAC Replacement, associated heating and cooling systems, electrical, building trades and temperature controls as described in Section 011000 Summary of Work and

Drawings

NOT APPLICABLE

TOTAL (This amount should equal the Alternate 1 amount on the Bid Summary Form) $

Alternate 1 Bid (Sum of Prices for all Alternate Bid Items):

________________________________________________________________ Dollars and No/Cents $__________________________ (use words) (in figures)

The Bidder further acknowledges and agrees that the separate prices bid on this “Schedule of Alternates,” where they are applicable and deemed acceptable by the Owner, will be used if incorporated into the Contract when the Owner issues the Notice of Award.

Name of the Bidder _________________________________________ Agency No. ________

Funding Code: 171CODOC7325 & ARFMaintProj

File No. 472-22350.MNB

Date _________________________

MICHSPEC§ DTMB 00300 ! 5 (R 03/22)

ARTICLE 7 SCHEDULE OF CHANGE ORDER PRICES

7.1 The Bidder shall use this “Schedule of Change Order Prices” to propose contingent prices. The proposed contingent Change Order prices set forth in this schedule, at the sole discretion of the Owner, may, or may not be incorporated into the Contract Documents. The Owner reserves the right to negotiate contingent Change Order prices set forth herein prior to their possible incorporation into the Contract Documents.

Proposed Change Order prices will not affect determination of the lowest Bid.

7.2 Subject to their incorporation into the Contract Documents, as provided in the Agreement, the Bidder will add to, or deduct from, the Contract Work covered by the contingent prices that follow and accept in full payment, or allow in full credit, for that Work (a) those prices bid by the Bidder, or (b) if a particular price is not bid, the price proposed by the Owner (and shown in the appropriate column):

Item No. Bid Quantity

Description Unit Price

Item Bid Price

1 Temporary Heat Building 200 Cost per day

2 Temporary Heat Building 300 Cost per day

Name of the Bidder _________________________________________ Agency No. ________

Funding Code: 171CODOC7325 & ARFMaintProj

File No. 472-22350.MNB

Date _________________________

MICHSPEC§ DTMB 00300 ! 6 (R 03/22)

ARTICLE 8 BID SUBMITTED ON the _______ day of ________________, 20____.

8.1. Bid Security is in the form of a Bid Bond _______ Bid Bond form provided in Section 00310 has been duly executed _______; or

A Certified or Cashier's check ___ or Money Order ___ if a check or money order is provided as Bid Security, the original check/money order must be delivered before Bid Due Time to the issuing office as per Section 00100 paragraph 5.2 and Section 00110 item 3.

8.2. If the Bidder is an Individual:

Name of Individual: _________________________________________________________

Name & Title of Person Authorized to sign: _________________________________________________________

Signature: _________________________________________________________ (If not the Individual, Attach Power of Attorney) Date

Doing Business as: _________________________________________________________

Business Address: _________________________________________________________

SIGMA VENDOR NUMBER ____________________________________________

County of registration _________________________

Telephone: _________________________ FAX: ______________________

8.3. If the Bidder is a Partnership:

By: _________________________________________________________ (True Name of the Partnership)

Partner Authorized to Sign Date

Signature: _________________________________________________________ (Attach evidence of Authority to sign) Date

Business Address: _________________________________________________________

SIGMA VENDOR NUMBER ____________________________________________

County of registration _________________________

Telephone: _________________________ FAX _______________________

8.4. If the Bidder is a Corporation:

By: _________________________________________________________ (Legal Corporation Name)

Name & Title of Authorized Officer: _________________________________________________________

Signature: _________________________________________________________ (Attach evidence of Authority to sign) Date

Name & Title of Officer Attesting: _________________________________________________________

Signature: _________________________________________________________ Date

Business Address: _________________________________________________________

SIGMA VENDOR NUMBER ____________________________________________

Telephone: _________________________ FAX _______________________

(State of Incorporation): _________________________________________________________

MICHSPEC§ DTMB 00300 ! 7 (R 03/22)

8.5. If The Bidder is A Joint Venture: JOINT VENTURE SIGNATURES SHALL BE AS PROVIDED IN PARAGRAPH 9.5 OF SECTION 00100 INSTRUCTIONS TO BIDDERS. EACH JOINT VENTURER SIGNING THE BID SHALL SIGN IN THE MANNER INDICATED FOR AN INDIVIDUAL, A PARTNERSHIP OR A CORPORATION. IF MORE THAN TWO JOINT VENTURERS OF THE SAME TYPE ARE INCLUDED, USE ADDITIONAL PAGES. JOINT VENTURE STATE OF INCORPORATION ___________________ OR COUNTY OF

