This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for contract CN200 with George F. Young, Inc. The change order pertains to Task Assignment No. 08 for the Little Manatee River State Park Campground Bathhouse project (Project No. 60993). The consultant representative is Stuart Cullen, and the FDEP Contract Manager is Adam Browne. The change order was approved by multiple FDEP officials including Greg Turral (Budget Representative), Laura Ross (Project Manager), Adam Browne (Contract Manager), and Stuart Cullen (Consultant), with signatures dated between June 27, 2018 and July 12, 2018.
This is a no-cost time extension that allows the consultant to complete construction administration components of the task assignment. The original task amount of $68,914.08 (consisting of $3,220.00 in reimbursement and $65,694.08 in fixed fee) remains unchanged with no increase or decrease in this change order. The original task execution date was May 24, 2017, with an original end date of August 1, 2018. This change order extends the task end date by 365 days to August 1, 2019, enabling George F. Young, Inc. to provide construction administrative services through project closeout following the selection of a construction contractor.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Browne, Adam
From: Cullen, Stuart <scullen@georgefyoung.com> Sent: Tuesday, June 26, 2018 13:46 To: Ross, Laura S.
Subject: Little Manatee River - Task Assignment Extension
Follow Up Flag: Follow up Flag Status: Completed
Laura, The Task Assignment for the above referenced project expires on 8/1/2018. We have recently completed the design tasks, and it is my understanding that a contractor has been selected. As our contract includes Construction Administrative services, we respectfully request an extension to 8/1/2019 to encompass the construction phase and close out of this project.
Thanks, Stuart Cullen, PE Vice President, Engineering, LEED Green Associate
George F. Young, Inc.
1905 South Main Street Gainesville, FL 32601 Phone:352‐378‐1444 Cell:352‐318‐9461 Check out our new Web Site!
www.georgefyoung.com
PRIVACY/CONFIDENTIALITY NOTICE:
This message contains private, confidential, or legally privileged information and is intended for the recipient ONLY. If you are not the intended recipient or have received this e‐mail in error, please notify postmaster@georgefyoung.com immediately by return e‐mail or phone and delete all copies of this e‐mail, including all attachments without reading them or saving to any storage device. If you are the intended recipient(s) you will need to secure the contents conforming to all applicable state and/or federal requirements relating to the privacy and confidentiality of such information. E‐mail transmission cannot be guaranteed to be secure or error‐free as information could be intercepted, corrupted, lost, destroyed, arrive late or incomplete, or contain viruses. The sender and George F. Young, Inc. therefore do not accept liability for any errors or omissions in the contents of this message, which arise as a result of e‐mail transmission. If verification is required please request a hard‐copy version.
File details come from the government source that posted it. Updated .