This is a Task Assignment Notification Form and associated proposal for professional engineering and surveying services issued by the Florida Department of Environmental Protection (FDEP) under Contract CN200, Task Assignment No. 16. The contract is between FDEP and George F. Young, Inc., a consulting engineering firm, for the Paynes Prairie State Preserve pavement rehabilitation project located in Alachua County, Florida. The project manager for FDEP is Terry McCullum, Jr., and the consultant representative is Jonathan Langston, P.E. Additional services are provided by subcontractors GSE Engineering and Consulting for geotechnical investigations.

The scope of work consists of seven subtasks encompassing survey, geotechnical engineering, design development at 60%, 90%, and 100% completion levels, permitting coordination with the St. Johns River Water Management District, Florida Department of Transportation, and Alachua County, and construction administration services. Specific deliverables include topographic survey with CAD files, geotechnical reports including pavement cores and culvert site investigations, design plans with opinions of probable cost utilizing FDOT historical cost data, and permitting documentation. The contract establishes a fixed price cost of $184,351.00 and reimbursable costs not to exceed $1,350.00, for a total task amount of $185,701.00. Payment is made upon FDEP approval of deliverables for each subtask. The project schedule extends approximately 238 days through permit approvals, with construction administration services limited to no more than 84 days and 80 hours following 100% plan approval. The completion date is June 30, 2024.

View the file

Other files

File Type Posted
CN-370000-CN200-CMC3.pdf PDF
CN-370000-CN200-CMC4.pdf PDF
CN-370000-CN200-T12.pdf PDF
CN-370000-CN200-T14CO2.pdf PDF
CN-370000-CN200-T15.pdf PDF
CN-370000-CN200-T22CO1.pdf PDF
CN-370000-CN200-T27.pdf PDF
CN-370000-CN200-T3CO4.pdf PDF
CN-370000-CN200-T5.pdf PDF
CN-370000-CN200-TA14CO1.pdf PDF
CN-370000-CN200-A1.pdf PDF
CN-370000-CN200-CMC2.pdf PDF
CN-370000-CN200-T13.pdf PDF
CN-370000-CN200-T19.pdf PDF
CN-370000-CN200-T21.pdf PDF
CN-370000-CN200-T27CO1.pdf PDF
CN-370000-CN200-T3CO1.pdf PDF
CN-370000-CN200-T3CO3.pdf PDF
CN-370000-CN200-T4.pdf PDF
CN-370000-CN200-T5CO1.pdf PDF
CN-370000-CN200-T7.pdf PDF
CN-370000-CN200-TA2.pdf PDF
CN-370000-CN200.pdf PDF
CN-370000-CN200-CMC1.pdf PDF
CN-370000-CN200-CMC5.pdf PDF
CN-370000-CN200-T10.pdf PDF
CN-370000-CN200-T11.pdf PDF
CN-370000-CN200-T12CO3.pdf PDF
CN-370000-CN200-T14.pdf PDF
CN-370000-CN200-T14CO2.pdf.crdownload CRDOWNLOAD file
CN-370000-CN200-T19CO1.pdf PDF
CN-370000-CN200-T28.pdf PDF
CN-370000-CN200-T29.pdf PDF
CN-370000-CN200-T2CO1.pdf PDF
CN-370000-CN200-T2CO7.pdf PDF
CN-370000-CN200-T6.pdf PDF
CN-370000-CN200-T8.pdf PDF
CN-370000-GC923.pdf PDF
CN-370000-CN200-T12CO2.pdf PDF
CN-370000-CN200-T17.pdf PDF
CN-370000-CN200-T18.pdf PDF
CN-370000-CN200-T22.pdf PDF
CN-370000-CN200-T23.pdf PDF
CN-370000-CN200-T25.pdf PDF
CN-370000-CN200-T26.pdf PDF
CN-370000-CN200-T2C02.pdf PDF
CN-370000-CN200-T2CO4.pdf PDF
CN-370000-CN200-T2CO5.pdf PDF
CN-370000-CN200-T3CO2.pdf PDF
CN-370000-CN200-T4CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN200 16 FDEP 61471C

Paynes Prairie State Preserve Repave Entrance Road

George F. Young, Inc.

Jonathan Langston, P.E. (727) 822-4317 jlangston@georgefyoung.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Consultant is to provide design and permit documents for pavement rehabilitation of the main park road, campground loop road, visitors' center parking lot and boat ramp parking lot and Puggy road overflow parking, per attached proposal dated February 7, 2023.

Terry McCullum, Jr. or successor

Upon Execution $ 184,351.00 06/30/2024 $ 1,350.00

$ 185,701.00

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.07 13:39:24 -05'00'

Terry McCullum, Jr. Terry McCullum, Jr.

Digitally signed by Terry McCullum, Jr.

Date: 2023.02.07 14:20:00 -05'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.08 09:01:39 -05'00'

Jonathan Langston, P.E. Jonathan C Langston Digitally signed by Jonathan C Langston Date: 2023.02.08 14:32:05 -05'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.02.17 14:18:52 -05'00'

61471C 37502000092 080039/23 423001 U3200 131500 QK $ 185,701.00

$ 185,701.00 integrity | quality | service

February 7, 2023

Terry L McCullum Jr.

Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399

RE: CN200 TA16– George F. Young

Paynes Prairie State Preserve – Pavement Rehabilitation

Dear Mr. McCullum, For your review, George F. Young Inc. has provided a proposal summary and man‐hour documentation for professional surveying and engineering services for the pavement rehabilitation project through the Paynes Prairie State Preserve, purposed to extend the service life of the roadway and provide solutions to specific areas of base and pavement distress.

This scope reflects our previous meeting held on November 9, 2022, our understanding of the project, our research efforts, and the information provided. We trust the information contained in the attached proposal is consistent with your understanding.

Please review the attached Proposal Summary. We appreciate the opportunity to be of service to you on this project and look forward to working with you. Please feel free to contact me if you should have any questions or require any changes.

Sincerely, Jonathan Langston, PE Project Manager

Pavement Rehabilitation

Paynes Prairie State Preserve

DEP Agreement Number CN200, Task Assignment Number 16

Subtask 1: Survey

Description: GFY proposes to perform a detailed topographic survey including cross sections every 100‐ ft, a surface 3D model and traditional topo survey of the existing ground to include three shots, (one centerline, and each side edge of pavement). Trees within the limits of parking loops or within the limits of the unpaved shoulder (approximately 2’ outside the edge of pavement) will also be identified. Lastly, the handicap spaces in the Picnic/Boat Ramp parking loop will have additional elevation shots to aid in design necessary to meet ADA slope compliance and potential for sidewalk addition behind the handicap parking stalls.

Survey ‐ Paynes Prairie State Preserve Roadway

Includes mainline roadway limits from the Park Entrance off US‐441 South to the termination of

Savanah Blvd at the Alachua Savannah Visitor Center & Tower Parking Lot.

Also included in the “Mainline Roadway” is Puggy Road, located off Savannah Blvd running west terminating at the Puc Puggy Campground and Boat Ramp/Picnic Area.

Additional areas such as parking lots and campground areas are also included. Each of these additional areas described below are to be completed under the same effort and timeframe as the “mainline”.

Gate and Administrative Parking Area

Puggy Road Parking Loop

Puggy Road Campground Loop

Puggy Road Lakeside Parking Lot (boat ramp excluded)

Alachua Savannah Visitor Center & Tower Parking Lot

Deliverable: Survey deliverables will include an electronically signed and sealed topographic survey on 11x17 or 24x36 sheets in pdf format and .dwg CAD files. Paper copies can be provided upon request.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost: Manhour Summary

Total for Subtask 1: $40,230.90

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

George F. Young Professional Surveyor & Mapper (Surveyor Manager) $105.00 125.08 $13,133.40 George F. Young Field Crew (2-Person) $70.59 250.00 $17,647.50 George F. Young CADD Technician $63.00 150.00 $9,450.00 Fee $40,230.90

Subtask 1: Survey

Subtask 2: Geotechnical Engineering Description: Geotechnical Coordination and Evaluation is provided in the scope to aid in design. Pavement cores are being proposed to assist in evaluating the existing structural number and ensure our resurfacing plan will provide adequate strength and longevity of the proposed design. We also recommend additional hand auger borings to estimate the seasonal high ground water table (SHGWT) and ensure areas of significant pavement distress are not the result of a perched water table. The geotechnical data will be obtained at the time of the survey phase.

