Updated_-_01_11_00_-_Summary_of_Work_Revised_2025_01_13_0003.pdf

PDF 132 KB Posted

Attached to
GVIC FISH SCREEN REHABILITATION
Solicitation number
140R4024R0024
Issued by

About this file

This is a Summary of Work section from solicitation #140R4024R0024 for the GVIC Fish Screen Rehabilitation project issued by the Bureau of Reclamation. The work site is located in Mesa County, Colorado, south of downtown Palisade, directly downstream on the GVIC Canal from the GVIC River Gates.

The principal components include demolishing existing concrete sections and fish screens, installing new cast-in-place concrete structures, 4 bi-fold overshot gates, 1 dual leaf gate, 16 government-furnished fish screens, debris trough, conveyor system, screen control system, and debris trough pump. Additional work involves installing wash water supply system components, plumbing connections, 3 new gate actuators, and electrical/data connections. The work must be completed between November 1, 2025 (when canal dewatering begins) and April 1, 2026 (when GVIC resumes water deliveries), with final completion by May 1, 2026. Work cannot interfere with GVIC's normal operations between April-November 2025.

View the file

Other files

File Type Posted
Updated_-_35_22_18_-_Gate_Actuators_Revised_2025_01_14_0003.pdf PDF
Updated_-_01_33_00_-_Submittals_Revised_2025_01_14_0003.pdf PDF
Updated_-_26_05_33_-_Electrical_Conduit_Revised_2025_01_10_0003.pdf PDF
Updated_-_31_23_02_-_Compacting_Earth_Materials_Revised_2025_01_14_0003.pdf PDF
Updated_-_Attachment_J5_-__Past_Performance_Questionnaire_0003.pdf PDF
Sol_140R4024R0024_Amd_0003.pdf PDF
Updated_Site_Visit_Questions_2025_01_15_-_GVIC_0003.pdf PDF
Updated_-_00_01_10_-_Table_of_Contents_Revised_2025_01_14_0003.pdf PDF
Site_Visit_Agenda_GVIC_Fish_Screen_0002.pdf PDF
Site_Visit_Questions_and_Answers_-_140R4024R0024_0002.pdf PDF
Sol_140R4024R0024_Amd_0002.pdf PDF
Sign_in_Sheet_for_Site_Visit_0002.pdf PDF
Sol_140R4024R0024_Amd_0001.pdf PDF
Attachment_J7_-_SF25_Performance_Bond.pdf PDF
Attachment_J9_-_Price_Schedule_Sheet.xlsx XLSX spreadsheet
Attachment_J6_-_SF24_Bid_Bond_Form.pdf PDF
Complete_RFP_140R4024R0024_GVIC_Fish_Screen_2.pdf PDF
Attachment_J1_-_Descriptions_and_Specifications.pdf PDF
Attachment_J5_-__Past_Performance_Questionnaire.pdf PDF
Attachment_J3_-_Wage_Requirements_Determination__8_Nov_24.pdf PDF
Attachment_J2c_-_GVIC_Drawing_Package_3_of_3.pdf PDF
Attachment_J2b_-_GVIC_Drawing_Package_2_of_3.pdf PDF
Attachment_J2a_-_GVIC_Drawing_Package_1_of_3.pdf PDF
Sol_140R4024R0024.pdf PDF
Attachment_J8_-_SF25A_Payment_Bond.pdf PDF
Attachment_J4_-__Subcontractor_Percentage_Worksheet.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GVIC Fish Screen Rehabilitation Upper Colorado River Endangered Fish Recovery Program Solicitation No. 140R4024R0024

Summary of Work

01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. The work site is in Mesa County south of downtown Palisade, Colorado. The existing fish screen is directly downstream on the GVIC Canal from the GVIC River Gates.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Demolish concrete sections of existing fish return structure, bypass channel area, and adjacent slabs.

B. Place new cast-in-place concrete for fish return structure, bypass channel structure, and adjacent slabs.

C. Remove and dispose of 21 existing weld wire fish screens and screen cleaning equipment.

D. Furnish and install 4 new bi-fold overshot gates and 1 new dual leaf gate.

E. Install 16 new government furnished fish screens, debris trough, and conveyor system.

F. Install government furnished screen control system.

G. Furnish support platform and install government furnished debris trough pump.

H. Furnish and install all components of the Wash Water Supply System.

I. Furnish and install all plumbing and water control connections.

J. Furnish and install 3 new gate actuators on existing check structure gates.

K. Provide electrical service and data connections to all new components.

1.03 WORK RESTRICTIONS AND LIMITATIONS

A. Do not interfere with GVIC’s maintenance or operations in the vicinity.

B. GVIC will operate the canal and fish screen from April 1, 2025, to November 1, 2025.

Work that interferes with GVIC’s normal operations or requires dewatering of the canal may begin after November 1, 2025, when the river gates are closed.

C. On April 1st, 2026, GVIC will supply the canal with water for their deliveries. Facilities shall be able to receive water by this date.

GVIC Fish Screen Rehabilitation Upper Colorado River Endangered Fish Recovery Program Solicitation No. 140R4024R0024

Summary of Work

01 11 00 - 2

1.04 SCHEDULE

A. Construction Period: Notice to proceed date to April 1st, 2026, for substantial completion.

B. Contractor shall complete all work by May 1st, 2026.

1.05 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.06 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. GVIC: Grand Valley Irrigation Company.

2. BOR: Bureau of Reclamation

3. CO: Contracting Officer

4. COR: Contracting Officer’s Representative

5. CY: Cubic yard

6. LF: Linear Foot

1.07 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION