Complete_RFP_140R4024R0024_GVIC_Fish_Screen_2.pdf

PDF 3 MB Posted

Attached to
GVIC FISH SCREEN REHABILITATION
Solicitation number
140R4024R0024
Issued by

About this file

This is a Request for Proposals (RFP) issued by the Bureau of Reclamation for the GVIC Fish Screen Rehabilitation project located in Mesa County south of downtown Palisade, Colorado. The project involves improving a fish screen system with bifold overshot gates, automated trash screens, and a fish return structure at the beginning of the Grand Valley Canal system operated by the Grand Valley Irrigation Company.

The work includes removing existing weld wire fish screens, installing government-furnished traveling screens and trash conveyor system, installing overshot bifold gates with electrical service, adding data connections for flow monitoring, modifying the fish return structure concrete, and placing cast-in-place concrete for the bypass channel. This is a total small business set-aside with a size standard of $45 million under NAICS code 237110. The estimated magnitude is $1-5 million. Offers are due January 8, 2025 at 2:00 PM MST. A pre-bid site visit is scheduled for December 18, 2024 at 10:00 AM MST. The period of performance is 366 calendar days from Notice to Proceed, with an anticipated start date of April 1, 2025. The technical evaluation factors, in descending order of importance, are Technical Approach, Comprehensive Construction Schedule, Project Team Composition, Past Performance, and Price, with non-price factors being significantly more important than price.

View the file

Other files

File Type Posted
Updated_-_35_22_18_-_Gate_Actuators_Revised_2025_01_14_0003.pdf PDF
Updated_-_01_33_00_-_Submittals_Revised_2025_01_14_0003.pdf PDF
Updated_-_26_05_33_-_Electrical_Conduit_Revised_2025_01_10_0003.pdf PDF
Updated_-_01_11_00_-_Summary_of_Work_Revised_2025_01_13_0003.pdf PDF
Updated_-_31_23_02_-_Compacting_Earth_Materials_Revised_2025_01_14_0003.pdf PDF
Updated_-_Attachment_J5_-__Past_Performance_Questionnaire_0003.pdf PDF
Sol_140R4024R0024_Amd_0003.pdf PDF
Updated_Site_Visit_Questions_2025_01_15_-_GVIC_0003.pdf PDF
Updated_-_00_01_10_-_Table_of_Contents_Revised_2025_01_14_0003.pdf PDF
Site_Visit_Agenda_GVIC_Fish_Screen_0002.pdf PDF
Site_Visit_Questions_and_Answers_-_140R4024R0024_0002.pdf PDF
Sol_140R4024R0024_Amd_0002.pdf PDF
Sign_in_Sheet_for_Site_Visit_0002.pdf PDF
Sol_140R4024R0024_Amd_0001.pdf PDF
Attachment_J7_-_SF25_Performance_Bond.pdf PDF
Attachment_J9_-_Price_Schedule_Sheet.xlsx XLSX spreadsheet
Attachment_J6_-_SF24_Bid_Bond_Form.pdf PDF
Attachment_J1_-_Descriptions_and_Specifications.pdf PDF
Attachment_J5_-__Past_Performance_Questionnaire.pdf PDF
Attachment_J3_-_Wage_Requirements_Determination__8_Nov_24.pdf PDF
Attachment_J2c_-_GVIC_Drawing_Package_3_of_3.pdf PDF
Attachment_J2b_-_GVIC_Drawing_Package_2_of_3.pdf PDF
Attachment_J2a_-_GVIC_Drawing_Package_1_of_3.pdf PDF
Sol_140R4024R0024.pdf PDF
Attachment_J8_-_SF25A_Payment_Bond.pdf PDF
Attachment_J4_-__Subcontractor_Percentage_Worksheet.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

- BUREAU OF -

RECLAMATION

Solicitation No. 140R4024R0024

GVIC Fish Screen Rehabilitation

U.S. Department of the Interior

Bureau of Reclamation

Upper Colorado Region

Salt Lake City, Utah December 2024

140R4024R0024

GVIC Fish Screen Rehabilitation

PART I THE SCHEDULE…………………………………………………………………………….A-1

SECTION A SOLICITATION/CONTRACT FORM……………………………………………...A-2

SECTION B SUPPLIES OR SERVICES AND PRICE/COSTS…………………………………..B-1

SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK…………………...C-1

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 14 10 Use of Site

01 31 19 Project Management and Coordination

01 33 00 Submittals

01 35 10 Safety Data Sheets

01 35 20 Safety and Health

01 35 21 Removal from Work

01 42 10 Reference Standards

01 46 00 Quality Procedures

01 51 00 Temporary Utilities

01 56 10 Protection of Existing Installations

01 56 15 Protection of Existing Utilities

01 57 20 Environmental Controls

01 57 30 Water Pollution Control

01 57 60 Protected Species

01 57 90 Preservation of Historical and Archeological Data

01 60 00 Product Requirements

01 64 40 Governmental Furnished Products

01 71 13 Mobilization and Preparatory Work

01 71 20 Surveying

01 74 00 Cleaning and Waste Management

01 78 30 Project Record Documents

DIVISION 02 – EXISTING CONDITIONS

02 41 07 Modification or Removal of Existing Features

DIVISION 03 – CONCRETE

03 11 10 Concrete Forming

03 20 00 Concrete Reinforcing

03 20 30 Grouted Anchor Bars

03 30 00 Cast-In-Place Concrete

03 62 20 Nonshrink Grout for Equipment and Metalwork

03 81 10 Concrete Removals

DIVISION 04 – NOT USED

DIVISION 05 – METALS

05 50 00 Metal Fabrications

DIVISION 06-10 – NOT USED

DIVISION 11 – EQUIPMENT

11 95 00 Traveling Screen System

DIVISION 12-21 – NOT USED

DIVISION 22 – PLUMBING

22 11 00 Facility Water Distribution

22 16 00 Wash Water Supply System

DIVISION 23-25 – NOT USED

DIVISION 26 – ELECTRICAL

26 05 02 Basic Electrical Materials and Methods

26 05 10 Conductors and Cables

26 05 20 Grounding and Bonding

26 05 33 Electrical Conduit

26 24 24 Distribution Panelboard

DIVISION 27-30 – NOT USED

DIVISION 31 – EARTHWORK

31 02 10 Water for Dust Abatement

31 03 33 Removal and Control of Water

31 23 02 Compacting Earth Materials

31 23 11 Earthwork for Structures

31 23 39 Disposal of Excavated Materials

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 15 10 Road Surfacing

DIVISION 33 – UTILITIES

33 41 10 Polyethylene Storm Drain

DIVISION 34 – NOT USED

DIVISION 35 – WATERWAYS AND MARINE CONSTRUCTION

35 22 17 Dual Leaf Gates

35 22 18 Gate Actuators

35 22 20 Bi-fold Overshot Gates

35 69 20 Safety Cable with Floats

DIVISION 36-50 – NOT USED

DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS

51 00 00 Information Available to Offerors

DIVISION 52 – DRAWINGS

52 00 00 Drawings

SECTION D PACKAGING AND MARKING……………………………………………………D-1

SECTION E INSPECTION AND ACCEPTANCE………………………………………………..E-1

E.1. 52.236-5 Material and Workmanship (APR 1984).…………………………………..E-1

E.2. 52.246-12 Inspection of Construction (Aug 1996)…………………………………….E-1

E.3. 52.246-21 Warranty of Construction (Mar 1994), Alternate I (Apr 1984)…………….E-1

….SECTION F Section F Deliveries and Performance……………………………………………….F-1

F.1. 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)………F-1

F.2. 52.211-12 Liquidated Damages – Construction (Sep 2000)…………………………...F-1

F.3. 52.211-13 Time Extensions (Sep 2000)………………………………………………..F-1

F.4. 52.211-18 Variation in Estimated Quantity (Apr 1984)………………………………..F-1

F.5. 52.242-14 Suspension of Work (Apr 1984)……………………………………………F-1

SECTION G CONTRACT ADMINISTRATION………………………………………………….G-1

G.1. Government Point of Contact…………………………………………………………..G-1

G.2. WBR 1452.201-70 Authorities and Delegations (Sep 2011)…………………………..G-1

G.3. DOI-AAAP-0028 Electronic Invoicing and Payment Requirements – Invoice Processing

Platform (IPP) (Apr 2013)………………………………………………………………………G-1

G.4. WBR 1452.201-80 Contracting Officer’s Representative’s Authorities and Limitations

-- Bureau of Reclamation (May 2018)…………………………………………………………..G-1

SECTION H SPECIAL CONTRACT REQUIREMENTS………………………………………...H-1

H.1. DOI-AAAP-0050 Contractor Performance Assessment Reporting System

(Dec 2015………………………………………………………………………………………..H-1

PART II CONTRACT CLAUSES………………………………………………………………...I-1

SECTION I CONTRACT CLAUSES……………………………………………………………....I-1

I.1. 52.252-2 Clauses Incorporated by Reference (Feb 1998)……………………………....I-1

I.2. 52.201-1 Acquisition 360: Voluntary Survey (Sep 2023)………………………………I-1

I.3. 52.202-1 Definitions (Jun 2020)………………………………………………………..I-1

I.4. 52.203-3 Gratuities (Apr 1984)…………………………………………………………I-1

I.5. 52.203-5 Covenant Against Contingent Fees (May 2014)……………………………...I-1

I.6. 52.203-6 Restriction on Subcontractor Sales to the Government (Jun 2020)…………..I-1

I.7. 52.203-7 Anti-Kickback Procedures (Jun 2020)………………………………………..I-1

I.8. 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper

Activity (May 2014)……………………………………………………………………………...I-1

I.9. 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)……...I-1

I.10. 52.203-12 Limitations on Payments to Influence Certain Federal Actions (Jun 2020)...I-1

I.11. 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021)……………...I-1

I.12. 52.203-14 Display of Hotline Poster(s) (Nov 2021)……………………………………I-1

I.13. 52.203-15 Whistleblower Protections Under the American Recovery and Reinvestment

Act of 2009 (Jun 2010)…………………………………………………………………………...I-1

I.14. 52.203-16 Preventing Personal Conflicts of Interest (Jun 2020)……………………….I-1

I.15. 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)...…………………I-1

I.16. 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (Jan 2017)……………………………………………………………………………I-1

I.17. 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)…………..I-1

I.18. 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(Jun 2020)………………………………………………………………………………………...I-1

I.19. 52.204-12 Unique Entity Identifier Maintenance (Oct 2016)…………………………..I-1

I.20. 52.204-13 System for Award Management (Oct 2018)………………………………...I-1

I.21. 52.204-14 Service Contract Reporting Requirements (Oct 2016)……………………...I-1

I.22. 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020)………I-1

I.23. 52.204-19 Incorporation by Reference Representations and Certifications (Dec

2014)……………………………………………………………………………………………...I-2

I.24. 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov

2021)……………………………………………………………………………………………...I-2

I.25. 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed

Or Provided by Kaspersky Lab and Other Covered Entities (Dec 2023)………………………..I-2

I.26. 52.204.25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services and Equipment (Nov 2021)……………………………………………….I-2

I.27. 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023)………………I-2

I.28. 52.204-30 Federal Acquisition Supply Chain Security Act Orders – Prohibition (Dec

2023)……………………………………………………………………………………………...I-2

I.29. 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (Nov 2021)……………………………….....I-2

I.30. 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

(Oct 2018)………………………………………………………………………………………..I-2

I.31. 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov

2015)……………………………………………………………………………………………...I-2

I.32. 52.210-1 Market Research (Nov 2021)…………………………………………………I-2

I.33. 52.215-2 Audit and Records – Negotiation (Jun 2020)…………………………………I-2

I.34. 52.215-8 Order of Precedence – Uniform Contract Format (Oct 1997)………………..I-2

I.35. 52.215-10 Price Reduction Defective Cost or Pricing Data (Aug 2011)…………….....I-2

I.36. 52.215-12 Subcontractor Cost or Pricing Data (Jun 2020)……………………………..I-2

I.37. 52.215-21 Requirements for Cost of Pricing Data and Data Other Than Certified

Cost or Pricing Data – Modifications (Nov 2021)…………………………………………….....I-2

I.38. 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020)…………………….....I-2

I.39. 52.219-8 Utilization of Small Business Concerns (Sep 2023)……………………….....I-2

I.40. 52.219-14 Limitations on Subcontracting (Oct 2022)……………………………….....I-2

I.41. 52.219-28 Post-Award Small Business Program Representation (Feb 2024)…………..I-2

I.42. 52.222-3 Convict Labor (Jun 2003)…………………………………………………….I-2

I.43. 52.222-4 Contract Work Hours and Safety Standards – Overtime Compensation

(May 2018)…………………………………………………………………………………….....I-2

I.44. 52.222-6 Construction Wage Rate Requirements (Aug 2018)……………………….....I-2

I.45. 52.222-7 Withholding of Funds (May 2014)…………………………………………...I-2

I.46. 52.222-8 Payrolls and Basic Records (Jul 2021)…………………………………….....I-2

I.47. 52.222-9 Apprentices and Trainees (Jul 2005)……………………………………….....I-2

I.48. 52.222-10 Compliance with Copeland Act Requirements (Feb 1988)…………………I-2

I.49. 52.222-11 Subcontracts (Labor Standards) (May 2014)………………………………..I-2

I.50. 52.222-12 Contract Termination – Debarment (May 2014)………………………….....I-3

I.51. 52.222-13 Compliance with Construction Wage Rate Requirements and Relation

Regulations (May 2014)……………………………………………………………………….....I-3

I.52. 52.222-14 Disputes Concerning Labor Standards (Feb 1988)……………………….....I-3

I.53. 52.222-15 Certification of Eligibility (May 2014)……………………………………...I-3

I.54. 52.222-21 Prohibition of Segregated Facilities (Apr 2015)…………………………….I-3

I.55. 52.222-26 Equal Opportunity (Sep 2016)………………………………………………I-3

I.56. 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr

2015)……………………………………………………………………………………………...I-3

I.57. 52.222-35 Equal Opportunity for Veterans (Jun 2020)…………………………………I-3

I.58. 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020)…………….....I-3

I.59. 52.222-37 Employment Reports on Veterans (Jun 2020)………………………………I-3

I.60. 52.222-40 Notification of Employee Rights Under the National Labor Relations

Act (Dec 2010)…………………………………………………………………………………...I-3

I.61. 52.222-50 Combating Trafficking of Persons (Nov 2021)……………………………..I-3

I.62. 52.222-54 Employment Eligibility Verification (May 2022)…………………………...I-3

I.63. 52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022)………………..I-3

I.64. 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)………………...I-3

I.65. 52.223-3 Hazardous Material Identification and Material Safety Data (Feb 2021), Alternate I (Jan 1995)………………………………………………………………………….....I-3

I.66. 52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)……….....I-3

I.67. 52.223-20 Aerosols (May 2024)...………………………………………………………I-3

I.68. 52.223-21 Foams (May 2024)..…………………………………………………………I-3

I.69. 52.225-9 Buy American-Construction Materials (Oct 2022)…………………………...I-3

I.70. 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021)……………………...I-3

I.71. 52.227-1 Authorization and Consent (Jun 2020)…………………………………….....I-3

I.72. 52.227-4 Patent Indemnity – Construction Contracts (Dec 2007)……………………...I-3

I.73. 52.227-17 Rights in Data – Special Works (Dec 2007)………………………………...I-3

I.74. 52.228-2 Additional Bond Security (Oct 1997)………………………………………...I-3

I.75. 52.228-5 Insurance – Work on a Government Installation (Jan 1997)…………………I-3

I.76. 52.228-11 Pledges of Assets (Feb 2021)………………………………………………..I-3

I.77. 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022)………………...I-3

I.78. 52.228-14 Irrevocable Letter of Credit (Nov 2014)………………………………….....I-4

I.79. 52.228-15 Performance and Payment Bonds – Construction (Jun 2020)………………I-4

I.80. 52.229-3 Federal, State, and Local Taxes (Feb 2013)…………………………………..I-4

I.81. 52.229-12 Tax on Certain Foreign Procurements (Feb 2021)…………………………..I-4

I.82. 52.232-5 Payment Under Fixed-Price Construction Contracts (May 2014)……………I-4

I.83. 52.232-17 Interest (May 2014)……………………………………………………….....I-4

I.84. 52.232-23 Assignment of Claims (May 2014)……………………………………….....I-4

I.85. 52.232-27 Prompt Payment for Construction Contracts (Jan 2017)……………………I-4

I.86. 52.232-33 Payment by Electronic Funds Transfer – System for Award Management

(Oct 2018)………………………………………………………………………………………..I-4

I.87. 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)…………………I-4

I.88. 52.232-40 Providing Accelerated Payments to Small Business Subcontractors

(Mar 2023)………………………………………………………………………………………..I-4

I.89. 52.233-1 Disputes (Mar 2014), Alternate I (Dec 1991)………………………………...I-4

I.90. 52.233-3 Protest After Award (Aug 1996)……………………………………………...I-4

I.91. 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)…………………...I-4

I.92. 52.236-2 Differing Site Conditions (Apr 1984)………………………………………...I-4

I.93. 52.236-3 Site Investigation and Conditions Affecting Work (Apr 1984)………………I-4

I.94. 52.236-5 Material and Workmanship (Apr 1984)………………………………………I-4

I.95. 52.236-6 Superintendent by the Contractor (Apr 1984)………………………………..I-4

I.96. 52.236-7 Permits and Responsibilities (Nov 1991)………………………………….....I-4

I.97. 52.236-8 Other Contracts (Apr 1984)…………………………………………………..I-4

I.98. 52.236-9 Protecting Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (Apr 1984)………………………………………………………………………..I-4

I.99. 52.236-10 Operation and Storage Areas (Apr 1984)……………………………………I-4

I.100. 52.236-11 Use and Possession Prior to Completion (Apr 1984)…………………….....I-4

I.101. 52.236-12 Cleaning Up (Apr 1984)………………………………………………….....I-4

I.102. 52.236-13 Accident Prevention (Nov 1991), Alternate I (Nov 1991)…………………..I-4

I.103. 52.236-14 Availability and Use of Utility Services (Apr 1984)………………………...I-4

I.104. 52.236-15 Schedules for Construction Contracts (Apr 1984)…………………………..I-4

I.105. 52.236-17 Layout of Work (Apr 1984)…………………………………………………I-4

I.106. 52.236-21 Specifications and Drawings for Construction (Feb 1997), Alternate I

(Apr 1984)………………………………………………………………………………………..I-4

I.107. 52.236-26 Preconstruction Conference (Feb 1995)………………………………….....I-5

I.108. 52.242-13 Bankruptcy (Jul 1995)…………………………………………………….....I-5

I.109. 52.243-4 Changes (Jun 2007)…………………………………………………………...I-5

I.110. 52.244-2 Subcontracts (Jun 2020)……………………………………………………....I-5

I.111. 52.244-6 Subcontracts for Commercial Products and Commercial Services (Sep

2023)……………………………………………………………………………………………...I-5

I.112. 52.245-1 Government Property (Sep 2021).....................................................................I-5

I.113. 52.245-9 Use and Charges (Apr 2012)……………………………………………….....I-5

I.114. 52.248-3 Value Engineering – Construction (Oct 2020), Alternate I (Apr 1984)………I-5

I.115. 52.249-2 Termination for Convenience of the Government (Fixed Price) (Apr 2012)

Alternate I (Sep 1996)……………………………………………………………………………I-5

I.116. 52.249-10 Default (Fixed Price Construction) (Apr 1984)……………………………..I-5

I.117. WBR 1452.203-70 Restrictions on Endorsements-Department of Interior (Jul 1996).....I-5

I.118. WBR 1452.204-70 Release of Claims – Department of the Interior (Jul 1996)………...I-5

I.119. DOI-AAAP-0081 Security Requirements: Facility Access Information Technology (Aug

2016)……………………………………………………………………………………………...I-5

I.120. WBR 1452.215-70 Examination of Records by the Department of Interior (Aug 1996)

(Deviation)…………………………………………………………………………………….....I-9

I.121. WBR 1452.215-87 Incorporation of Technical Proposal – Bureau of Reclamation (Mar

2021)……………………………………………………………………………………………...I-9

I.122. WBR 1452.223-80 Asbestos Free Warranty – Bureau of Reclamation (Aug 2021)…....I-9

I.123. WBR 1452.223-81 Safety and Health – Bureau of Reclamation (Oct 2022)…………..I-9

I.124. WBR 1452.223-82 Ensuring Adequate COVID-19 Safety Protocols in Federal buildings and Federally Controlled Facilities – Bureau of Reclamation (Nov 2022)……………………..I-10

I.125. WBR 1452.228-70 Liability Insurance – Department of Interior (Jul 1996)………….I-10

I.126. WBR 1452.232-81 Payment for Mobilization and Preparatory Work – Bureau of

Reclamation (Mar 2022)………………………………………………………………………..I-10

I.127. WBR 1452.236-84 Preservation of Cultural Resources – Bureau of Reclamation (Mar

2022)……………………………………………………………………………………………I-12

I.128. WBR 1452.237-80 Security Requirements – Bureau of Reclamation (Mar 2022)…...I-13

I.129. WBR 1452.243-80 Modification Proposals – Bureau of Reclamation (Mar 2022) Alt II

(Mar 2022)………………………………………………………………………………………I-24

PART III LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS……………...J-1

SECTION J LIST OF ATTACHMENTS…………………………………………………………...J-1

J.1. Descriptions/Specifications, 258 pages………………………………………………….J-1

J.2a. GVIC Drawings, 33 pages...…………………………………………………………….J-1

J.2b. GVIC Drawings, 31 pages………………………………………………………………J-1

J.2c. GVIC Drawings, 46 pages………………………………………………………………J-1

J.3. Department of Labor, General Wage Decision No. CO20240002, dated November 8, 2024, 7 pages..…………………………………………………………………………..J-1

J.4. Subcontract Worksheet, 2 pages………………………………………………………...J-1

J.5. Past Performance Questionnaire, 2 pages……………………………………………….J-1

J.6. SF24 Bid Bond Form, 4 pages…………………………………………………………..J-1

J.7. SF25 Performance Bond Form, 4 pages………………………………………………...J-1

J.8. SF25a Payment Bond Form, 3 pages……………………………………………………J-1

J.9. Price Schedule Sheet, 1 page……………………………………………………………J-1

PART IV REPRESENTATIONS AND INSTRUCTIONS………………………………………..K-1

SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS

OF OFFERORS OR RESPONDENTS

K.1. 52.203-2 Certificate of Independent Price Determination (Apr 1985)………………...K-1

K.2. 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal

Confidentiality Agreements or Statements – Representation (Jan 2017)……………………….K-1

K.3. 52.204-8 Annual Representations and Certifications (Mar 2023)……………………..K-2

K.4. 52.204-24 Representation Regarding Certain Telecommunications and Video

Surveillance Services or Equipment (Nov 2021)……………………………………………….K-6

K.5. 52.204-26 Covered Telecommunications Equipment or Service-Representation

(Oct 2020)…………………………………………………………………………………….....K-8

K.6. 52.209-5 Certification Regarding Responsibility Matters (Aug 2020)………………..K-8

K.7. 52.209-7 Information Regarding Responsibility Matters (Oct 2018)………………....K-8

K.8. 52.225-25 Prohibition on Contracting With Entities Engaging in Certain Activities

Or Transactions Relating to Iran—Representation and Certifications (Jun 2020)…………….K-10

K.9. 52.229-11 Tax on Certain Foreign Procurements – Notice and Representation

(Jun 2020)……………………………………………………………………………………...K-11

SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS……………...L-1

L.1. 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998)……………...L-1

L.2. 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain

Federal Transactions (Sep 2007)………………………………………………………………...L-1

L.3. 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal

Confidentiality Agreements or Statements – Representation (Jan 2017)………………………..L-1

L.4. 52.204-7 System for Award Management (Oct 2018)…………………………………L-1

L.5. 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020)………...L-2

L.6. 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications

Standards and Commercial Item Descriptions, FPMR Part 101-29 (Sep 2023)………………...L-2

L.7. 52.211-2 Availability of Specifications, Standards, and Data Item Descriptions Listed

In the Acquisition Streamlining and Standardization Information System (ASSIST) (Sep

2023)…………………………………………………………………………………………….L-2

L.8. 52.211-6 Brand Name or Equal (Aug 1999)…………………………………………...L-2

L.9. 52.215-1 Instructions to Offerors – Competitive Acquisitions (Nov 2021)……………L-2

L.10. 52.215-16 Facilities Capital Cost of Money (Jun 2003)……………………………….L-5

L.11. 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than

Certified Cost or Pricing Data (Nov 2021)……………………………………………………...L-5

L.12. 1452.215-71 Use and Disclosure of Proposal Information – Department of Interior

(Apr 1984)……………………………………………………………………………………….L-5

L.13. WBR 1452.215-80 Source Selection Evaluation Procedures – Bureau of Reclamation

(Mar 2021)………………………………………………………………………………………L-6

L.14. WBR 1452.215-81 Proposal Instructions – Bureau of Reclamation (Mar 2021)……...L-6

L.15. WBR 1452.215-86 Intent to Incorporate Technical Proposal – Bureau of Reclamation

(Mar 2021)……………………………………………………………………………………..L-12

L.16. 52.216-1 Type of Contract (Apr 1984………………………………………………...L-12

L.17. 52.222-5 Construction Wage Requirements – Secondary Site of Work (May 2014)...L-12

L.18. 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment

Opportunity for Construction (Feb 1999)……………………………………………………...L-12

L.19. 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Oct

2020)…………………………………………………………………………………………...L-13

L.20. 52.225-12 Notice of Buy American Requirement – Construction Materials Under

Trade Agreements (May 2014)…………………………………………………………………L-13

L.21. 52.228-1 Bid Guarantee (Sep 1996)…………………………………………………..L-14

L.22. 1452.233-2 Service of Protest – Department of Interior (Deviation) (Jul 1996)……..L-15

L.23. 52.236-27 Site Visit (Construction) (Feb 1995), Alternate I (Feb 1995)……………..L-15

L.24. 52.236-28 Preparation of Offers – Construction (Oct 1997)…………………………L-16

L.25. WBR 1452.236-85 Instruction for Mobilization and Preparatory Work Schedule Line

Item – Bureau of Reclamation (Mar 2022)…………………………………………………….L-16

L.26. 52.252-2 Authorized Deviations in Provisions (Nov 2020)…………………………..L-16

SECTION M EVALUATION FACTORS FOR AWARD…………………………………………M-1

M.1. WBR 1452.215-84 Evaluation Factors for Award – Quality and Cost/Price

Approximately Equal – Bureau of Reclamation (Mar 2021)…………………………………...M-1

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

40668287

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

Bureau of Reclamation

Upper Colorado Region

Regional Office 125 South State Street, Room 8100

R40

Salt Lake City UT 84138

Tamaron Calloway 8033073567

1x 12/09/2024

140R4024R0024

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

GVIC FISH SCREEN REHABILITATION, Mesa County south of downtown Palisade, Colorado.

Estimated Magnitude: $1,000,000.00 to $5,000,000.00

NAICS 237110 Water and Sewer Line and Related Structures Construction

Total Small Business Set-Aside, Size Standard $45m

Questions will be accepted up to 7 calendar days after site visit. Questions shall be emailed to Ana Fife at afife@usbr.gov. Questions will be answered via an amendment to the solicitation.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 366 calendar days and complete it within ________________ ________________ calendar days after receiving

FAR 52.211-10

01/08/2025

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Upper Colorado Region

Regional Office 125 South State Street, Room 8100

R40

Salt Lake City UT 84138

Ana Fife

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R4024R0024

Delivery Location Code: 0011285654

Bureau of Reclamation-UC-WCAO

445 West Gunnison Ave Suite 221

Grand Junction CO 81501 US

Period of Performance: 04/01/2025 to 05/01/2026

00010 GVIC FISH SCREEN REHABILITATION - Mesa County 1 AU south of downtown Palisade, Colorado.

Product/Service Code: Y1PZ

Product/Service Description: CONSTRUCTION OF

OTHER NON-BUILDING FACILITIES

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

D-1

SECTION D PACKAGING AND MARKING

Section not used.

E-1

SECTION E INSPECTION AND ACCEPTANCE

E.1. 52.236-5 Material and Workmanship (Apr 1984)

E.2. 52.246-12 Inspection of Construction (Aug 1996)

E.3. 52.246-21 Warranty of Construction (Mar 1994), Alternate I (Apr 1984)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to

Government-owned or controlled real or personal property, when that damage is the result of –

(1) The Contractor’s failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall –

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the

Contracting Officer.

(h) In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the

Government may bring suit at its expense to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design

E-2 furnished by the Government nor for the repair of any damage that results from any defect in

Government-furnished material or design.

(j) This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

(k) Defects in design or manufacture of equipment specified by the Government on a “brand name and model” basis, shall not be included in this warranty. In this event, the Contractor shall require any subcontractors, manufacturers, or suppliers thereof to execute their warranties, in writing, directly to the Government.

F-1

SECTION F Section F Deliveries and Performance

F.1. 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to

(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 826 Days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

F.2. 52.211-12 Liquidated Damages - Construction (Sep 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $ 3,650.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

F.3. 52.211-13 Time Extensions (Sep 2000)

F.4 52.211-18 Variation in Estimated Quantity (Apr 1984)

F.5. 52.242-14 Suspension of Work (Apr 1984)

G-1

SECTION G CONTRACT ADMINISTRATION

G.1. Government Point of Contact

The contracting office's point of contact for this contract is:

Name: Ana Fife

Title: Contracting Officer

Address: Bureau of Reclamation, 125 South Street, Salt Lake City, Utah 84138

E-Mail: afife@usbr.gov

G.2. WBR 1452.201-70 Authorities and Delegations (Sep 2011)

G.3. DOI-AAAP-0028 Electronic Invoicing and Payment Requirements - Invoice Processing

Platform (IPP) (Feb 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice

Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the

Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4

Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice [Contracting Officer to edit and include the documentation required under this contract]: The

Contractor must use the IPP website to register access and use IPP for submitting requests for payment.

The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP

Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

G.4. WBR 1452.201-80 Contracting Officer's Representative's Authorities and Limitations --

Bureau of Reclamation (May 2018)

a) Performance of the work under this contract shall be subject to the technical direction of the

Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:

(1) Inspecting and accepting or rejecting work performed under the contract.

(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.

mailto:afife@usbr.gov https://www.ipp.gov/

G-2

(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.

(b) The Contractor will receive a copy of the written COR designation from the Contracting Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting Officer.

(c) Technical direction must be within the scope of work stated in the contract. Only the Contracting

Officer is authorized to determine if a change is within the scope of the contract; therefore, the COR does not have the authority to, and may not, issue any technical direction that –

(1) Constitutes a direction of additional work outside the Contract requirements;

(2) Constitutes a change as defined in the contract clause entitled “Changes;”

(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;

(4) Changes any of the expressed terms, conditions or specifications of the contract; or

(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.

(d) All technical direction shall be issued in writing by the COR.

(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the

COR in the manner prescribed by this clause and within its authority under the provisions of this clause.

If, in the opinion of the Contractor, any instruction or direction by the COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must –

(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or

(2) Advise the Contractor that the Government will issue a written change order. (f) A failure of the

Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”

H-1

SECTION H SPECIAL CONTRACT REQUIREMENTS

H.1. DOI-AAAP-0050 Contractor Performance Assessment Reporting System (Dec 2015)

1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The

Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting

System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for

Government use in evaluating past performance as part of a source selection action.

3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c) All information provided should be reviewed for accuracy prior to submission.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the

Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6) The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

https://www.cpars.gov/ https://www.cpars.gov/

H-2

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the

CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

I-1

PART II CONTRACT CLAUSES

SECTION I CONTRACT CLAUSES

I.1. 52.252-2 Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses: FAR:

www.acquisition.gov/browse/index/far. DIAR: www.ecfr.gov/current/title-48/chapter-14.

The following clauses are hereby incorporated by reference:

I.2. 52.201-1 Acquisition 360: Voluntary Survey (Sep 2023)

I.3. 52.202-1 Definitions (Jun 2020)

I.4. 52.203-3 Gratuities (Apr 1984)

I.5. 52.203-5 Covenant Against Contingent Fees (May 2014)

I.6. 52.203-6 Restriction on Subcontractor Sales to the Government (Jun 2020)

I.7. 52.203-7 Anti-Kickback Procedures (Jun 2020)

I.8. 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May

2014)

I.9. 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)

I.10. 52.203-12 Limitations on Payments to Influence Certain Federal Actions (Jun 2020)

I.11. 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021)

I.12. 52.203-14 Display of Hotline Poster(s) (Nov 2021)

I.13. 52.203-15 Whistleblower Protections Under the American Recovery and Reinvestment Act of

2009 (Jun 2010)

I.14. 52.203-16 Preventing Personal Conflicts of Interest (Jun 2020)

I.15. 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)

I.16. 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (Jan 2017)

I.17. 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)

I.18. 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020)

I.19. 52.204-12 Unique Entity Identifier Maintenance (Oct 2016)

I.20. 52.204-13 System for Award Management (Oct 2018)

I.21. 52.204-14 Service Contract Reporting Requirements (Oct 2016)

I.22. 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) http://www.acquisition.gov/browse/index/far http://www.ecfr.gov/current/title-48/chapter-14

I-2

I.23. 52.204-19 Incorporation by Reference Representations and Certifications (Dec 2014)

I.24. 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov 2021)

I.25. 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab and Other Covered Entities (Dec 2023)

I.26. 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services and Equipment (Nov 2021)

I.27. 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023)

I.28. 52.204-30 Federal Acquisition Supply Chain Security Act Orders – Prohibition (Dec 2023)

I.29. 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (Nov 2021)

I.30. 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct

2018)

I.31. 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)

I.32. 52.210-1 Market Research (Nov 2021)

I.33. 52.215-2 Audit and Records – Negotiation (Jun 2020)

I.34. 52.215-8 Order of Precedence – Uniform Contract Format (Oct 1997)

I.35. 52.215-10 Price Reduction Defective Cost or Pricing Data (Aug 2011)

I.36. 52.215-12 Subcontractor Cost or Pricing Data (Jun 2020)

I.37. 52.215-21 Requirements for Cost or Pricing Data and Data Other Than Certified Cost or

Pricing Data – Modifications (Nov 2021)

I.38 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020)

I.39. 52.219-8 Utilization of Small Business Concerns (Feb 2024)

I.40. 52.219-14 Limitations on Subcontracting (Oct 2022)

I.41. 52.219-28 Post-Award small Business Program Representation (Feb 2024)

I.42. 52.222-3 Convict Labor (Jun 2003)

I.43. 52.222-4 Contract Work Hours and Safety Standards – Overtime Compensation (May 2018)

I.44. 52.222-6 Construction Wage Rate Requirements (Aug 2018)

I.45. 52.222-7 Withholding of Funds (May 2014)

I.46. 52.222-8 Payrolls and Basic Records (Jul 2021)

I.47. 52.222-9 Apprentices and Trainees (Jul 2005)

I.48. 52.222-10 Compliance with Copeland Act Requirements (Feb 1988)

I.49. 52.222-11 Subcontracts (Labor Standards) (May 2014)

I-3

I.50. 52.222-12 Contract Termination – Debarment (May 2014)

I.51. 52.222-13 Compliance with Construction Wage Rate Requirements and Relation Regulations

(May 2014)

I.52. 52.222-14 Disputes Concerning Labor Standards (Feb 1988)

I.53. 52.222-15 Certification of Eligibility (May 2014)

I.54. 52.222-21 Prohibition of Segregated Facilities (Apr 2015)

I.55. 52.222-26 Equal Opportunity (Sep 2016)

I.56. 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015)

I.57. 52.222-35 Equal Opportunity for Veterans (Jun 2020)

I.58. 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020)

I.59. 52.222-37 Employment Reports on Veterans (Jun 2020)

I.60. 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010)

I.61. 52.222-50 Combating Trafficking of Persons (Nov 2021)

I.62. 52.222-54 Employment Eligibility Verification (May 2022)

I.63. 52.222-55 Minimum Wages Under Executive Order 14026 (Jan 2022)

I.64. 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)

I.65. 52.223-3 Hazardous Material Identification and Material Safety Data (Feb 2021), Alternate I

(Jul 1995)

I.66. 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024)

I.67. 52.223-20 Aerosols (May 2024)

I.68. 52.223-21 Foams (May 2024)

I.69. 52.225-9 Buy American – Construction Materials (Oct 2022)

I.70. 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021)

I.71. 52.227-1 Authorization and Consent (Jun 2020)

I.72. 52.227-4 Patent Indemnity – Construction Contracts (Dec 2007)

I.73. 52.227-17 Rights in Data – Special Works (Dec 2007)

I.74. 52.228-2 Additional Bond Security (Oct 1997)

I.75. 52.228-5 Insurance – Work on a Government Installation (Jan 1997)

I.76. 52.228-11 Pledges of Assets (Feb 2021)

I.77. 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022)

I-4

I.78. 52.228-14 Irrevocable Letter of Credit (Nov 2014)

I.79. 52.228-15 Performance and Payment Bonds – Construction (Jun 2020)

I.80. 52.229-3 Federal, State, and Local Taxes (Feb 2013)

I.81. 52.229-12 Tax on Certain Foreign Procurements (Feb 2021)

I.82. 52.232-5 Payment Under Fixed-Price Construction Contracts (May 2014)

I.83. 52.232-17 Interest (May 2014)

I.84. 52.232-23 Assignment of Claims (May 2014)

I.85. 52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

I.86. 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (Oct 2018)

I.87. 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

I.88. 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023)

I.89. 52.233-1 Disputes (Mar 2014), Alternate I (Dec 1991)

I.90. 52.233-3 Protest After Award (Aug 1996)

I.91. 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

I.92. 52.236-2 Differing Site Conditions (Apr 1984)

I.93. 52.236-3 Site Investigation and Conditions Affecting Work (Apr 1984)

I.94. 52.236-5 Material and Workmanship (Apr 1984)

I.95. 52.236-6 Superintendence by the Contractor (Apr 1984)

I.96. 52.236-7 Permits and Responsibilities (Nov 1991)

I.97. 52.236-8 Other Contracts (Apr 1984)

I.98. 52.236-9 Protecting Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(Apr 1984)

I.99. 52.236-10 Operation and Storage Areas (Apr 1984)

I.100. 52.236-11 Use and Possession Prior to Completion (Apr 1984)

I.101. 52.236-12 Cleaning Up (Apr 1984)

I.102. 52.236-13 Accident Prevention (Nov 1991), Alternate I (Nov 1991)

I.103. 52.236-14 Availability and Use of Utility Services (Apr 1984)

I.104. 52.236-15 Schedules for Construction Contracts (Apr 1984)

I.105. 52.236-17 Layout of Work (Apr 1984)

I.106. 52.236-21 Specifications and Drawings for Construction (Feb 1997), Alternate I (Apr 1984)

I-5

I.107. 52.236-26 Preconstruction Conference (Feb 1995)

I.108. 52.242-13 Bankruptcy (Jul 1995)

I.109. 52.243-4 Changes (Jun 2007)

I.110. 52.244-2 Subcontracts (Jun 2020)

I.111. 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2024)

I.112. 52.245-1 Government Property (Sep 2021)

I.113. 52.245-9 Use and Charges (Apr 2012)

I.114. 52.248-3 Value Engineering – Construction (Oct 2020), Alternate I (Apr 1984)

I.115. 52.249-2 Termination for Convenience of the Government (Fixed Price) (Apr 2012), Alternate

I (Sep 1996)

I.116. 52.249-10 Default (Fixed-Price Construction) (Apr 1984)I.116. 52.253-1 Computer Generated

Forms (Jan 1991)

I.117. WBR 1452.203-70 Restrictions on…

This is the start of the file's text. The full file is on GovTribe.