Additionally, geotechnical investigation around the proposed culvert replacement has been provided in

Subtask 2B. This will ensure the necessary information is gathered for structural design of the in‐kind pipe culvert replacement.

Subtask 2A: Geotechnical Report Pavement ‐ Pavement Cores

Clear utilities at the site through Sunshine One Call.

Provide Maintenance of Traffic (MOT). MOT will include signage and cones. Since it is a lightly trafficked roadway, we anticipate one flagman will be sufficient.

Mobilize to the site with coring equipment.

Advance fourteen (14) cores through the asphalt wearing surface, limerock base course and stabilized subgrade (if present) to determine their thicknesses. We will patch the cores with cold patch asphalt. You should consider the patches to be temporary.

Advance seven (7) auger borings to depths of 5 feet depth. The auger borings will be performed at locations to provide anticipated seasonal high groundwater levels spread across the site.

Develop a Geotechnical Pavement Report documenting the following:

o Existing site conditions.

o Exploration, testing and sampling methods.

o A tabulation of the coring results.

o Auger boring logs and estimates for the seasonal high groundwater table.

o Preliminary recommendations for milling and resurfacing and preliminary recommendations for pavement design. If detailed information regarding the average daily traffic (ADT), ESALs, serviceability, design life, etc. can be provided a more detailed pavement design can be provided.

Deliverable 2A: The results of the exploration will be presented in electronically provided geotechnical engineering report in PDF format.

Performance Measure 2A: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost 2A:

Firm Name Position Classification Unit Rate Units Unit Type

Total Fixed Price Cost

GSE Engineering and Consulting Principal Engineer $132.69 3.81 Hours $505.55 GSE Engineering and Consulting Engineer Intern $88.95 3.35 Hours $297.98 GSE Engineering and Consulting CADD/Computer Tech $69.00 4.35 Hours $300.15 GSE Engineering and Consulting Technical Secretary $63.47 2.37 Hours $150.42 GSE Engineering and Consulting Materials and Testing $3,445.00 1.00 Each $3,445.00 Fee

Subtask 2A: Geotechnical Pavement Investigation

$4,699.11

2B: Geotechnical Investigation at Culvert Replacement Location

Clear utilities at the site through Sunshine One Call.

Provide Maintenance of Traffic (MOT) consisting of flagmen, signs and cones. We anticipate FDOT Index 102‐603 will be utilized.

Mobilize to the site with limited access drilling equipment.

Perform two (2) Standard Penetration Test (SPT) borings to a depth of 30 feet bls in accessible areas.

Collect one (1) soil samples for corrosion series testing.

Upon completion of the field testing, we will backfill the boreholes with the soil cuttings and/or grout.

Perform visual classification of the soil samples obtained from the soil borings to confirm field classifications.

Perform soil laboratory classification tests on representative samples, as considered appropriate.

These tests may include the percent passing the No. 200 sieve, natural moisture content, corrosion series, organic content, and Atterberg Limits tests.

Develop a Geotechnical Investigation Report at the Culvert Replacement Location documenting the following:

o Existing site conditions.

o Exploration, testing and sampling methods.

o Subsurface soil conditions encountered and Unified soil classifications, including any unsuitable materials encountered.

o Depth to groundwater at the time of the exploration and estimated seasonal high, if encountered.

o Box culvert expansion recommendations.

Deliverable 2B: The results of the exploration will be presented in electronically provided geotechnical engineering report in PDF format.

Performance Measure 2B: Deliverables will be reviewed by the Department to confirm they are

Fixed Price Cost 2B:

Total for Subtask 2: $11,637.20

Subtask 2B: Geotechnical Culvert Investigation Firm Name Position Classification Unit Rate Units Unit

Type Total Fixed Price Cost

GSE Engineering and Consulting MAT Principal Engineer $132.69 3.67 Hours $486.97 GSE Engineering and Consulting MAT Engineer Intern $88.95 11.83 Hours $1,052.28 GSE Engineering and Consulting MAT CADD/Computer Technician $69.00 5.65 Hours $389.85 GSE Engineering and Consulting MAT Technical Secretary $63.47 2.90 Hours $184.06 GSE Engineering and Consulting 419-Geo Drilling Crew (2-person EI Rate) $177.90 2.13 Hours $378.93 GSE Engineering and Consulting Materials and Testing $4,446.00 1.00 Each $4,446.00 Fee $6,938.09

Subtask 3: 60% Plans Subtask 3A: 60% Roadway Plans: Limits of roadway design are from the Park Entrance off US‐441 South to the termination of Savanah Blvd at the Alachua Savannah Visitor Center & Tower Parking Lot. Also included is Puggy Road, located off Savannah Blvd running west terminating at the Puc Puggy Campground and Boat Ramp/Picnic Area. Additional areas such as parking lots and campground areas are also included.

Each of these additional areas described below are to be designed within the same timeframe and plans set as the “mainline” work.

Gate and Administrative Parking Area

Puggy Road Parking Loop

Puggy Road Campground Loop

Puggy Road Lakeside Parking Lot (boat ramp excluded)

Alachua Savannah Visitor Center & Tower Parking Lot

Roadway plans will include a best fit alignment, detailed resurfacing typical sections, plan sheets, and cross sections as need for construction documents. Roadway plans will include an Opinion of Probable Cost at 60% utilizing FDOT Historical Costs.

Civil Engineering services shall include construction documents with two (2) pavement designs to include a standard milling and resurfacing (in‐kind) and reconstruction options.

There are no stormwater concerns at this time as impervious areas are not anticipated to increase for this maintenance related scope of work. Note that the proposed culvert, weir, and headwall replacement is to replace “in‐kind”. Should the culvert be replaced with something different from the existing condition, additional stormwater, watershed modelling, and design efforts could become necessary and is not currently included in this scope of work.

This scope of services is limited to the maintenance of the pavement structure within Paynes Prairie Preserve State Park; efforts to alleviate ADA issues within the park limits are limited to the known area of the handicap parking stalls at the Boat Ramp and Picnic Area Parking Lot near the restrooms.

The 60% roadway submittal will contain, the title, general notes, existing conditions, roadway alignment and project overview sheets, typical sections, and summary of quantities.

Deliverable 3A: A 60% roadway plan set will be submitted electronically via a signed and sealed 11x17 pdf plan set including an opinion of probable cost.

Performance Measure 3A: Deliverables will be reviewed by the Department to confirm they are complete, Fixed Price Cost 3A:

Price Cost

George F. Young Contract Mgr. Civil EOR $130.41 121.00 $15,779.61 George F. Young Project Engineer $93.16 104.00 $9,688.64 George F. Young Senior CADD Technician $78.00 120.00 $9,360.00 George F. Young CADD Technician $63.00 164.00 $10,332.00 Fee

Subtask 3A: Roadway Design - 60%

$45,160.25

Subtask 3B: 60% Structural Plans: It is understood the Department is considering in‐kind replacement of one culvert of unknown length, necessary headwalls, and inflow/outfall structure. See subtasks 3B, 4B, and 5B for structural engineering fees regarding pipe culvert and headwall replacement up to 60’ in length.

Should the replacement exceed these assumptions additional services could apply.

Deliverable 3B: A 60% structural supplemental plan set will be submitted electronically via a signed and sealed 11x17 pdf plan set.

Performance Measure 3B: Deliverables will be reviewed by the Department to confirm they are complete, Fixed Price Cost 3B:

Total for Subtask 3: $48,327.22

George F. Young Contract Mgr. Civil EOR $130.41 9.00 $1,173.69 George F. Young Project Engineer $93.16 8.00 $745.28 George F. Young Senior CADD Technician $78.00 16.00 $1,248.00 George F. Young CADD Technician $63.00 $0.00 Fee

Subtask 3B: Structural Design - 60%

$3,166.97

Subtask 4: Permitting Description: Anticipated permitting tasks are outlined below for the Florida Department of Transportation

(FDOT), Saint John’s River Water Management District (SJRWMD), and Alachua County. Pre‐application meetings will be scheduled by George F. Young upon project commencement.

Note, no permitting is included for the culvert replacement and is not expected since it is to be replaced in‐kind. Please note that the culvert replacement does not include any permitting services related to stormwater design, stormwater modelling or flow analysis. Should any permitting services be required beyond FDEP approval, for example with the Water Management District or County relating to the culvert replacement, additional design/permitting scope and fees will be handled in an addendum.

Subtask 4A: St. Johns River Water Management District

Expected De‐Minimus Exception.

Additional permitting/watershed modelling, or drainage related tasks beyond a de‐minimus exception is not anticipated and is excluded.

Deliverable 4A: The permitting deliverables will be provided by the SJRWMD in their format and forwarded to FDEP in pdf format.

Performance Measure 4A: Deliverables will be reviewed by the Department to confirm they are

Fixed Price Cost 4A:

Reimbursable Cost 4A:

SJRWMD: De‐Minimus $400.00*

Postage $25.00

Printing 30‐40 pages ($25.00 estimate)

Overnight Travel N/A

Mileage (@ $0.445 per mile) N/A

Reimbursable Total Cost $450

Subtask 4B: Florida Department of Transportation

Complete a pre‐application meeting to verify only a General Use Permit is required. A General

Use Permit is included with this scope of work. As is understood with the on‐site improvements, the contractor is to provide Maintenance of Traffic (MOT) Plans. MOT Plans are not included in this scope and fee.

Deliverable 4B: The permitting deliverables will be provided by the FDOT in their format and forwarded to FDEP in pdf format.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

George F. Young Contract Mgr. Civil EOR $130.41 16.00 $2,086.56 George F. Young Project Engineer $93.16 24.00 $2,235.84 Fee

Subtask 4A: St. Johns River Water Management District

$4,322.40

Performance Measure 4B: Deliverables will be reviewed by the Department to confirm they are

Fixed Price Cost 4B:

Reimbursable Cost 4B:

FDOT: General Use $400.00*

Postage $25.00

Printing 30‐40 pages ($25.00 estimate)

Overnight Travel N/A

Mileage (@ $0.445 per mile) N/A

Reimbursable Total Cost $450

Subtask 4C: Alachua County

Will complete a pre‐application meeting to verify permitting requirements. It is assumed the equivalent of a general use or erosion control permit may be required for the culvert replacement.

Should this permit not be required, no fees will be apply.

Deliverable 4C: The permitting deliverables will be provided by the County in their format and forwarded to FDEP in pdf format.

Performance Measure 4C: Deliverables will be reviewed by the Department to confirm they are

Fixed Price Cost 4C:

Reimbursable Cost 4C:

FDOT: General Use $400.00*

Postage $25.00

Printing 30‐40 pages ($25.00 estimate)

Overnight Travel N/A

Mileage (@ $0.445 per mile) N/A

Reimbursable Total Cost $450

Total for Subtask 4: $13,422.92

*permit fees are an estimate

George F. Young Contract Mgr. Civil EOR $130.41 16.00 $2,086.56 George F. Young Project Engineer $93.16 24.00 $2,235.84 Fee

Subtask 4B: Florida Department of Transportation

$4,322.40

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

George F. Young Contract Mgr. Civil EOR $130.41 12.00 $1,564.92 George F. Young Project Engineer $93.16 20.00 $1,863.20 Fee $3,428.12

Subtask 4C: Alachua County

Subtask 5: – 90% Plans Subtask 5A: 90% Roadway Plans Description: Please refer to the description outlined in Subtask 3 for the overall engineering description.

90% plans will refine limits of reconstruction where necessary as well as provide details, refined/updated site/grading plan to address the ADA concern in the boat ramp/picnic area parking lots, and a re‐striping plan (to match existing condition) for the parking lots.

Deliverable 5A: A 90% roadway plan set will be submitted electronically via a signed and sealed 11x17 pdf plan set within 2 months of receipt of 60% plans FDEP comments with the appropriate revisions.

Performance Measure 5A: Deliverables will be reviewed by the Department to confirm they are complete, Fixed Price Cost 5A:

Subtask 5B: 90% Structural Plans Description: 90% plans will incorporate any necessary revisions from permitting agency comments as well as any additional details and plan refinements/updates.

Deliverable 5B: A 90% structural plan set will be submitted electronically via a signed and sealed 11x17 supplemental pdf plan set within 2 months of receipt of 60% plans FDEP comments with the appropriate revisions.

Performance Measure 5B: Deliverables will be reviewed by the Department to confirm they are complete, Fixed Price Cost 5B:

Total for Subtask 5: $30,341.14

George F. Young Contract Mgr. Civil EOR $130.41 57.00 $7,433.37 George F. Young Project Engineer $93.16 80.00 $7,452.80 George F. Young Senior CADD Technician $78.00 88.00 $6,864.00 George F. Young CADD Technician $63.00 96.00 $6,048.00 Fee

Subtask 5A: Roadway Design - 90%

$27,798.17

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

George F. Young Contract Mgr. Civil EOR $130.41 9.00 $1,173.69 George F. Young Project Engineer $93.16 8.00 $745.28 George F. Young Senior CADD Technician $78.00 8.00 $624.00 George F. Young CADD Technician $63.00 0.00 $0.00 Fee

Subtask 5B: Structural Design - 90%

$2,542.97

Subtask 6: 100% Plans Subtask 6A: 100% Roadway Plans

Description: Please refer to the description outlined in Subtask 3 for the overall engineering description.

100% plans will incorporate last comments, refined details, any detailed plans sheets necessary for constructability concerns, and specifications package. Roadway plans will include an Opinion of Probable Cost at 100% utilizing FDOT Historical Costs.

Deliverable 6A: A 100% roadway plan set and Specifications Package will be submitted electronically via a signed and sealed 11x17 pdf plan set within 90 days of receipt of 90% plans FDEP comments with appropriate revisions made. All relevant .dwg CAD files will be sent with the 100% submittal.

Performance Measure 6A: Deliverables will be reviewed by the Department to confirm they are complete, Fixed Price Cost 6A:

Subtask 6B: 100% Structural Plans Description 6B: 100% plans will incorporate any necessary revisions from permitting agency comments as well as any additional details and plan refinements/updates.

Deliverable 6B: A 100% structural supplemental plan set and Specifications Package will be submitted electronically via a signed and sealed 11x17 pdf plan set within 90 days of receipt of 90% plans FDEP comments with appropriate revisions made. All relevant .dwg CAD files will be sent with the 100% submittal.

Performance Measure 6B: Deliverables will be reviewed by the Department to confirm they are complete, Fixed Price Cost 6B:

Total for Subtask 6: $28,364.88

George F. Young Contract Mgr. Civil EOR $130.41 64.00 $8,346.24 George F. Young Project Engineer $93.16 80.00 $7,452.80 George F. Young Senior CADD Technician $78.00 56.00 $4,368.00 George F. Young CADD Technician $63.00 80.00 $5,040.00 Fee

Subtask 6A: Roadway Design - 100% and Specifications Package

$25,207.04

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

George F. Young Contract Mgr. Civil EOR $130.41 8.00 $1,043.28 George F. Young Project Engineer $93.16 16.00 $1,490.56 George F. Young Senior CADD Technician $78.00 8.00 $624.00 George F. Young CADD Technician $63.00 0.00 $0.00 Fee

Subtask 6B: Structural - 100% and Specifications Package

$3,157.84

Subtask 7: Construction Administration Services Description: Construction Administration Services are outlined below in two subphases; bidding assistance and construction phase services.

Subtask 7A ‐ Bidding Assistance: Bidding assistance will be provided through responding to RFI’s and attendance at one pre‐construction meeting.

Deliverable 7A: To be provided in correspondence with the FDEP representatives via phone calls, carbon copied email correspondence with outside entities, i.e. contractor. A correspondence log will be updated upon coordination tasks and submitted to FDEP in a pdf format.

Performance Measure 7A: Deliverables will be reviewed by the Department to confirm they are

Fixed Price Cost 7A:

Subtask 7B – Substantial Completion: Substantial Completion tasks will be provided and is limited to answering RFI’s and one on‐site visit. No materials testing or CEI is included in this scope or fee.

Deliverable 7B: To be provided in correspondence with the FDEP representatives via phone calls, carbon copied email correspondence with outside entities, i.e. contractor. A correspondence log will be updated upon coordination tasks and submitted to FDEP in a pdf format.

Performance Measure 7B: Deliverables will be reviewed by the Department to confirm they are

Fixed Price Cost 7B:

Total for Subtask 7: $13,376.74

George F. Young Contract Mgr. Civil EOR $130.41 25.00 $3,260.25 George F. Young Project Engineer $93.16 16.00 $1,490.56 Fee

Subtask 7A: Bidding Assistance

$4,750.81

Firm Name Position Classification Hourly Rate Hours Total Fixed George F. Young Contract Mgr. Civil EOR $130.41 49.00 $6,390.09 George F. Young Project Engineer $93.16 24.00 $2,235.84 Fee

Subtask 7B: Substantial Completion

$8,625.93

Project Schedule:

Note, time frames are approximate and often depend on agency review timeframe for turnaround.

Activity Duration (Calendar Days)

Subtask 1 70 days

Subtask 2 42 days

Subtask 3: 60% Plans 126 days (8 weeks from Subtask 1A/1B & 2 completion)

Subtask 4: Permit Applications 154 days (Upon Subtask 3 FDEP conditional approval / review / necessary edits)

Subtask 5: 90% Plans 168 days (allows 2 weeks of Subtask 3 FDEP review, 4 weeks for GFY turnaround)

Subtask 6: 100% Plans / Specifications Package

210 days (allows 2 weeks of Subtask 5 FDEP review, 4 weeks for GFY turnaround)

Subtask 4: Permit Approvals 238 days (anticipated 12 weeks from permit application date)

Subtask 7: Construction Administration Services

No more than 84 days from 100% plan approval (Not to exceed 80 hours).

Summary of Fees:

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

Subtask 1: Survey 40,230.90$ ‐$ 40,230.90$

Subtask 2A: Geotech (Pav't) 4,699.11$ ‐$ Subtask 2B: Geotech (Culvert) 6,938.09$ ‐$

11,637.20$

Subtask 3A: Roadway (60%) 45,160.25$ ‐$ Subtask 3B: Structural (60%) 3,166.97$ ‐$

48,327.22$

Subtask 4A: Permitting (FDOT) 4,322.40$ 450.00$

Subtask 4B: Permitting (SJRWMD) 4,322.40$ 450.00$

Subtask 4C: Permitting (County) 3,428.12$ 450.00$

Subtask 4: Permitting Subtotal

Subtask 5A: Roadway (90%) 27,798.17$ ‐$ Subtask 5B: Structures (90%) 2,542.97$ ‐$

30,341.14$

Subtask 6A: Roadway (100%) 25,207.04$ ‐$ Subtask 6B: Structures (100%) 3,157.84$ ‐$

28,364.88$

Subtask 7A: Const. Bidding Ast. 4,750.81$ ‐$ Subtask 7B: Substantial Completion 8,625.93$ ‐$

Subtask 7: Const. Adm. Subtotal

Total Fixed Price Cost

Total Reimbursable Cost

Overall Total Cost

$184,351.00

$1,350.00

$185,701.00

13,376.74$

Subtask 1: Survey Subtotal

Subtask 2: Geotech Subtotal

Subtask 3: Engineering - 60% Subtotal

Subtask 5: Engineering - 90% Subtotal

Subtask 6: Engineering - 100% and Specs Subtotal

13,422.92$

Subtask Subtask Fixed

Price Cost

Fee Summary

Subtask Reimbursable

FDEP - Paynes Prairie State Park Pavement Rehabilitation

File details come from the government source that posted it. Updated .