This document is a Task Assignment Change Order Form (Change Order No. CO2) issued by the Florida Department of Environmental Protection (FDEP) for FDEP Contract No. CN200. The change order involves the consultant George F. Young, Inc., represented by Stuart Cullen, for work on the A1A Turn Lanes project located at Gamble Rogers. The FDEP Contract Manager is Mae Roth. The change order was approved by multiple FDEP officials including Budget Representative Diane Langston, Project Manager Brian Miller, and Contract Manager Mae Roth, with authorization from Contract Authority Michael W. Foster Jr., P.E. All signatures were obtained between July 20-22, 2016.
The change order extends the original task assignment period by 155 days to accommodate additional permitting and scope requirements, as well as construction administration services. The original task execution date was July 30, 2015, with an original end date of March 31, 2016. The new task end date is December 31, 2016. The change order contains no additional cost to the project, with all work coordinated through other efforts. The original fixed fee task amount of $32,037.56 remains unchanged, with total amounts across all change orders equaling $50,896.68 in reimbursement and $49,896.68 in fixed fees, for a combined total of $50,896.68.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .