This document is a Task Assignment Change Order Form (Change Order No. 2) issued by the Florida Department of Environmental Protection (FDEP) for consulting services related to the Fakahatchee Strand Preserve State Park Big Cypress Parking Improvements project located in Collier County, Florida. The primary contractor is George F. Young, Inc., a civil and transportation engineering firm with offices in Florida, working under FDEP Contract No. CN200, Task Assignment No. 14. The project involves coordination with multiple government agencies including Collier County Health Department, Collier County Building Department, South Florida Water Management District (SFWMD), and FDEP's Bureau of Design and Construction, Division of Recreation and Parks.
Change Order 2 authorizes additional services totaling $86,805.72 in fixed price costs plus $9,831.28 in reimbursable expenses, for a combined total of $96,637.00. Services include Collier County Department of Health on-site sewage treatment and disposal systems (OSTDS) permitting assistance ($6,884.41), design of an 8-foot-wide wooden boardwalk to current Florida Building Code 2020 standards ($14,651.76), miscellaneous civil site plan updates ($4,359.06), Collier County Site Development Plan (SDP) permit modification assistance ($12,534.12), South Florida Water Management District Environmental Resource Permit (ERP) modification support ($5,111.41), building permit support ($1,194.16), construction administration services including shop drawing review and RFI responses ($14,256.00), and six inspection visits each by a structural engineer ($9,215.88), principal ecologist ($8,796.48), and civil engineer ($9,802.44) during boardwalk construction. All work is scheduled on an as-needed basis with a task end date of March 15, 2023. Payment is contingent upon FDEP approval of deliverables for each subtask. The change order was approved and digitally signed on May 6, 2022 by FDEP's Contract Authority Bryan Bradner.
Text of this file
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN200 14 02 60857C
Fakahatchee Strand Preserve State Park Big Cypress Parking Improvements
George F. Young, Inc.
Stefan Thoenes, PE 941-413-6790 jsthoenes@georgefyoung.com
Jeffrey Whitfield 850-245-2630 jeffrey.whitfield@floridadep.gov
Consultant will provide boardwalk design, site and sewer permitting, and boardwalk construction services for site, sewer and boardwalk. See attached proposal dated 03/08/2022.
$ 8,244.15 $ 8,244.15 $ 3,510.16 $ 176,254.70 $ 179,764.86 $ 9,831.28 $ 76,974.44 $ 86,805.72 $ 13,341.44 $ 253,229.14 $ 266,570.58
12/18/2020
3/15/2022
3/15/2023
3/15/2023
Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.05.02 08:24:10 -04'00'
John Goss John Goss Digitally signed by John Goss Date: 2022.05.02 09:20:41 -04'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.05.02 09:32:18 -04'00'
Matt Walker, PE Matt Walker, PE Digitally signed by Matt Walker, PE DN: C=US, E=mwalker@georgefyoung.com, O="George F. Young, Inc.", CN="Matt Walker, PE" Reason: I have reviewed this document Date: 2022.05.02 13:29:00-04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2022.05.06 13:32:09 -04'00'
60857C 37504000114 080039/22 423001 U3200 131500 QK $ 86,805.72
$ 86,805.72
G A I N E S V I L L E � L A K E W O O D R A N C H � O R L A N D O � S T . P E T E R S B U R G � T A M P A
Passionately committed to Integrity, Quality & Service
10540 Portal Crossing, Suite 105 Lakewood Ranch, Florida 34211-4913
Phone: (941) 747-2981 www.georgefyoung.com
George F. Young, Inc.
Turning Vision into Reality Since 1919
CIVIL & TRANSPORTATION ENGINEERING | ECOLOGY | GIS | LANDSCAPE ARCHITECTURE | PLANNING | SURVEYING | SUBSURFACE UTILITY ENGINEERING
September 21st, 2021 (Revised 03/08/2022)
John Goss Project Manager Florida Department of Environmental Protection Bureau of Design and Construction, Division of Recreation and Parks
John.Goss@FloridaDEP.gov Office: 941-882-7211
RE: DEP Agreement CN200 TA14 CO2
Fakahatchee Strand Preserve State Park
Additional Services Proposal
Dear John:
For your review, George F. Young has provided a proposal summary and man-hour documentation for the tasks identified below that will be added to Task Assignment 14 as
Change Order 2:
• Subtask 5 – Collier County Health Department On-Site Sewage Treatment and Disposal
Systems (OSTDS) Permitting Assistance including Collier County DOH Permit Review
Fees
• Subtask 6 – 8ft wide Wooden Boardwalk Design – Replacement of current, permitted
Boardwalk Design
• Subtask 7 – Miscellaneous permitted Civil Site Plan Revisions/Updates
• Subtask 8 – Collier County SDP Permit Modification with updated Plans
• Subtask 9 – ERP Permit modification through SFWMD for updated, modified Civil Site
Plan
• Subtask 10 - Building Permitting Support to Contractor and FDEP for 8ft wide, wooden
Boardwalk
• Subtask 11 - Construction Administration Services for 8ft wide, wooden Boardwalk
• Subtask 12 – FDEP requested/As needed - additional Construction Inspection Visits by structural Engineer for wooden Boardwalk Construction (Six (6) individual Visits to cover long Duration of Construction)
• Subtask 13 – FDEP requested/As needed – one (1) additional Construction Inspection
Visit by Principal Ecologist during wooden Boardwalk Construction (Six (6) individual
Visits to cover long Duration of Construction)
DEP Agreement CN200 TA14 CO2 September 21st, 2021 (Revised 03/08/2022)
• Subtask 14 – FDEP requested/As needed – one (1) additional Construction Inspection
Visit by Civil Engineer during wooden Boardwalk Construction (Six (6) individual Visits to cover long Duration of Construction)
Please review the attached proposal summary, deliverables, Exhibit “B” - Excluded Services and
Exhibit “C” – Client Responsibilities. If you have any questions, please feel free to contact us.
Sincerely, GEORGE F. YOUNG, INC.
Stefan Oliver Thoenes, PE, LEED AP BD+C Senior Project Manager, Engineering
FAK-CN200 TA14 C02 (ASA Proposal)-EX-B-C_2021-09-21REV2022-03-08R5.docx
Fakahatchee Strand Preserve State Park CN200, Task Assignment 14, Change Order 2 (TA14 CO2)
SUBTASK 5 – Collier County Department of Health (DOH) OSTDS (Onsite Sewage Treatment and Disposal Systems) Permit Application Assistance to BDC (FDEP)
Subtask 5A: Collier County DOH OSTDS Permit Application Package Description: GFY, Inc will review, research, and coordinate with FDEP and the contractor the currently proposed on-site septic system design and prepare and assemble the permit application package including. necessary civil plans and other information for transmittal to Collier County Health Department (DOH). As confirmed with FDEP BDC staff, the proposed and to be permitted on-site OSTDS system is sized to serve 61 visitors using the restroom (no showers) and the two (2) on-site RV spaces, which will generate a daily wastewater flow of 394 gallons (394 gpd). Septic system design changes deviating from the current contractor bid plans are not included in Task 5A.
Deliverable: GFY, Inc. will prepare and assemble the Collier County DOH OSTDS permit application package.
Performance Measure: An electronic copy of the permit application package transmittal to Collier County Health Department (DOH) will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $3,585.56 Reimbursables: Collier County DOH OSTDS Permitting Fees of $670.00
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 5A: Collier County DOH OSTDS Permit Application Package
$3,585.56 $670.00
Subtask 5A Total: $4,255.56 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Subtask 5B: Collier County DOH OSTDS Septic Permitting Assistance to BDC (FDEP) Description: GFY, Inc. will coordinate and submit the OSTDS permit application package to Collier County DOH for review and approval. GFY, Inc. will follow up with DOH staff to confirm receipt, will answer staff review comments and revise the application package as necessary to assist FDEP BDC to attain the permit.
Deliverable: PDFs of email communication with DOH staff. Communication with staff can be but is not limited to receipt of application confirmation, review comment/s, clarification/s, and/or requested correction/s about submitted application. PDFs of available email communication with DOH staff will be provided to BDC.
Performance Measure: Provided email printouts will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $2,628.85 Reimbursables: N/A
Summary of Fees:
Subtask Subtask Fixed Price Cost
Reimbursable
Subtask 5B: Collier County DOH OSTDS Permitting Assistance to
BDC (FDEP)
$2,628.85 $0.00
Subtask 5B Total: $2,628.85 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 5A – Collier County DOH OSTDS Application Package
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 5.0 $652.05
George F. Young, Inc. Civil Engineer $142.54 12.5 $1,781.75
George F. Young, Inc. Senior CAD Tech. $78.00 12.5 $975.00
George F. Young, Inc. Staff Assistant $44.19 4.0 $176.76
Subtask 5A - Fixed Price Cost – Manhour Subtotal: 34.0 $3,585.56
Subtask 5B – Collier County DOH OSTDS Permitting Assistance to BDC (FDEP)
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 5.0 $652.05
George F. Young, Inc. Civil Engineer $142.54 9.5 $1,354.13
George F. Young, Inc. Senior CAD Tech. $78.00 6.0 $468.00
George F. Young, Inc. Staff Assistant $44.19 3.5 $154.67
Subtask 5B - Fixed Price Cost – Manhour Subtotal: 24.0 $2,628.85
Subtasks 5A, 5B- Fixed Price Cost – Manhour Total: 58.0 $6,214.41
SUBTASK 6 – 8ft wide, wooden Boardwalk Design
Subtask 6: 8ft wide, wooden Boardwalk Design Description: GFY, Inc. and the structural engineering subconsultant will replace the current, permitted boardwalk design with the design of a wooden, 8ft wide boardwalk and prepare constructions drawings with specifications. The design of the 8ft wide boardwalk will be to the current building code, FBC2020. The design will be coordinated and reviewed by FDEP staff and the contractor during the design process. The completed structural plans with specifications (on plans) will be used for permitting through Collier County building department and Collier County SDP permit modification and modification of the SFWMD ERP permit. It is anticipated that the structural drawing set for the wooden, 8ft wide boardwalk will consist of one (1) general notes/specification sheet, two (2) structural detail/s and section/s sheets and seven (7) piling plan sheets. Updates to the current, permitted civil plan set will consist of revising the boardwalk alignment by removing the currently shown curves in the boardwalk, coordination of surveyed filed staked alignment and stationing between the civil and structural plans and updating the transition/connection area at the Interpretive Building/Bridge boardwalk.
Deliverable: GFY, Inc. and the structural engineering subconsultant will prepare and assemble constructions plans with specifications (on plans) for the wooden, 8ft wide boardwalk design.
Performance Measure: An electronic copy, in PDF format, of the wooden, 8ft wide boardwalk design plans and corresponding updated civil plan sheets will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $14,651.76 Reimbursables: N/A
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 6: 8ft wide, wooden Boardwalk Design $14,651.76 $0.00
Subtask 6 Total: $14,651.76 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 6 – 8ft wide, wooden Boardwalk Design
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 5.0 $652.05
George F. Young, Inc. Civil Engineer $142.54 12.0 $1,710.48
George F. Young, Inc. Senior CAD Tech. $78.00 32.0 $2,496
George F. Young, Inc. Staff Assistant $44.19 5.0 $220.95
George F. Young, Inc. Principal Ecologist $126.39 8.0 $1,011.12
David Corban Architect Project Architect $135.00 4.0 $540.00
McCarthy & Associates Inc. Project Manager $144.24 21.5 $3,101.16
McCarthy & Associates Inc. Structural Engineer $75.00 26.0 $1,950.00
McCarthy & Associates Inc. CADD Drafter $90.00 33.0 $2,970.00
Subtask 6- Fixed Price Cost – Manhour Total: 146.5 $14,651.76
SUBTASK 7 – Miscellaneous Updates to permitted Civil Site Plan Set
Subtask 7: Miscellaneous Updates to permitted Civil Site Plan Description: GFY, Inc. will update the current, permitted civil plan set with the boardwalk detail sheets and make other miscellaneous updates to the plans as discussed with the owner i.e. RV space reconfiguration with driveway apron adjustment, IP building location change and changed planting areas at Jane Scenic Drive. The complete or portions of the revised civil plan set will be used for permitting through Collier County building department and Collier County SDP permit modification and modification of the SFWMD ERP permit.
Deliverable: GFY, Inc. will prepare and assemble a revised civil constructions plan set.
Performance Measure: An electronic copy, in PDF format, of the revised civil construction plan set will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $4,359.06
Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 7: Miscellaneous Updates to permitted Civil Plan Set $4,359.06 $0.00
Subtask 7 Total: $4,359.06 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 7: Miscellaneous Civil Updates to permitted Civil Plan Set
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 3.0 $391.23
George F. Young, Inc. Civil Engineer $142.54 12.0 $1710.48
George F. Young, Inc. Senior CAD Tech. $78.00 24.0 $1872.00
George F. Young, Inc. Staff Assistant $44.19 3.0 $132.57
George F. Young, Inc. Principal Ecologist $126.39 2.0 $252.78
Subtask 7- Fixed Price Cost – Manhour Total: 44.0 $4,359.06
SUBTASK 8 – Collier County SDP Permit Modification
Subtask 8A: Collier County SDP Permit Modification Application Package for Revised Civil Plan Sheets
Description: GFY, Inc will prepare and assemble the SDP permit modification application package for the revised civil site plan sheets. The Collier County SDP permit modification application review is $400 per revised, submitted plan sheet. There is no review fee for the revised cover sheet. It is anticipated that there will be up to fifteen (15) revised civil plan sheets in this submittal.
Deliverable: GFY, Inc. will prepare and assemble the Collier County SDP permit modification application package.
Performance Measure: An electronic copy (PDF format) of the civil plans SDP permit modification application package to Collier County will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $2,852.90 Reimbursables: $6,000.00
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 8A: Collier County SDP Permit Modification Application Package for Revised Civil Plan Sheets
$2,852.90 $6,000.00
Subtask 8A Total: $8,852.90 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Subtask 8B: Collier County Collier County Civil Plan Set SDP Modification Permitting
Assistance to BDC (FDEP) Description: GFY, Inc. will coordinate and submit the revised landscape plans to Collier County for a modification of the current SDP permit for review and approval. GFY, Inc. will follow up with County staff to confirm receipt, will answer staff review comments and revise/amend the application package as necessary to assist FDEP BDC to attain the permit.
Deliverable: PDFs of email communication and/or screenshots with Collier County.
Communication with staff can be but is not limited to receipt of application confirmation, review comment/s, clarification/s, and/or requested correction/s about submitted application. PDFs of available email communication with County staff will be provided to BDC.
Performance Measure: Provided PDFs of email printouts and/or screenshots will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $3,681.22 Reimbursables: N/A
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 8B: Collier County Civil Plan Sheets SDP Permit Modification Permitting Assistance to BDC (FDEP)
$3,681.22 $0.00
Subtask 8B Total: $3,681.22 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 8A – Collier County SDP Permit Modification Application Package for Civil Plans
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 3.0 $391.23
George F. Young, Inc. Civil Engineer $142.54 8.0 $1,140.32
George F. Young, Inc. Senior CAD Tech. $78.00 12.0 $936.00
George F. Young, Inc. Principal Ecologist $126.39 2.0 $252.78
George F. Young, Inc. Staff Assistant $44.19 3.0 $132.57
Subtask 8A - Fixed Price Cost – Manhour Total: 28.0 $2,852.90
Subtask 8B – Collier County Collier County Civil Plans SDP Modification Permitting
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 3.0 $391.23
George F. Young, Inc. Civil Engineer $142.54 16.0 $2,280.64
George F. Young, Inc. Senior CAD Tech. $78.00 8.0 $624.00
George F. Young, Inc. Principal Ecologist $126.39 2.0 $252.78
Subtask 8B - Fixed Price Cost – Manhour Total: 32.0 $3,681.22
Subtasks 8A, 8B- Fixed Price Cost – Manhour Total: 60.0 $6,534.12
SUBTASK 9 – South Florida Water Management District (SFWMD) Environmental Resource Permit (ERP) Permit Modification Assistance to BDC (FDEP)
Subtask 9A: SFWMD Environmental Resource Permit (ERP) Permit Modification Application Preparation
Description: GFY, Inc will review and prepare the necessary documents and application for the Environmental Resource Permit (ERP) minor modification permitting package for submittal to the South Florida Water Management District (SFWMD).
Deliverable: GFY, Inc. will prepare and assemble the SFWMD ERP Permit Modification application package.
Performance Measure: An electronic copy, in PDF format, of the ERP Permit Modification application package transmittal to SFWMD will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $2,852.90 Reimbursables: N/A
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 9A: SFWMD Environmental Resource Permit (ERP) Modification Application Preparation and Coordination
$2,852.90 $0.00
Subtask 9A Total: $2,852.90 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Subtask 9B: SFWMD Environmental Resource Permit (ERP) Modification Permitting
Description: GFY, Inc. will coordinate and submit ERP Permit Modification application package to South Florida Water Management District through their webportal, for review and approval. GFY, Inc. will follow up with SFWMD staff to confirm receipt, will answer staff review comments and revise the application package as necessary to assist FDEP BDC to attain the permit.
Deliverable: PDFs of screenshots from the upload process to the portal and if available PDFs of email communication with SFWMD staff. Communication with staff can be but is not limited to receipt of application confirmation, review comment/s, clarification/s, and/or requested correction/s about submitted application. PDFs of available email communication with SFWMD staff will be provided to BDC.
Performance Measure: Provided PDFS of communication as described above will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $2,258.51 Reimbursables: N/A
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 9B: SFWMD Environmental Resource Permit (ERP) Modification Permitting Assistance to BDC (FDEP)
$2,258.51 $0.00
Subtask 9B Total: $2,258.51 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 9A – SFWMD Environmental Resource Permit (ERP) Modification Application Preparation and Coordination
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 3.0 $391.23
George F. Young, Inc. Civil Engineer $142.54 8.0 $1,140.32
George F. Young, Inc. Senior CAD Tech. $78.00 12.0 $936.00
George F. Young, Inc. Principal Ecologist $126.39 2.0 $252.78
Subtask 9A - Fixed Price Cost – Manhour Total: 28.0 $2,852.90
Subtask 9B – SFWMD Environmental Resource Permit (ERP) Modification Permitting
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 3.0 $391.23
George F. Young, Inc. Civil Engineer $142.54 8.0 $1,140.32
George F. Young, Inc. Senior CAD Tech. $78.00 6.0 $468.00
George F. Young, Inc. Principal Ecologist $126.39 1.0 $126.39
Subtask 9B - Fixed Price Cost – Manhour Total: 21.0 $2,258.51
Subtasks 9A, 9B - Fixed Price Cost – Manhour Total: 49.0 $5,111.41
SUBTASK 10 – Collier County Building Permit Application Support to Contractor and FDEP for 8ft wide, wooden Boardwalk
Subtask 10: Collier County Building Permit Application Support to Contractor and FDEP for 8ft wide, wooden Boardwalk
Description: GFY, Inc. and the structural engineering subconsultant will support the Contractor and FDEP in providing for building permit application package, signed and sealed construction documents for the 8ft wide, wooden boardwalk.
Deliverable: GFY, Inc. and structural engineering subconsultant will provide signed and sealed construction documents for the 8ft wide, wooden boardwalk.
Performance Measure: An electronic copy, in PDF format, of the signed and sealed construction documents for the 8ft wide, wooden boardwalk will be provided to BDC.
Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,194.16
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 10: Collier County Building Permit Application Support to Contractor and FDEP for 8ft wide, wooden Boardwalk
$1,194.16 $0.00
Subtask 10 Total: $1,194.16 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 10 – Collier County Building Permit Application Support to Contractor and FDEP for 8ft wide, wooden Boardwalk
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Civil Engineer $142.54 4.0 $570.16
George F. Young, Inc. Senior CAD Tech. $78.00 8.0 $624.00
Subtask 10 - Fixed Price Cost – Manhour Total: 12.0 $1,194.16
SUBTASK 11 – Construction Administration for 8ft wide, wooden Boardwalk Construction
Subtask 11A: 8ft wide, wooden Boardwalk Shop Drawing Review
Description: GFY, Inc. and the structural engineering subconsultant will review 8ft wide, wooden boardwalk shop drawings.
Deliverable: GFY, Inc. and structural engineering subconsultant will provide reviewed shop drawings.
Performance Measure: Electronic copies of reviewed shop drawings, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,861.00 Reimbursables: N/A
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 11A: 8ft wide, wooden Boardwalk Shop Drawing Review $1,861.00 $0.00
Subtask 11A Total: $1,861.00 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 11A – 8ft wide, wooden Boardwalk Shop Drawing Review
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.0 $130.41
George F. Young, Inc. Civil Engineer $142.54 4.0 $570.16
George F. Young, Inc. Senior CAD Tech. $78.00 4.0 $312.00
George F. Young, Inc. Staff Assistant $44.19 1.0 $44.19
McCarthy & Associates Inc. Project Manager $144.24 1.0 $144.24
McCarthy & Associates Inc. Structural Engineer $75.00 4.0 $300.00
McCarthy & Associates Inc. CADD Drafter $90.00 4.0 $360.00
Subtask 11A Fixed Price Cost – Manhour Total: 19.0 $1,861.00
Subtask 11B: 8ft wide, wooden Boardwalk Response to Contractor construction RFI/s
Description: GFY, Inc. and the structural engineering subconsultant will respond to contractor RFI/s related to the boardwalk construction.
