Attachment_J1_-_Descriptions_and_Specifications.pdf

PDF 4 MB Posted

Attached to
GVIC FISH SCREEN REHABILITATION
Solicitation number
140R4024R0024
Issued by

About this file

This is a specifications document detailing requirements for the GVIC Fish Screen Rehabilitation project located in Mesa County south of downtown Palisade, Colorado. The work involves rehabilitating an existing fish screen facility directly downstream on the GVIC Canal from the GVIC River Gates.

Key components include demolishing existing concrete sections, placing new cast-in-place concrete, removing 21 existing weld wire fish screens and cleaning equipment, installing 4 new bi-fold overshot gates and 1 dual leaf gate, installing 16 government-furnished fish screens with debris trough and conveyor system, installing control systems, and providing all necessary plumbing, electrical, and water control connections. The government will furnish approximately $2.85M worth of equipment including screens, conveyors, pumps, and control panels. Construction must be completed between Notice to Proceed and April 1st, 2026 for substantial completion, with final completion by May 1st, 2026. The work supports the Upper Colorado River Endangered Fish Recovery Program and must accommodate simultaneous construction of a separate dam crest raising project. The contractor must maintain specific access routes, follow environmental controls, and coordinate closely with the Bureau of Reclamation's Contracting Officer Representative throughout construction.

View the file

Other files

File Type Posted
Updated_-_35_22_18_-_Gate_Actuators_Revised_2025_01_14_0003.pdf PDF
Updated_-_01_33_00_-_Submittals_Revised_2025_01_14_0003.pdf PDF
Updated_-_26_05_33_-_Electrical_Conduit_Revised_2025_01_10_0003.pdf PDF
Updated_-_01_11_00_-_Summary_of_Work_Revised_2025_01_13_0003.pdf PDF
Updated_-_31_23_02_-_Compacting_Earth_Materials_Revised_2025_01_14_0003.pdf PDF
Updated_-_Attachment_J5_-__Past_Performance_Questionnaire_0003.pdf PDF
Sol_140R4024R0024_Amd_0003.pdf PDF
Updated_Site_Visit_Questions_2025_01_15_-_GVIC_0003.pdf PDF
Updated_-_00_01_10_-_Table_of_Contents_Revised_2025_01_14_0003.pdf PDF
Site_Visit_Agenda_GVIC_Fish_Screen_0002.pdf PDF
Site_Visit_Questions_and_Answers_-_140R4024R0024_0002.pdf PDF
Sol_140R4024R0024_Amd_0002.pdf PDF
Sign_in_Sheet_for_Site_Visit_0002.pdf PDF
Sol_140R4024R0024_Amd_0001.pdf PDF
Attachment_J7_-_SF25_Performance_Bond.pdf PDF
Attachment_J9_-_Price_Schedule_Sheet.xlsx XLSX spreadsheet
Attachment_J6_-_SF24_Bid_Bond_Form.pdf PDF
Complete_RFP_140R4024R0024_GVIC_Fish_Screen_2.pdf PDF
Attachment_J5_-__Past_Performance_Questionnaire.pdf PDF
Attachment_J3_-_Wage_Requirements_Determination__8_Nov_24.pdf PDF
Attachment_J2c_-_GVIC_Drawing_Package_3_of_3.pdf PDF
Attachment_J2b_-_GVIC_Drawing_Package_2_of_3.pdf PDF
Attachment_J2a_-_GVIC_Drawing_Package_1_of_3.pdf PDF
Sol_140R4024R0024.pdf PDF
Attachment_J8_-_SF25A_Payment_Bond.pdf PDF
Attachment_J4_-__Subcontractor_Percentage_Worksheet.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GVIC Fish Screen Rehabilitation

Upper Colorado River Endangered Fish Recovery Program Solicitation No. 140R4024R0024

Summary of Work

01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. The work site is in Mesa County south of downtown Palisade, Colorado. The existing fish screen is directly downstream on the GVIC Canal from the GVIC River Gates.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Demolish concrete sections of existing fish return structure, bypass channel area, and adjacent slabs.

B. Place new cast-in-place concrete for fish return structure, bypass channel structure, and adjacent slabs.

C. Remove and dispose of 21 existing weld wire fish screens and screen cleaning equipment.

D. Furnish and install 4 new bi-fold overshot gates and 1 new dual leaf gate.

E. Install 16 new government furnished fish screens, debris trough, and conveyor system.

F. Install government furnished screen control system.

G. Furnish support platform and install government furnished debris trough pump.

H. Furnish and install all components of the Wash Water Supply System.

I. Furnish and install all plumbing and water control connections.

J. Furnish and install 3 new gate actuators on existing check structure gates.

K. Provide electrical service and data connections to all new components.

1.03 WORK RESTRICTIONS AND LIMITATIONS

A. Do not interfere with GVIC’s maintenance or operations in the vicinity.

B. On April 1st, 2026, GVIC will supply the canal with water for their deliveries. Facilities shall be able to receive water by this date.

Summary of Work

01 11 00 - 2

1.04 SCHEDULE

A. Construction Period: Notice to proceed date to April 1st, 2026, for substantial completion.

B. Contractor shall complete all work by May 1st, 2026.

1.05 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.06 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. GVIC: Grand Valley Irrigation Company.

2. BOR: Bureau of Reclamation

3. CO: Contracting Officer

4. COR: Contracting Officer’s Representative

5. CY: Cubic yard

6. LF: Linear Foot

1.07 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations

(FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. Inspection & Cleaning Manual-2021 Inspection and Cleaning Manual for

Equipment and Vehicles to Prevent the Spread of Invasive Species (Policy and Programs, Environmental Compliance Division) 2021 Edition Available online at:

http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid and medical facilities.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences.

2. Submit revised drawings of changes in use of land made during design and erection stages or after use of land is in operation.

http://www.usbr.gov/mussels/prevention

01 14 10 - 2

1.04 PROJECT CONDITIONS

A. Areas shown on Drawing No. 1745-417-112 are areas specifically identified for this construction contract that may be used for required construction facilities and staging areas.

B. Location, construction, operation, maintenance, and removal of construction facilities in areas shown in the Land Use and Landscape Rehabilitation Plan Submittal will be subject to approval by COR.

C. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

D. Do not interfere with work of other contractors or the Owner/Government in vicinity, or with reservations made by the Owner/Government for use of such land.

1. A second construction project to raise the crest of the diversion dam and install new flood gates will likely run simultaneously with this project. This effort will require the following:

a. A 14’ wide lane for access through site as shown on Drawing No. 1745-

417-112 must be maintained along the south canal road from the Colorado river to the bridge that exits onto Logan Ct. at Riverbend Park. If this lane must be closed for periods longer than one hour, contractor must coordinate closure with government and may be required to schedule closure during non-normal work hours.

E. Vehicle traffic on the north side of the canal is accessed through the gate at the end of Brentwood Drive. As shown on Drawing No. 1745-417-112, the Contractor may install a temporary canal crossing just downstream of the Check Structure for ferrying vehicles and heavy equipment across the canal.

F. Contractor may use existing GVIC bridge for passenger vehicle traffic only as shown on Drawing No. 1745-417-112.

G. Housing for construction personnel will not be permitted on site, except housing for guards or watchmen as may be approved by COR.

H. Contractor shall take steps to protect trees adjacent to the potential staging area south of the canal.

1.05 PROVISIONS FOR GOVERNMENT TRAILER

A. The Contractor shall provide an area and maintain vehicle access for a Government trailer.

B. The Government trailer is a towed trailer approximately 25’ in length, that will be used by the COR for storing materials and an office area.

01 14 10 - 3

C. The area for the Government trailer shall be located outside the area of construction and haul roads.

D. Locate the trailer close to the Contractor’s job trailer or in another area approved by the

COR.

E. Provide temporary power for the Government trailer.

1. Power requirement: 110 volts, 30 amps.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEANING

A. Construction equipment:

1. Clean construction equipment before bringing on site. Remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.

3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.

3.02 RESTORATION

A. Repair, at Contractor's expense, damage to existing installations due to Contractor's operations or Contractor's failure to provide proper protection. At the Government's option, damage may be repaired by the Government, and the Contractor will be back charged repair costs.

B. Restore Contractor use areas to pre-construction condition.

C. After completion of work, regrade disturbed land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

01 14 10 - 4

This page intentionally left blank.

Project Management and Coordination

01 31 19 - 1

SECTION 01 31 19

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include project management in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (Reclamation)

1. RSHS-2024 Reclamation Safety and Health Standards, including revisions posted at https://www.usbr.gov/ssle/safety/RSHS/rshs

.html.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 PROJECT COORDINATION

A. Contractor shall coordinate all work with the COR throughout the duration of this contract.

B. The following meetings are considered significant, but do not relieve the Contractor from the responsibility of other meetings required by the specifications.

3.02 PRECONSTRUCTION MEETING

A. Meet with COR at Reclamation’s Western Colorado Area Office in Grand Junction, CO prior to the start of construction. The Contractor shall provide as a minimum the Project

Manager or Project Superintendent and the critical subcontractors for the Preconstruction

Meeting. Review will include, but may not be limited to:

1. Use of premises by Contractor, Owner, and Government.

2. Construction facilities and controls.

3. Temporary utilities.

https://www.usbr.gov/ssle/safety/RSHS/rshs.html https://www.usbr.gov/ssle/safety/RSHS/rshs.html

01 31 19 - 2

4. Survey layout.

5. Security.

6. Housekeeping procedures.

7. Schedules and sequence of work.

8. Work restrictions.

9. Quality assurance by the Government.

10. Quality control by the Contractor.

11. Procedures for maintaining record documents.

12. Roles and responsibilities:

a. Reclamation organization and personnel.

b. Contractor organization and personnel.

c. Subcontractors.

d. Proposed work schedule.

13. Contract requirements:

a. Progress payments.

b. Invoices.

c. Differing site conditions.

d. Changes.

e. Superintendence by the Contractor.

f. Payment for mobilization and preparatory work.

g. Submittal procedures.

h. As-built drawings.

3.03 PRECONSTRUCTION SAFETY MEETING

A. On the same day and after the Preconstruction Meeting, meet with COR.

B. Review will include:

1. Safety requirements.

2. Monthly joint safety policy meetings.

3. Weekly toolbox safety meetings.

4. Contractor’s safety program.

5. Job hazard analysis.

6. Required safety inspections.

7. Government will monitor Contractor’s operations for compliance with RSHS.

01 31 19 - 3

3.04 PROGRESS MEETINGS

A. Contractor will conduct weekly progress meetings on-site or via conference call with

COR to review work, review status of submittals, progress made, difficulties in performing work, and resolution necessary to meet specifications requirements.

B. Meetings will include review of upcoming work (two week look ahead) and include updating of construction schedule as necessary.

01 31 19 - 4

Submittals

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-2011 United States National CAD Standards, Version 5

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as part of a complete submittal.

C. Submittal Types, as listed in Table 01 33 00A – List of Submittals:

1. A – Approval:

a. Government will approve or disapprove these submittals.

b. Approval submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.

2. I – Informational:

a. The Government will acknowledge receipt of these submittals.

b. The Government may reject an Informational submittal when the submittal does not comply with the contract. The Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.

c. Informational submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by the Government is not required.

01 33 00 - 2

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number, contract title, and RSN.

3. Measurement units: US Customary Units.

C. Drawings:

1. Minimum identification in title block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

3. Size: D size (22 inches by 34 inches) as defined by ASME Y14.1.

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.

5. Government Format drawings:

a. Prepare drawings designated as “Government Format” in the specifications as follows:

1) Title block and sheet format:

a) As shown on Drawing 40-D-7102.

b) Government will provide specific title block information to be used.

2) Drawing format:

a) AutoCAD, Version 2018 or later.

b) In accordance with NIBS NCS.

3) Government will provide an electronic AutoCAD template.

6. Final drawings:

a. Drawing format: AutoCAD, Version 2018 or later.

b. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

01 33 00 - 3

c. Electronic files: On flash drives.

d. Government will provide an electronic AutoCAD template.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

E. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

F. Manuals:

1. Copies:

a. Printed copies: Bound and indexed.

b. Electronic copies: pdf files or flash drives.

1) Bookmark longer files to assist in navigating file.

2. Contents:

a. Parts identification lists, lists of special tools, and accessories.

b. Schematics and wiring diagrams.

c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.

G. As-built drawings, photographs, and test records or reports if required by the specifications.

H. Sample Submittals:

1. Label with complete manufacturer's product and color identification.

2. Include type and quantity of materials specified in the referenced section in each

“set” of samples.

3. Samples: Representative of product to be installed.

4. Label each sample or sample kit with contract number and title.

01 33 00 - 4

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit sets specified in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

1. Electronic submittals:

a. In pdf form.

b. Include RSN transmittal letter.

c. Do not include Personally Identifiable Information (PII) in electronic submittals.

C. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

D. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

E. Each RSN shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.

01 33 00 - 5

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require up to 14 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of paper copy materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.

a. The time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract and,

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR

52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C. Submittal Response:

1. A response letter from the COR for each submittal will be sent to the Contractor indicating whether the submittal is approved, approved subject to identified changes, or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.

Submittals 01 33 00 - 6

1.07 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Where the recipient is the Contracting Officer, address the transmittal letter to

Bureau of Reclamation, 125 South State Street, Salt Lake City, UT, 84137-1148, Attn.: Ana Fife

a. Electronic submittals for CO shall be made to afife@usbr.gov.

2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: Joshua Dunham, Suite 221, 445 West Gunnison Avenue, Suite 221 Grand Junction, CO 81501.

a. Electronic submittals to COR shall be made to jdunham@usbr.gov thook@usbr.gov, and mbryner@usbr.gov.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used mailto:desplin@usbr.gov mailto:jdunham@usbr.gov mailto:thook@usbr.gov mailto:mbryner@usbr.gov

01 33 00 - 7

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information.

** CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.

RSN

Clause or

Section Title Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to:

CO COR

I-1 Bonds

52.228-15 Performance and Payment Bonds

Within 10 calendar days after award

A CO 1

electronic

I-2 Insurance-work on a Government Installation

(WBR 1452.228-70)

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

At least 28 days before commencing onsite work

A

CO 1

electronic

I-3 Liability Insurance

(WBR 1452.228-70)

Acceptable Certificate of Liability Insurance

Before commencement of work under the contract

A CO 1

electronic

I-4 Equal Opportunity 52.222-26

Information required by Executive Order

112246 (SF-100)

Within 30 days following award

A CO 1

electronic

I-5 Release of Claims

(WBR 1452.204-70)

Release of Claims (DI-

137) against the Government

After completion of the work and before final payment

A CO 1

electronic

I-6 Labor Standards Data 52.222-11

1) List of subcontractors

2) Statement and acknowledgement Form (SF-1413) for each subcontract

Within 14 days after award of contract

COR

1 electronic

I-7 Payrolls 52.222-08 Copies of all payrolls

Statement of Compliance

Weekly for each week of contract performance

Weekly for each week of contract performance

I

I

I-8 Schedules for Construction Contracts

(FAR 52.236-15)

Baseline Schedule Within 5 days after receipt of Notice to Proceed

I COR 1

electronic electronic

I-9 Schedules for Construction Contracts

(FAR 52.236-15)

Updated Schedule With monthly requests for progress payments, at least 28 days before onsite mobilizations, and as requested by the CO

I COR 1

electronic electronic

01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan

At least 28 days before use of Government land

I COR 1

electronic

01 33 00 - 8

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information.

** CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.

RSN

Clause or

Section Title Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to:

CO COR

01 35 10-1 Safety Data Sheets Complete LHM and

SDS

At least 14 days before jobsite delivery of hazardous material

I COR 1

electronic electronic

01 35 10-2 Safety Data Sheets Updated LHM and SDS At least 14 days before jobsite delivery of hazardous material not previously listed

I COR 1

electronic electronic

01 35 20-1 Safety and Health

WBR 1452.223-81

Safety Program Submitted and accepted at least 28 days before mobilization

A COR 1

electronic electronic

01 35 20-2 Safety and Health Certificates At least 14 days before beginning onsite work

A COR 1

electronic electronic

01 35 20-3 Safety and Health

WBR 1452.223-81

Monthly Reports Monthly I COR 1 electronic electronic

01 57 30-1 Water Pollution Control

Pollution Prevention Plan

At least 14 days before commencing construction activities

A COR 1

electronic electronic

01 57 30-2 Water Pollution Control

Spill Prevention, Control, and Countermeasure (SPCC) Plan

At least 14 days before delivery or storage of oil

A COR 1

electronic electronic

01 57 90-1 Preservation of Historical and Archeological Data

Maps showing locations of alternate staging areas, off-site borrow areas

Submitted and approved at least 45 days prior to use of staging areas, and off-site borrow areas not from commercial sources

A COR 1

electronic electronic

01 64 40-1 Government Furnished Equipment

Shortage and Damage Report

Within 24 hours after GFE inspection.

I COR 1

electronic electronic

01 71 20-1 Surveying Resumes At least 14 days before beginning survey work

I COR 1

electronic electronic

01 71 20-2 Surveying Accuracy Check Results

At least 14 days before beginning work on site.

A COR 1

electronic electronic

01 74 00-1 Cleaning and Waste Management

Certifications and Records of hazardous waste disposal (if applicable)

Within 14 days of completion of work

I COR 1

electronic electronic

01 78 30-1 Project Record Documents

Final As-Built Drawings

At least 14 days after completing the work

A COR 1

electronic electronic

03 20 00-1 Concrete Reinforcing Reinforcement Diagrams and Lists

At least 14 days before fabrication or procurement

I COR 1

electronic electronic

03 20 30-1 Grouted Anchor Bars Approval Data At least 14 days before using grout

I COR 1

electronic

01 33 00 - 9

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information.

** CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.

RSN

Clause or

Section Title Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to:

CO COR

03 20 30-2 Grouted Anchor Bars Instructions At least 14 days before using grout

I COR 1

electronic electronic 03 30 00-1 Cast-in-Place

Concrete Approval Data At least 14 days before placing concrete

A COR 1

electronic electronic 03 30 00-2 Cast-in-Place

Concrete Concrete Repair Methods

At least 14 days before placing concrete

A COR 1

electronic electronic

03 30 00-3 Cast-in-Place Concrete

Lean Concrete Grout Placement Methods

At least 14 days before placing concrete

I COR 1

electronic electronic

03 62 20-1 Nonshrink Grout for Equipment and Metalwork

Packaged Nonshrink Grout Data

At least 14 days before placing grout

I COR 1

electronic electronic

03 81 10-1 Concrete Removal Concrete Removal Plan At least 14 days before beginning work

A COR 1

electronic electronic

22 11 00-1 Facility Water Distribution

Commercial Product Data

At least 14 days before purchase/installation of equipment.

I COR 1

electronic electronic

22 16 00-1 Wash water supply system

Designer/Supplier Resume

At least 14 days before procurement

A COR 1

electronic electronic

22 16 00-2 Wash water supply system

Component Drawings At least 14 days prior to fabrication

A COR 1

electronic electronic

22 16 00-3 Wash water supply system

Installation Drawings (Stamped by PE)

At least 14 days prior to beginning fabrication of support structure components

A COR 1

electronic electronic

22 16 00-4 Wash water supply system

Commercial components/products

At least 14 days prior to purchasing components

A COR 1

electronic electronic

22 16 00-5 Wash water supply system

Electrical drawings Within 14 days of completion of work

I COR 1

electronic electronic

22 16 00-6 Wash water supply system

Operation and Maintenance instructions

Prior to shipping wash water supply system

I COR 1

electronic electronic

22 16 00-7 Wash water supply system

Factory Test Report Within 14 days of completion of work

I COR 1

electronic electronic

26 05 02-1 Basic Electrical materials and methods

Commercial product data

At least 14 days before purchase of equipment

I COR 1

electronic electronic

26 05 02-2 Basic Electrical materials and methods

Final as-built Electrical drawings

Within 14 days after completing work

I COR 1

electronic electronic

26 05 20-1 Grounding and Bonding

Test Reports Within 5 days of test completion

I COR 1

electronic electronic

26 24 24-1 Distribution panel board

Commercial product data

At least 14 days before purchase of equipment

I COR 1

electronic

01 33 00 - 10

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information.

** CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative.

RSN

Clause or

Section Title Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to:

CO COR

26 24 24-2 Distribution panel board Informational data Within 14 days after completing work

I COR 1

electronic electronic 31 03 33-1 Removal of Water from Excavation Removal of Water Plan At least 14 days before beginning excavation

I COR 1

electronic electronic 32 15 10 -1 Road Surfacing Certification and

Laboratory Results At least 14 days before installation

I COR 1

electronic electronic

33 41 10-1 Polyethylene Storm Drain

Approval data At least 14 days before purchase of equipment.

I COR 1

electronic electronic

35 22 17-1 Dual Leaf Gate Product data At least 14 days before purchase of equipment.

I COR 1

electronic electronic

35 22 17-2 Dual Leaf Gate Installation procedures At least 14 days before installation.

I COR 1

electronic electronic

35 22 17-3 Dual Leaf Gate Operation and Maintenance Service Manuals

Within 14 days after completing work

I COR 1

electronic electronic

35 22 18-1 Gate Actuators Product data At least 14 days before purchase of equipment

A COR 1

electronic electronic

35 22 18-2 Gate Actuators Final data At least 14 days before purchase of equipment

I COR 1

electronic electronic

35 22 20-1 Bifold Overshot Gate Approval data At least 14 days before purchase of equipment

A COR 1

electronic electronic

35 22 20-2 Bifold Overshot Gate Installation procedures At least 14 days before installation

I COR 1

electronic electronic

35 22 20-3 Bifold Overshot Gate Operation and Service Manuals

Within 14 days after completing work

I COR 1

electronic electronic

35 22 20-4 Bifold Overshot Gate Written Warranty Within 14 days after completing work

I COR 1

electronic electronic

35 22 20-5 Bifold Overshot Gate Final Testing Data Within 14 days after completing work

I COR 1

electronic electronic

35 69 20-1 Safety Cable with Floats

Product data At least 14 days before purchase of equipment

I COR 1

electronic

Safety Data Sheets

01 35 10 - 1

SECTION 01 35 10

SAFETY DATA SHEETS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. LHM: List of Hazardous Materials.

B. SDS: Safety Data Sheet.

1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous

Material Identifications and Material Safety Data - Alternate 1.

1.03 APPLICATION

A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data -

Alternate 1, includes:

1. Materials delivered to Government.

2. Materials incorporated into work.

3. Materials used by the Contractor during contract performance at the jobsite.

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 10-1, Complete LHM and SDS.

C. RSN 01 35 10-2, Updated LHM and SDS:

1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material

Identification and Material Safety Data - Alternate 1.

1.05 DELIVERY

A. Do not deliver hazardous materials to jobsite which are not included on original or previously updated LHM and SDS before receipt of updated LHM and SDS by COR.

Safety Data Sheets

01 35 10 - 2

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Safety and Health

01 35 20 - 1

SECTION 01 35 20

SAFETY AND HEALTH

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in the prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

2. FIST 1-1 (2012) Hazardous Energy Control Program available at:

www.usbr.gov/power/data/fist_pub.html

B. Applicable Tribal and State Safety and Health Regulations for Construction.

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 20-1, Safety Program:

1. Prepared in accordance with RSHS Section 3 and RSHS Appendix B.

2. Job specific. Generic company safety program will not be accepted.

3. Comprehensive, detailed information on safe work practices, training, engineering controls and personal protective equipment that will be used for this job.

C. RSN 01 35 20-2, Certificates:

1. CPR and First Aid training certificates for on-site supervisors and foremen.

D. RSN 01 35 20-3, Monthly reports:

1. Safety Inspection Reports:

a. List noted deficiencies, their abatement dates, and follow-up action for jobsite activities.

http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://www.usbr.gov/power/data/fist_pub.html

01 35 20 - 2

b. Base inspection report on findings of jobsite walk-through with

Government personnel.

2. Monthly summary: Form 7-2218 or other acceptable form in accordance with paragraph 3.5.8 of RSHS.

1.04 QUALIFICATIONS

A. Contractor’s Onsite Safety Representative(s):

1. Competent supervisory employee with appropriate level of safety related training and experience.

2. Holds current certificates for first aid and adult CPR.

1.05 CONTRACTOR’S ONSITE SAFETY PERSONNEL

A. Designate employee(s) as Contractor’s Onsite Safety Representative(s) prior to start of construction.

B. Contractor’s Onsite Safety Representative(s) authorities, duties, and responsibilities:

1. Review and approve Safety Program prior to submittal.

2. Implement Safety Program.

3. Full authorization to correct unsafe activity on the spot.

4. Prepare safety inspection reports.

5. At least one Contractor Onsite Safety Representative shall be onsite during construction activities.

1.06 SAFETY AND HEALTH

A. Onsite work, including mobilization, shall not begin until the COR has reviewed the

Safety Program and replied that the Safety Program is adequate for proceeding with onsite work.

B. Comply with the clause at FAR 52.236-13 - Accident Prevention, the clause at WBR

1452.223-81- Safety and Health, RSHS, local safety programs, referenced safety and health standards, and Safety Program.

1. In the event there is a conflict between requirements contained in these documents, the more stringent requirement shall prevail.

1.07 MEDICAL SERVICES AND FIRST AID

A. Provide medical services and first aid in accordance with RSHS Section 5.

B. Make facilities and services available for emergency aid to employees, subcontractor employees, and Government employees.

01 35 20 - 3

1. Provide services free of charge to Government employees injured on job.

2. Government employees not injured on job may be charged fees for rendered services based on reasonable and established fee rates.

C. Ambulance service:

1. Arrange for dependable ambulance service in accordance with RSHS, paragraph

5.5.

2. On site ambulance is not required.

3. Ambulance operators: Certified to render first aid/CPR and competent to operate vehicle.

1.08 QUALITY ASSURANCE

A. Contractor’s Onsite Safety Representative(s):

1. The effectiveness of Contractor’s Onsite Safety Representative(s) in prosecuting the safety program will be subject to continual review by the CO.

B. Safety Program:

1. The effectiveness of the Safety Program will be subject to continual review by the

CO.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 35 20 - 4

Removal from Work

01 35 21 - 1

SECTION 01 35 21

REMOVAL FROM WORK

GENERAL

REMOVAL FROM WORK

If, in the opinion of the CO, an employee refuses or repeatedly fails to comply, or supervisors fail to enforce compliance with the safety requirements contained in the

"Accident Prevention" clause and the "Safety and Health - Bureau of Reclamation" clause in Section I of this contract, the CO may require, in accordance with paragraph (c) of the "Material and Workmanship" clause in Section E, that the individual be removed from the work, and the site if necessary.

PRODUCTS

Not Used

EXECUTION

Removal from Work

01 35 21 - 2

Reference Standards

01 42 10 - 1

SECTION 01 42 10

REFERENCE STANDARDS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Referenced editions of standard specifications, codes, and manuals form a part of this specification to the extent referenced.

B. These specifications take precedence when conflicting requirements occur between specifications and referenced standard.

1.03 JOBSITE REFERENCE STANDARDS

A. Maintain at fabrication site, access to referenced standard specifications, codes, and manuals required for work in progress at fabrication site. Make available for use by the

Government.

B. Maintain onsite, access to referenced standard specifications, codes, and manuals required for onsite work in progress. Make available for use by the Government.

1.04 AVAILABILITY

A. Code of Federal Regulations (CFR):

1. Available online, authorized by the National Archives and Records

Administration (NARA) and the Government Printing Office (GPO), at http://www.gpo.gov/fdsys/search/home.action

B. Federal Specifications, Standards, and Commercial Item Descriptions; and Military

Specifications:

1. Copies of Federal Specifications, Standards, and Commercial Item Descriptions may be obtained from GSA Federal Supply Service, see the provision at FAR

52.211-1, Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29.

2. Copies of Military Specifications may be obtained from Department of Defense, see the provision at FAR 52.211-2, Availability of Specifications, Standards, and

Data Item Descriptions Listed in the Acquisition Streamlining and

Standardization Information System (ASSIST).

http://www.gpo.gov/fdsys/search/home.action

01 42 10 - 2

C. Bureau of Reclamation Documents:

1. Reclamation Safety and Health Standards (RSHS) may be downloaded at www.usbr.gov/ssle/safety/RSHS/rshs.html.

2. Bureau of Reclamation manuals and other publications including significant scientific, technical, and engineering works are available from the National

Technical Information Service (NTIS). Information regarding availability and pricing may be obtained by contacting NTIS at the following address:

United States Department of Commerce

National Technical Information Service

5285 Port Royal Road

Springfield, VA 22161

Telephone: 703-487-4650 or 1-800-553-6847

D. Industrial and Governmental Documents:

1. When a reference has a joint designation (e.g. ANSI/IEEE) these specifications generally cite the proponent organization (e.g. IEEE).

2. Addresses for obtaining industrial and governmental (other than Federal and

Bureau of Reclamation specifications and standards) specifications, standards, and codes are listed in Table 01 42 10A - Addresses for Specifications, Standards, and Codes.

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

AASHTO American Association of State Highway and

Transportation Officials

444 North Capitol Street, NW., Suite 249

Washington, DC 20001 www.aashto.org

202-624-5800

800-231-3475

ACI American Concrete Institute

38800 Country Club Dr.

Farmington Hills, MI 48331-3439 https://www.concrete.org/home.aspx”

248-848-3700

AEIC Association of Edison Illuminating Companies

PO Box 2641

Birmingham, AL 35291-0992 http://aeic.org/

205-257-3839 http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://www.aashto.org/ https://www.concrete.org/home.aspx http://aeic.org/

01 42 10 - 3

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

AGC Associated General Contractors of America

333 John Carlyle Street, Suite 200

Alexandria, VA 22314 www.agc.org

703-548-3118

AISC American Institute of Steel Construction

One East Wacker Drive, Suite 3100

Chicago, IL 60601-2001 www.aisc.org

312-670-2400

ANSI American National Standards Institute

1819 L. Street, NW.

Washington, DC 20036 www.ansi.org

202-293-8020

APA/EWA APA-The Engineered Wood Association

P.O. Box 11700

Tacoma, WA 98411-0700 www.apawood.org

253-565-6600

ASTM ASTM International

P.O. Box C700

100 Barr Harbor Drive

West Conshohocken, PA 19428-2959 www.astm.org

610-832-9585

AWS American Welding Society

550 NW LeJeune Road

Miami, FL 33126 www.amweld.org

800-443-9353

305-443-9353

ICRI International Concrete Repair Institute

1000 Westgate Drive, Suite 252 | St. Paul, Minnesota 55114 http://www.icri.org/

651-366-6095

NACE NACE International

1440 South Creek Drive

Houston, TX 77084 www.nace.org

281-228-6200

SSPC SSPC: The Society for Protective Coatings

40 24th Street, 6th Floor

Pittsburgh, PA 15222-4656 www.sspc.org

800-837-8303

412-281-2331 http://www.agc.org/ http://www.aisc.org/ http://www.ansi.org/ http://www.apawood.org/ http://www.astm.org/ http://www.amweld.org/ http://www.icri.org/ http://www.nace.org/ http://www.sspc.org/

01 42 10 - 4

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

UL Underwriters Laboratories, Inc.

333 Pfingsten Road

Northbrook, IL 60062-2096 www.ul.com

847-272-8800

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

http://www.ul.com/

Quality Procedures

01 46 00 - 1

SECTION 01 46 00

QUALITY PROCEDURES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. Government Contract Quality Assurance: (from FAR 46.101) Various functions, including inspection, performed by the Government to determine whether a contractor has fulfilled the contract obligations pertaining to quality and quantity.

B. Contractor Quality Assurance / Quality Control (QA/QC): Activities performed by the

Contractor to ensure work conforms to contract requirements.

1. The clause at FAR 52.246-12 - Inspection of Construction, requires the

Contractor to establish an inspection system to ensure quality.

2. Contractor QA/QC includes activities in addition to specified Contractor Quality

Testing to ensure work conforms to contract requirements.

C. Contractor Quality Testing: Specified tests shall be performed by the Contractor.

1. The Government will evaluate results of these tests when determining acceptability of work.

2. The Contractor may use the test results as part of Contractor QA/QC.

a. The Government anticipates that these tests will be part of the

Contractor’s QA/QC program, however the tests do not relieve the

Contractor of maintaining adequate quality system in accordance with the clause at FAR 52.246-12 - Inspection of Construction.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Quality Procedures

01 46 00 - 2

Temporary Utilities

01 51 00 - 1

SECTION 01 51 00

TEMPORARY UTILITIES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the price schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Institute of Electrical and Electronics Engineers (IEEE)

1. IEEE C2-12 National Electrical Safety Code (NESC)

1.03 TEMPORARY ELECTRICITY

A. Contractor is permitted to use the existing onsite electrical service for construction activities included in this contract.

1. The site is currently powered with 208VAC 3-phase and 110V single phase power.

B. The Contractor is responsible to provide temporary power connection, transmission lines, distribution circuits, transformers, and other electrical equipment and facilities required for obtaining power beyond what is available onsite and distributing power from existing locations to points of use.

C. Provide temporary electrical service to government trailer in accordance with specification section 01 14 10.

D. Comply with IEEE C2 clearances and spacing for temporary communications and supply lines.

1.04 TEMPORARY WATER

A. Provide water required for construction purposes.

B. Water can be purchased from Ute Water Conservancy located at 777 35-3/10 Road

Clifton, CO

C. Use water which meets specified requirements for water used in concrete, soil-cement, masonry, grouting, and other permanent work.

D. Provide means of conveying water to points of use.

Temporary Utilities

01 51 00 - 2

1.05 TELEPHONE

A. Cellular service signal is available at the site.

1.06 SANITARY FACILITIES

A. Contractor shall provide sanitary facilities.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 REMOVAL

A. Remove temporary equipment and facilities upon completion of work under this contract.

Protection of Existing Installations

01 56 10 - 1

SECTION 01 56 10

PROTECTION OF EXISTING INSTALLATIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work, except as specified.

2. Costs for repair of installations damaged by the Contractor's operations are the

Contractor's responsibility.

1.02 PROJECT CONDITIONS

A. Drawings included in these specifications show items of existing materials and equipment but may not show all equipment and materials existing at the jobsite.

B. Obtain the location of embedded conduit, pipe, cable, ground mat, and other buried items before performing any excavation, demolition, drilling or cutting of concrete.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 PROTECTION

A. Provide protection for personnel and existing facilities from harm due to the Contractor's operations. Protection shall be subject to approval of the Government.

B. Arrange protective installations to permit operation of existing equipment and facilities by the Government while work is in progress.

3.02 REMOVAL OF PROTECTIVE INSTALLATIONS

A. Remove protective installations after purpose has been served. Materials furnished by the

Contractor to provide protection remain property of the Contractor.

Protection of Existing Installations

01 56 10 - 2

3.03 REPAIR

A. Repair, at Contractor's expense, damage to existing installations due to Contractor's operations or Contractor's failure to provide proper protection. At the Government's option, damage may be repaired by the Government, and the Contractor will be back charged repair costs.

Protection of Existing Utilities

01 56 15 - 1

SECTION 01 56 15

PROTECTION OF EXISTING UTILITIES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards

B. Institute of Electrical and Electronics Engineers (IEEE)

1. IEEE C2-2012 National Electrical Safety Code (NESC)

1.03 PROJECT CONDITIONS

A. Drawings included in these specifications show some existing utilities, but do not show all utilities existing at the jobsite.

B. Prior to any excavation, contact Colorado 811, Website: www.colorado811.org.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 INTERFERENCE WITH OPERATION OR MAINTENANCE

A. Do not interfere with operation or maintenance service on utilities.

1. Provide for access to utilities in a manner satisfactory to owners and operators and the Government.

B. Provide required temporary structures; make necessary repairs, replacements, or similar operations; and furnish indemnity or other bonds.

3.02 CLEARANCES

A. Maintain clearances required for construction operations: The Contractor shall provide in accordance with RSHS.

http://www.colorado811.org/

Protection of Existing Utilities

01 56 15 - 2

Environmental Controls

01 57 20 - 1

SECTION 01 57 20

ENVIRONMENTAL CONTROLS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work, except as specified.

2. Costs for damages and work stoppage are the Contractor's responsibility.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

1.03 REGULATORY REQUIREMENTS

A. Comply with Federal, State, and local laws and regulations.

B. Comply with RSHS.

C. Conform to most stringent requirement in cases of conflict between specifications, regulatory requirements, and RSHS.

D. Contractor shall be responsible for damages resulting from dust originating from Contractor operations in accordance with clause at FAR 52.236-7, Permits and Responsibilities.

E. The CO may stop construction activity in violation of Federal, State, or local laws and additional expenses resulting from work stoppage will be responsibility of Contractor.

1.04 DUST CONTROL

A. Provide dust control and abatement during performance of work.

B. Prevent, control, and abate dust pollution on rights-of-way provided by Government or elsewhere during performance of work.

Environmental Controls

01 57 20 - 2

1.05 AIR POLLUTION CONTROL

A. Use reasonably available methods and devices to prevent, control, and otherwise minimize atmospheric emissions or discharges of air contaminants.

B. Do not operate equipment and vehicles that show excessive exhaust gas emissions until corrective repairs or adjustments reduce such emissions to acceptable levels.

1.06 NOISE CONTROL

A. Only construction activities approved by COR will be allowed during hours of 6 pm to 7 am.

1.07 LIGHT CONTROL

A. Direct stationary floodlights shall shine downward at an angle less than horizontal.

B. Shield floodlights so that floodlights will not be a nuisance to surrounding areas.

C. Direct lighting so that residences are not in direct beam of light.

D. Correct lighting control problems when they occur as approved by the COR.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Water Pollution Control

01 57 30 - 1

SECTION 01 57 30

WATER POLLUTION CONTROL

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

B. Code of Federal Regulations (CFR)

1. 40 CFR, Part 112 Oil Pollution Prevention

C. Public Law

1. Sections 311, 402, and 404 Clean Water Act (Public Law 92-500, as amended)

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 57 30-1. Pollution Prevention Plan for GVIC Fish Screen Rehabilitation:

1. As required by the stormwater permit for discharges from construction sites.

2. Include copy of 402 Wastewater Permit.

C. RSN 01 57 30-2, Spill Prevention, Control, and Countermeasure (SPCC) Plan:

1. Submit when SPCC Plan is required in accordance with 40 CFR, Part 112.

a. SPCC Plan is required where release of oil and oil products could reasonably be expected to enter into or upon navigable waters of the

United States or adjoining shorelines in quantities that may be harmful (40

CFR, Part 110), and aggregate on site oil storage capacity is over 1,320 gallons. Only containers with capacity of 55 gallons and greater are included in determining on site aggregate storage capacity.

01 57 30 - 2

2. Reviewed and certified by a registered professional engineer in accordance with

40 CFR, Part 112, as required by section 311 of the Clean Water Act (Public Law

92-500 as amended).

1.04 REGULATORY REQUIREMENTS

A. Construction Safety Standards:

1. Comply with sanitation and potable water requirements of chapter 2 of RSHS.

B. Laws, Regulations, and Permits:

1. Perform construction operations to comply, and ensure subcontractors comply, with:

a. Applicable Federal, State, and local laws, orders, regulations, and Water

Quality Standards concerning control and abatement of water pollution;

and terms and conditions of applicable permits issued by permit issuing authority.

b. If conflict occurs between Federal, State, and local laws, regulations, and requirements, the most stringent shall apply.

C. Contractor Violations:

1. If noncompliance should occur, immediately (verbally) report noncompliance to the CO. Submit specific written information within 2 days.

2. Violation of applicable Federal, State, or local laws, orders, regulations, or Water

Quality Standards may result in the CO stopping site activity until compliance is ensured.

3. The Contractor shall not be entitled to extension of time, claim for damage, or additional compensation by reason of such a work stoppage.

4. Corrective measures required to bring activities into compliance shall be at the

Contractor's expense.

1.05 REQUIRED PERMITS

A. Wastewater Discharge Permit:

1. Permit:

a. Prior to discharging wastewater or other pollutants, secure a permit to discharge pollutants as required under section 402 of the Clean Water Act

(Public Law 92-500 as amended).

2. Terms and Conditions: Comply with terms and conditions as stated in the permit.