Site_Visit_Questions_and_Answers_-_140R4024R0024_0002.pdf

PDF 139 KB Posted

Attached to
GVIC FISH SCREEN REHABILITATION
Solicitation number
140R4024R0024
Issued by

About this file

This is a Questions and Answers document from a site visit for Solicitation 140R4024R0024, GVIC Fish Screen Rehabilitation project, dated December 18, 2024. The document addresses two key questions regarding equipment delivery and staffing requirements.

The responses clarify that various Government-Furnished Equipment (GFE) will be delivered in phases: CCS panels and enclosures are already stored at the work site; traveling screens are undergoing final inspections and expected on-site by award time; debris trough and conveyor will be delivered after award but before Notice to Proceed; and GFE spare parts will arrive with associated equipment. Regarding staffing, at least one Contractor Onsite Safety Representative must be present during construction activities, though this role can be performed by the Onsite Project Superintendent. While a full-time quality control representative is not required, the contractor must establish an inspection system to ensure quality per Specification Section 01 46 00 and FAR Clause 52.246-12.

View the file

Other files

File Type Posted
Updated_-_35_22_18_-_Gate_Actuators_Revised_2025_01_14_0003.pdf PDF
Updated_-_01_33_00_-_Submittals_Revised_2025_01_14_0003.pdf PDF
Updated_-_26_05_33_-_Electrical_Conduit_Revised_2025_01_10_0003.pdf PDF
Updated_-_01_11_00_-_Summary_of_Work_Revised_2025_01_13_0003.pdf PDF
Updated_-_31_23_02_-_Compacting_Earth_Materials_Revised_2025_01_14_0003.pdf PDF
Updated_-_Attachment_J5_-__Past_Performance_Questionnaire_0003.pdf PDF
Sol_140R4024R0024_Amd_0003.pdf PDF
Updated_Site_Visit_Questions_2025_01_15_-_GVIC_0003.pdf PDF
Updated_-_00_01_10_-_Table_of_Contents_Revised_2025_01_14_0003.pdf PDF
Site_Visit_Agenda_GVIC_Fish_Screen_0002.pdf PDF
Sol_140R4024R0024_Amd_0002.pdf PDF
Sign_in_Sheet_for_Site_Visit_0002.pdf PDF
Sol_140R4024R0024_Amd_0001.pdf PDF
Attachment_J7_-_SF25_Performance_Bond.pdf PDF
Attachment_J9_-_Price_Schedule_Sheet.xlsx XLSX spreadsheet
Attachment_J6_-_SF24_Bid_Bond_Form.pdf PDF
Complete_RFP_140R4024R0024_GVIC_Fish_Screen_2.pdf PDF
Attachment_J1_-_Descriptions_and_Specifications.pdf PDF
Attachment_J5_-__Past_Performance_Questionnaire.pdf PDF
Attachment_J3_-_Wage_Requirements_Determination__8_Nov_24.pdf PDF
Attachment_J2c_-_GVIC_Drawing_Package_3_of_3.pdf PDF
Attachment_J2b_-_GVIC_Drawing_Package_2_of_3.pdf PDF
Attachment_J2a_-_GVIC_Drawing_Package_1_of_3.pdf PDF
Sol_140R4024R0024.pdf PDF
Attachment_J8_-_SF25A_Payment_Bond.pdf PDF
Attachment_J4_-__Subcontractor_Percentage_Worksheet.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GVIC Fish Screen Rehabilitation

Solicitation 140R4024R0024

Site Visit Questions – 18 December 2024

Question #1 - When does Reclamation expect delivery of the traveling screens?

Answer #1 -

a. See Specification Section 01 64 40 – Government-Furnished Equipment (GFE) for the list of GFE and associated storage, protection, and reporting requirements.

b. The CCS panels and enclosures (Items 6, 7, 8) have been delivered and are stored at the work site.

c. The traveling screens (Items 1, 2, 9) are undergoing their final inspections and are expected to be on-site by the time of Award.

d. The debris trough and conveyor (Items 3, 4, 5) are being fabricated and are expected to be delivered after award but before Notice to Proceed is issued.

e. The GFE Spare Parts will be delivered with the associated equipment.

Question #2 - Is a Full-Time Safety individual or a Full-Time QC person expected or required?

Answer #2 - Yes, Specification Section 01 35 20 – Safety and Health, Paragraph 1.05 B.

5. states “At least one Contractor Onsite Safety Representative shall be onsite during construction activities”. There is no restriction against the contractors Onsite Project

Superintendent serving collateral duty as the Contractor Onsite Safety Representative.

The specifications do not require the contractor to provide a full-time onsite quality control representative. However, Specification Section 01 46 00 – Quality Procedures and

Far Clause 52.246-12 – Inspection of Construction require the Contractor to establish an inspection system to ensure quality.

File details come from the government source that posted it. Updated .