Deliverable: GFY, Inc. and structural engineering subconsultant will provide RFI responses.
Performance Measure: Electronic copies of RFI responses, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $3,722.00 Reimbursables: N/A
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 11B: 8ft wide, wooden Boardwalk - Response to Contractor construction RFI/s
$3,722.00 $0.00
Subtask 11B Total: $3,722.00 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Subtask 11B – 8ft wide, wooden Boardwalk - Response to Contractor construction RFI/s
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 2.0 $260.82
George F. Young, Inc. Civil Engineer $142.54 8.0 $1,140.32
George F. Young, Inc. Senior CAD Tech. $78.00 8.0 $624.00
George F. Young, Inc. Staff Assistant $44.19 2.0 $88.38
McCarthy & Associates Inc. Project Manager $144.24 2.0 $288.48
McCarthy & Associates Inc. Structural Engineer $75.00 8.0 $600.00
McCarthy & Associates Inc. CADD Drafter $90.00 8.0 $720.00
Subtask 11B - Fixed Price Cost – Manhour Total: 38.0 $3,722.00
Subtask 11C: One (1) Construction Progress Visit during wooden Boardwalk Construction
Description: The civil engineer, principal ecologist and the structural engineer (subconsultant) will conduct one (1) construction progress visit during wooden boardwalk construction and each will provide a written report/memo after the visit/inspection.
Deliverable: GFY, Inc. will provide the structural engineer’s site visit reports.
Performance Measure: Electronic copies of the structural engineer’s site visit report, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $3,654.56 Reimbursables: $395.16
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 11C: One (1) Construction Progress Visit during wooden Boardwalk Construction
$3,654.56 $395.16
Subtask 11C Total: $4,049.72 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 11C – One (1) Construction Progress Visit during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 2.0 $260.82
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Civil Engineer $142.54 8.0 $1,140.32
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Principal Ecologist $126.39 8.0 $1,011.12
George F. Young, Inc. Staff Assistant $44.19 2.0 $88.38
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Project Manager $144.24 8.0 $1,153.92
Subtask 11C - Fixed Price Cost – Manhour Total: 28.0 $3,654.56
Task Reimbursable Breakdown:
Activity Roundtrip From To Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 11C
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY LWR
Office
Job Site 272 miles $121.04
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY ST.
PETE Office
Job Site 346 miles $153.97
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Job Site 270 miles $120.15
Subtask 11C Reimbursable – Total: 888 miles $395.16
Subtask 11D: One (1) Substantial Completion Meeting/Inspection for wooden Boardwalk
Description: The civil engineer, principal ecologist and the structural engineer (subconsultant) will conduct one (1) substantial completion meeting to inspect the substantially complete wooden boardwalk and each attending team member will provide a written report/memo after the meeting/inspection.
Deliverable: GFY, Inc. will provide the substantial completion meeting reports/memos by each attending team member.
Performance Measure: Electronic copies of the substantial completion meetings reports/memos by each attending team member, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $4,228.12 Reimbursables: $395.16
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 11D: One (1) Substantial Completion Meeting/Site Visit for wooden Boardwalk
$4,228.12 $395.16
Subtask 11D Total: $4,623.28 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 11D – One (1) Substantial Completion Meeting/Site Visit for wooden Boardwalk
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 2.0 $260.82
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Civil Engineer $142.54 10.0 $1,425.40
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Principal Ecologist $126.39 8.0 $1,011.12
George F. Young, Inc. Staff Assistant $44.19 2.0 $88.38
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Project Manager $144.24 10.0 $1,442.40
Subtask 11D - Fixed Price Cost – Manhour Total: 32.0 $4,228.12
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 11D
George F. Young, Inc. – One (1) Rep (One Vehicle)
GFY LWR
Office
Job Site 272 miles $ 121.04
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY St. Pete Office
Job Site 346 miles $153.97
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Subtask 11D Reimbursable – Total: 888 miles $395.16
SUBTASK 12 – FDEP requested/As needed - additional Construction Inspection Visits by structural Engineer for wooden Boardwalk Construction (Six (6) individual Visits to cover long Duration of Construction)
Subtask 12A: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Description: The structural engineer (subconsultant) will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the structural engineer’s construction visit report/memo.