REGISTRATION _____________________

CERTIFICATE OF PRINCIPAL

(BIDDER)

I, ________________________________, certify that I am the Secretary of the Corporation ____, or a General Partner ____ or Managing Partner ____ or Partner ____ of the partnership, named as the Bidder in the attached Section 00300 Bid Form; that __________________ _____________ who signed Section 00300 Bid Form on behalf of the Bidder, was then _____________________ of that corporation ____ or partnership ____; that I know the undersigned's signature, and the signature is genuine; and that Section 00300 Bid Form was duly signed, sealed and attested for and on behalf of that corporation ___ partnership ___ by authority of its governing body ___ or partners ___

Signed by the Secretary or Other Authorized Officer of the Corporation Date or By General Partner or Managing Partner or Authorized Partner Certifying

Name of the Corporation or True Name of the Partnership

Federal Identification (I.D.) No. or Social Security No. (LAST 4 ONLY)__________________________________

Telephone No. ____________________________

(Corporate Seal)

VERIFICATION

(BIDDER)

STATE OF MICHIGAN )

COUNTY OF __________________ )

Before me, a Notary duly commissioned, qualified and acting, personally appeared (enter name of person who signed the Bid Form on behalf of the Bidder), _______________________________________________ to me well known to be the person described in and who signed Section 00300 Bid Form, who being by me first duly sworn upon oath, says that he/she is the Attorney-in-Fact for (enter the Bidder's name) ___________________________________________________________________ and that he/she has been authorized by (enter name of individual, partnership name, or that governing body of the Bidder named in the attached corporate resolution) _______________ _____________________________________________________________________ to execute the attached Section 00300 Bid Form on behalf of the named Bidder in favor of the STATE OF MICHIGAN.

Subscribed and sworn before me this __________ day of ______________________________, 20_____.

Notary Public, State of: _________________

My Commission Expires: _____________________________________

END OF SECTION 00300

Image 1: Building 200 Boiler Pumps

Image 2: Building 200 Boilers

Image 3: Building 200, Above Boilers. Angle 1

Image 4: Building 200, Above Boilers. Angle 2.

Image 5: Building 200, Air Handling Unit Example (AHU 1)

Image 6: AHU Coil Connec on Example

Image 7: Building 300 Roo op Condensing Unit

Image 8: Building 300 AHU (AHU-3) Coil Connec ons Example

Image 9: Building 300 AHU-3

FILE 472-22397.MNB, 472-22350.MNB 23 05 93 - 1

GUS HARRISON-B-200 BOILER REPLACEMENT & B-300 HVAC REPLACEMENT 12/23

SECTION 23 05 93

TESTING, ADJUSTING, AND BALANCING

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Testing, adjustment, and balancing of air systems.

B. Testing, adjustment, and balancing of hydronic systems.

C. Measurement of final operating condition of HVAC systems.

1.2 RELATED SECTIONS

A. Division 23

PART 2 PRODUCTS

2.1 NOT USED

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 Pre-Demolition: TAB contractor shall provide total system balance prior to any demolition of existing systems to establish performance benchmark. TAB report shall include water flow at all main distribution pumps, Air Handling Unit pumps, and Air Handling Unit Supply, Return and Outside air flow at all existing Air Handling Units. Addendum #3

3.3 New work:

3.3.1 Perform total system balance in accordance with one of the following:

3.3.1.1 AABC MN-1, AABC National Standards for Total System Balance.

3.3.1.2 NEBB Procedural Standards for Testing Adjusting Balancing of

Environmental Systems.

3.3.1.3 SMACNA HVAC Systems Testing, Adjusting, and Balancing.

3.3.2 Begin work after completion of systems to be tested, adjusted, or balanced and complete work prior to Substantial Completion of the project.

3.3.3 TAB Agency Qualifications:

3.3.3.1 Company specializing in the testing, adjusting, and balancing of systems specified in this section.

3.3.3.2 Having minimum of three years documented experience.

3.3.3.3 Certified by one of the following:

3.3.3.3.1 AABC, Associated Air Balance Council: www.aabchq.com;

upon completion submit AABC National Performance Guaranty.

3.3.3.3.2 NEBB, National Environmental Balancing Bureau:

www.nebb.org.

3.3.3.3.3 TABB, The Testing, Adjusting, and Balancing Bureau of National Energy Management Institute:

www.tabbcertified.org.

3.3.3.3.4 2 Letters of recommendation from building Owner/Engineer referencing recent, similar sized project requiring testing and air/water balancing.

FILE 472-22397.MNB, 472-22350.MNB 23 05 93 - 2

3.3.4 TAB Supervisor and Technician Qualifications: Certified by same organization/requirements as TAB agency.

3.4 EXAMINATION

3.4.1 Verify that systems are complete and operable before commencing work. Ensure the following conditions:

3.4.1.1 Systems are started and operating in a safe and normal condition.

3.4.1.2 Temperature control systems are installed complete and operable.

3.4.1.3 Proper thermal overload protection is in place for electrical equipment.

3.4.1.4 Final filters are clean and in place. If required, install temporary media in addition to final filters.

3.4.1.5 Duct systems are clean of debris.

3.4.1.6 Fans are rotating correctly.

3.4.1.7 Air coil fins are cleaned and combed.

3.4.1.8 Access doors are closed and duct end caps are in place.

3.4.1.9 Air outlets are installed and connected.

3.4.1.10Duct system leakage is minimized.

3.4.1.11Hydronic systems are flushed, filled, and vented.

3.4.1.12Pumps are rotating correctly.

3.4.1.13Service and balance valves are open.

3.4.2 Submit field reports. Report defects and deficiencies noted during performance of services which prevent system balance.

3.4.3 Beginning of work means acceptance of existing conditions.

3.5 PREPARATION

3.5.1 Hold a pre-balancing meeting at least one week prior to starting TAB work.

3.5.1.1 Require attendance by all installers whose work will be tested, adjusted, or balanced.

3.6 INSTALLATION TOLERANCES

3.6.1 Air Moving Systems: Adjust to within plus or minus 5 percent of design for supply systems and plus or minus 10 percent of design for return and exhaust systems.

3.6.2 Outside Air Inlets: Adjust total to minimum air flow indicated on equipment schedule. (only required for media and room 19, and outside air quantities to mini-split units in Administrative area).

3.6.3 Hydronic Systems: Adjust to within plus or minus 10 percent of design.

3.7 RECORDING AND ADJUSTING

3.7.1 Field Logs: Maintain written logs including:

3.7.1.1 Running log of events and issues.

3.7.1.2 Discrepancies, deficient or uncompleted work by others.

3.7.1.3 Contract interpretation requests.

3.7.1.4 Lists of completed tests.

3.7.2 Ensure recorded data represents actual measured or observed conditions.

3.7.3 Permanently mark settings of valves, dampers, and other adjustment devices allowing settings to be restored. Set and lock memory stops.

3.7.4 After adjustment, take measurements to verify balance has not been disrupted or that such disruption has been rectified.

FILE 472-22397.MNB, 472-22350.MNB 23 05 93 - 3

3.7.5 Leave systems in proper working order, replacing belt guards, closing access doors, closing doors to electrical switch boxes, and restoring thermostats to specified settings.

3.8 AIR SYSTEM PROCEDURE

3.8.1 Adjust air handling and distribution systems to provide required or design supply, return, and exhaust air quantities.

3.8.2 Make air quantity measurements in ducts by Pitot tube traverse of entire cross sectional area of duct.

3.8.3 Measure air quantities at air inlets and outlets.

3.8.4 Adjust distribution system to obtain uniform space temperatures free from objectionable drafts and noise.

3.8.5 Use volume control devices to regulate air quantities only to extend that adjustments do not create objectionable air motion or sound levels. Effect volume control by duct internal devices such as dampers and splitters.

3.8.6 Vary total system air quantities by adjustment of fan speeds. Provide drive changes required. Vary branch air quantities by damper regulation.

3.8.7 Provide system schematic with required and actual air quantities recorded at each outlet or inlet.

3.8.8 Measure static air pressure conditions on air supply units, including filter and coil pressure drops, and total pressure across the fan. Make allowances for 50 percent loading of filters.

3.8.9 Adjust outside air automatic dampers, outside air, return air, and exhaust dampers for design conditions.

3.8.10 Measure temperature conditions across outside air, return air, and exhaust dampers to check leakage.

3.9 WATER SYSTEM PROCEDURE

3.9.1 Adjust water systems to provide required or design quantities. Prior to TAB work, test for flow at all terminal units and set all pumps to lowest bhp thru VFD as necessary to achieve required flow. Once flow is obtained at all terminal devices, re-balance system.

3.9.2 Use calibrated Venturi tubes, orifices, or other metered fittings and pressure gauges to determine flow rates for system balance. Where flow metering devices are not installed, base flow balance on temperature difference across various heat transfer elements in the system.

3.9.3 Adjust systems to provide specified pressure drops and flows through heat transfer elements prior to thermal testing. Perform balancing by measurement of

FILE 472-22397.MNB, 472-22350.MNB 23 05 93 - 4

temperature differential in conjunction with air balancing.

3.9.4 Effect system balance with automatic control valves fully open to heat transfer elements.

3.9.5 Effect adjustment of water distribution systems by means of balancing cocks, valves, and fittings. Do not use service or shut-off valves for balancing unless indexed for balance point.

3.9.6 Where available pump capacity is less than total flow requirements or individual system parts, full flow in one part may be simulated by temporary restriction of flow to other parts.

3.10 SCOPE

3.10.1 Test, adjust, and balance the following:

3.10.1.1Pumps (all new pumps in the heating system) 3.10.1.2Air Handling Unit Coils (air flow and water flow) 3.10.1.3Cabinet Unit and Unit Heaters 3.10.1.4VAV, VVR Units

3.11 MINIMUM DATA TO BE REPORTED

3.11.1 Electric Motors:

3.11.1.1Manufacturer 3.11.1.2Model/Frame

3.11.1.3HP/BHP

3.11.1.4Phase, voltage, amperage; nameplate, actual, no load

3.11.1.5RPM

3.11.1.6Service factor

3.11.2 V-Belt Drives:

3.11.2.1Identification/location 3.11.2.2Required driven RPM 3.11.2.3Driven sheave, diameter and RPM 3.11.2.4Belt, size and quantity

3.11.3 Pumps:

3.11.3.1Identification/number 3.11.3.2Manufacturer 3.11.3.3Size/model 3.11.3.4Impeller 3.11.3.5Service 3.11.3.6Design flow rate, pressure drop, BHP 3.11.3.7Actual flow rate, pressure drop, BHP 3.11.3.8Discharge pressure 3.11.3.9Suction pressure

3.11.3.10 Total operating head pressure

3.11.3.11 Shut off, discharge and suction pressures

3.11.3.12 Shut off, total head pressure

3.11.4 Heating Coils:

3.11.4.1Identification/number 3.11.4.2Location 3.11.4.3Service

FILE 472-22397.MNB, 472-22350.MNB 23 05 93 - 5

3.11.4.4Manufacturer 3.11.4.5Air flow, design and actual 3.11.4.6Water flow, design and actual 3.11.4.7Water pressure drop, design and actual 3.11.4.8Entering water temperature, design and actual 3.11.4.9Leaving water temperature, design and actual

3.11.4.10 Entering air temperature, design and actual

3.11.4.11 Leaving air temperature, design and actual

3.11.4.12 Air pressure drop, design and actual

3.11.5 Air Moving Equipment:

3.11.5.1Location 3.11.5.2Manufacturer 3.11.5.3Model number 3.11.5.4Serial number 3.11.5.5Arrangement/Class/Discharge 3.11.5.6Air flow, specified and actual 3.11.5.7Return air flow, specified and actual 3.11.5.8Outside air flow, specified and actual 3.11.5.9Total static pressure (total external), specified and actual

3.11.5.10 Inlet pressure

3.11.5.11 Discharge pressure

3.11.5.12 Fan RPM

3.11.6 AHU Return Air/Outside Air:

3.11.6.1Identification/location 3.11.6.2Design air flow 3.11.6.3Actual air flow 3.11.6.4Design return air flow 3.11.6.5Actual return air flow 3.11.6.6Design outside air flow 3.11.6.7Actual outside air flow 3.11.6.8Return air temperature 3.11.6.9Outside air temperature

3.11.6.10 Required mixed air temperature

3.11.6.11 Actual mixed air temperature

3.11.6.12 Design outside/return air ratio

3.11.6.13 Actual outside/return air ratio

3.11.7 Air Distribution VAV / VVR:

3.11.7.1Air terminal number 3.11.7.2Room number/location 3.11.7.3Terminal type 3.11.7.4Terminal size 3.11.7.5Design velocity 3.11.7.6Design air flow 3.11.7.7Test (final) velocity 3.11.7.8Test (final) air flow 3.11.7.9Percent of design air flow

END OF SECTION