Performance Measure: Electronic copies of the structural engineer’s construction visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,415.83 Reimbursables: $120.15
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 12A: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
$1,415.83 $120.15
Subtask 12A Total: $1,535.98 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 12A – FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.5 $195.62
George F. Young, Inc. Staff Assistant $44.19 1.5 $66.29
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Subtask 12A Fixed Price Cost – Manhour Total: 11.0 $1,415.83
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 12A
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Subtask 12A Reimbursable – Total: 270 miles $120.15
Subtask 12B: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Description: The structural engineer (subconsultant) will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the structural engineer’s construction visit report/memo.
Performance Measure: Electronic copies of the structural engineer’s construction visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,415.83 Reimbursables: $120.15
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 12B: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
$1,415.83 $120.15
Subtask 12B Total: $1,535.98 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 12B – FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.5 $195.62
George F. Young, Inc. Staff Assistant $44.19 1.5 $66.29
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Subtask 12B Fixed Price Cost – Manhour Total: 11.0 $1,415.83
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 12B
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Subtask 12B Reimbursable – Total: 270 miles $120.15
Subtask 12C: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The structural engineer (subconsultant) will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the structural engineer’s construction visit report/memo.
Performance Measure: Electronic copies of the structural engineer’s construction visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,415.83 Reimbursables: $120.15
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 12C: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
$1,415.83 $120.15
Subtask 12C Total: $1,535.98 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 12C – FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.5 $195.62
George F. Young, Inc. Staff Assistant $44.19 1.5 $66.29
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Subtask 12C Fixed Price Cost – Manhour Total: 11.0 $1,415.83
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 12C
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Subtask 12C Reimbursable – Total: 270 miles $120.15
Subtask 12D: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The structural engineer (subconsultant) will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the structural engineer’s construction visit report/memo.
Performance Measure: Electronic copies of the structural engineer’s construction visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,415.83 Reimbursables: $120.15
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 12D: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
$1,415.83 $120.15
Subtask 12D Total: $1,535.98 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 12D – FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.5 $195.62
George F. Young, Inc. Staff Assistant $44.19 1.5 $66.29
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Subtask 12D Fixed Price Cost – Manhour Total: 11.0 $1,415.83
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 12D
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Subtask 12D Reimbursable – Total: 270 miles $120.15
Subtask 12E: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The structural engineer (subconsultant) will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the structural engineer’s construction visit report/memo.
Performance Measure: Electronic copies of the structural engineer’s construction visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,415.83 Reimbursables: $120.15
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 12E: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
$1,415.83 $120.15
Subtask 12E Total: $1,535.98 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 12E – FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.5 $195.62
George F. Young, Inc. Staff Assistant $44.19 1.5 $66.29
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Subtask 12E Fixed Price Cost – Manhour Total: 11.0 $1,415.83
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 12E
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Subtask 12E Reimbursable – Total: 270 miles $120.15
Subtask 12F: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The structural engineer (subconsultant) will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the structural engineer’s construction visit report/memo.
Performance Measure: Electronic copies of the structural engineer’s construction visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,415.83 Reimbursables: $120.15
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 12F: FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
$1,415.83 $120.15
Subtask 12F Total: $1,535.98 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 12F – FDEP requested/As needed – one (1) additional Construction Inspection Visit by structural Engineer during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.5 $195.62
George F. Young, Inc. Staff Assistant $44.19 1.5 $66.29
McCarthy & Associates Inc. – One (1) Representative/One
(1) Visit
Subtask 12F Fixed Price Cost – Manhour Total: 11.0 $1,415.83
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 12F
McCarthy & Associates Inc.
– One (1) Rep. (One Vehicle)
Delray Beach Office
Subtask 12F Reimbursable – Total: 270 miles $120.15
SUBTASK 13 – FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction (Six
(6) individual Visits to cover long Duration of Construction)
Subtask 13A: FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
Description: The principal ecologist will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the principal ecologist’s site visit report/memo.
Performance Measure: Electronic copies of the principal ecologist’s site visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,312.11 Reimbursables: $153.97
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 13A: FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
$1,312.11 $153.97
Subtask 13A Total: $1,466.08 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 13A – FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.0 $130.41
George F. Young, Inc. Staff Assistant $44.19 1.0 $44.19
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Principal Ecologist $126.39 9.0 $1,137.51
Subtasks 13A Fixed Price Cost – Manhour Total: 11.0 $1,312.11
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 13A
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY ST.
PETE Office
Job Site 346 miles $153.97
Subtask 13A Reimbursable – Total: 346 miles $153.97
Subtask 13B: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The principal ecologist will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the principal ecologist’s site visit report/memo.
Performance Measure: Electronic copies of the principal ecologist’s site visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,312.11 Reimbursables: $153.97
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 13B: FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
$1,312.11 $153.97
Subtask 13B Total: $1,466.08 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 13B – FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.0 $130.41
George F. Young, Inc. Staff Assistant $44.19 1.0 $44.19
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Subtasks 13B Fixed Price Cost – Manhour Total: 11.0 $1,312.11
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 13B
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY ST.
PETE Office
Subtask 13B Reimbursable – Total: 346 miles $153.97
Subtask 13C: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The principal ecologist will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the principal ecologist’s site visit report/memo.
Performance Measure: Electronic copies of the principal ecologist’s site visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,312.11
Reimbursables: $153.97
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 13C: FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
$1,312.11 $153.97
Subtask 13C Total: $1,466.08 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 13C – FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.0 $130.41
George F. Young, Inc. Staff Assistant $44.19 1.0 $44.19
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Subtasks 13C Fixed Price Cost – Manhour Total: 11.0 $1,312.11
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 13C
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY ST.
PETE Office
Subtask 13C Reimbursable – Total: 346 miles $153.97
Subtask 13D: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The principal ecologist will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the principal ecologist’s site visit report/memo.
Performance Measure: Electronic copies of the principal ecologist’s site visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,312.11 Reimbursables: $153.97
Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 13D: FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
$1,312.11 $153.97
Subtask 13D Total: $1,466.08 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 13D – FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.0 $130.41
George F. Young, Inc. Staff Assistant $44.19 1.0 $44.19
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Subtasks 13D Fixed Price Cost – Manhour Total: 11.0 $1,312.11
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 13D
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY ST.
PETE Office
Subtask 13D Reimbursable – Total: 346 miles $153.97
Subtask 13E: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The principal ecologist will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the principal ecologist’s site visit report/memo.
Performance Measure: Electronic copies of the principal ecologist’s site visit report/memo, in PDF format, will be provided to BDC. Deliverables will be reviewed by BDC to confirm that they meet the expectations, are complete, and timely.
Fixed Price Cost: $1,312.11 Reimbursables: $153.97
Summary of Fees:
Subtask Subtask Fixed Price Cost
Reimbursable
Subtask 13E: FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
$1,312.11 $153.97
Subtask 13E Total: $1,466.08 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Fixed Price Cost – Manhour Summary:
Subtask 13E – FDEP requested/As needed – one (1) additional Construction Inspection Visit by Principal Ecologist during wooden Boardwalk Construction
Firm Name Position Classification
Hourly Rate
Hours Total Fixed Price Cost
George F. Young, Inc. Contract Manager $130.41 1.0 $130.41
George F. Young, Inc. Staff Assistant $44.19 1.0 $44.19
George F. Young, Inc. – One
(1) Representative/One (1) Visit
Subtasks 13E Fixed Price Cost – Manhour Total: 11.0 $1,312.11
Mileage
(Roundtrip) Reimbursable
($0.445 per mile)
Subtask 13E
George F. Young, Inc. – One (1) Rep. (One Vehicle)
GFY ST.
PETE Office
Subtask 13E Reimbursable – Total: 346 miles $153.97
Subtask 13F: FDEP requested/As needed – one (1) additional Construction Inspection Visit
Description: The principal ecologist will conduct one (1) wooden boardwalk construction site visit during boardwalk construction as requested in writing per FDEP; provide a written construction visit report/memo after each visit.
Deliverable: GFY, Inc. will provide the principal ecologist’s site visit report/memo.
Performance Measure: Electronic copies of the principal ecologist’s site visit report/memo, in PDF…
This is the start of the file's text. The full file is on GovTribe.
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .