This document comprises a Task Assignment Change Order Form and supporting project proposal for a Florida Department of Environmental Protection (DEP) contract with WS Atkins, Inc. (Atkins). The indefinite delivery contract is numbered BS136, and the change order, dated March 18, 2021, is Task Assignment Number 2, Change Order No. 1. The engagement involves the DEP's Office of Resilience and Coastal Protection and coordination with Aquatic Preserve (AP) and Buffer Preserve (BP) management staff across Florida's regions.

The scope of work requires Atkins to develop a comprehensive report incorporating Sea Level Rise (SLR) effects into AP and BP Management Plan objectives and performance measures. The project consists of five sequential tasks: coordinating with DEP staff to develop interview questions (due one month after notice to proceed); conducting interviews with AP, BP, and National Estuarine Research Reserves managers (due 3.5 months after NTP); developing a report outline (due 4.5 months after NTP); preparing a draft report with stakeholder feedback (due 30 days after receiving feedback); and delivering a final ADA-compliant PDF report (due one month after Task 4 completion). The not-to-exceed project cost is $28,325.02, comprised of Task 1 ($1,747.64), Task 2 ($6,242.87), Task 3 ($1,521.79), Task 4 ($9,206.45), and Task 5 ($9,606.27). The change order increased the original task amount by $17.81 through recasting the fee table, correcting rounding errors, and adjusting labor hour allocations among staff titles while maintaining the lump sum value limits. The project operates on a lump sum basis with invoicing based on percent completion, and the completion date remains September 30, 2021.

View the file

Other files

File Type Posted
CN-370000-BS136-A1R1.pdf PDF
CN-370000-BS136-A1R1.pdf.crdownload CRDOWNLOAD file
CN-370000-BS136-CMC3.pdf PDF
CN-370000-BS136-T11.pdf PDF
CN-370000-BS136-T11CO2.pdf PDF
CN-370000-BS136-T11CO3.pdf PDF
CN-370000-BS136-T17CO1.pdf PDF
CN-370000-BS136-T22.pdf PDF
CN-370000-BS136-T26.pdf PDF
CN-370000-BS136-T29CO1.pdf PDF
CN-370000-BS136-T31.pdf PDF
CN-370000-BS136-T32CO2.pdf PDF
CN-370000-BS136-T33CO1.pdf PDF
CN-370000-BS136-T4.pdf PDF
CN-370000-BS136-T7.pdf PDF
CN-370000-BS136-T7CO1.pdf PDF
CN-370000-BS136-CMC1.pdf PDF
CN-370000-BS136-CMC2.pdf PDF
CN-370000-BS136-T10CO1.pdf PDF
CN-370000-BS136-T11CO1.pdf PDF
CN-370000-BS136-T12.pdf PDF
CN-370000-BS136-T17.pdf PDF
CN-370000-BS136-T18CO1.pdf PDF
CN-370000-BS136-T2.pdf PDF
CN-370000-BS136-T21.pdf PDF
CN-370000-BS136-T22CO1.pdf PDF
CN-370000-BS136-T23.pdf PDF
CN-370000-BS136-T25CO1.pdf PDF
CN-370000-BS136-T27CO1.pdf PDF
CN-370000-BS136-T28CO1.pdf PDF
CN-370000-BS136-T28CO2.pdf PDF
CN-370000-BS136-T28CO3.pdf PDF
CN-370000-BS136-T29.pdf PDF
CN-370000-BS136-T32.pdf PDF
CN-370000-BS136-T32CO1.pdf PDF
CN-370000-BS136-T33.pdf PDF
CN-370000-BS136-T34.pdf PDF
CN-370000-BS136-T36.pdf PDF
CN-370000-LE807-8C-71562.pdf PDF
CN-370000-BS136-T1.pdf PDF
CN-370000-BS136-T10.pdf PDF
CN-370000-BS136-T11CO4.pdf PDF
CN-370000-BS136-T16.pdf PDF
CN-370000-BS136-T16CO1.pdf PDF
CN-370000-BS136-T19.pdf PDF
CN-370000-BS136-T23CO1.pdf PDF
CN-370000-BS136-T24.pdf PDF
CN-370000-BS136-T28.pdf PDF
CN-370000-BS136-T30.pdf PDF
CN-370000-BS136-T30CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3/19/2021

Genita Alexander Digitally signed by Genita Alexander Date: 2021.03.19 16:13:29 -04'00'

3/22/2021

WS Atkins, Inc.

Registered office: 200 Westlake Park Blvd, Suite 1100, Houston, Texas 77079

Atkins 3522 Thomasville Road

5th Floor Tallahassee, FL 32309

Tel: +1 850 575 1800 Fax: +1 850 575 0105 atkinsglobal.com snclavalin.com

RE: DEP WR Contract: BS136 Project Proposal - SLR in AP Incorporating the Effects of Sea Level Rise into Aquatic Preserve and Buffer Preserve Management Plan Objectives and Goals

Dear Avery, BACKGROUND

DEP has requested a proposal to work with Aquatic Preserve (AP) and Buffer Preserve (BP) staff to develop a report that will assist with inclusion of Sea Level Rise (SLR) and other related issues as performance measures in Preserve Management Plans. Because performance measures can vary from region to region, working in close coordination with field staff who are experts in their regions, who know best the resources most at risk from Sea Level Rise inundation, and can provide insights on effective mitigation strategies is most important. National Estuarine Research Reserves (NERR) have adapted similar measures in their Management Plans and will also be a useful resource. DEP would like Atkins to conduct interviews AP, BP and NERR staff to learn about SLR threats in their areas, and then seek input from AP and BP staff through review of the report. Questions for the interviews are to be developed in coordination with Office of Resilience and Coastal Protection (RCP) staff involved with either AP Management plans or Coastal Resilience issues.

SCOPE OF WORK

A report will be developed to provide suggestions on implementing adaptation strategies or other initiatives as part of the AP and BP Management Plans’ performance measures. The strategies/initiatives should help mitigate the effects of SLR on Preserve ecosystems and surrounding communities in a way that best fits the needs and resources of the APs and BPs while remaining within their authority. The resulting report will be organized by region to address the differences for each AP and BP area.

October 14, 2020

REVISED 3-18-2021 (ONLY AREAS IN RED)

Avery Lehmann Government Operations Consultant Beach Management Funding Assistance Program Office of Resilience and Coastal Protection 2600 Blair Stone Road Tallahassee, FL 32399

TASK 1

Atkins will meet with the DEP contract manager and other RCP staff involved with AP management plans to discuss scope of the report document and determine the interview questions (about 3-7 questions). Following the meeting, Atkins will develop the interview questions and submit to RCP for review.

� Deliverable: Interview questions for the AP and BP managers and list of managers and field staff proposed for interviews.

� Completion Date: One month after NTP

TASK 2

Atkins will conduct interviews with AP, BP, and NERR managers using the questions developed in Task 1. The goal of the interviews is to identify the potential impacts of SLR and determine potential adaptation strategies/related initiatives within the managers’ areas. It is expected 1 - 3 staff per region will be interviewed at one time with at least one interviewee being an AP manager.

� Deliverables: Answers and notes from interviews with AP, BP, and NERR staff and managers.

� Completion Date: Three and a half months after NTP

TASK 3

Atkins will develop a report outline using the information gathered from the interviews with the AP, BP, and NERR managers and submit to RCP staff for review and approval.

� Deliverable: Report outline

� Completion Date: One month following completion of Task 2

TASK 4

On approval of the report outline, Atkins will prepare a draft report. The regional portions of the document will be submitted to the AP, BP and NERR staff interviewed for their review. The draft report will be submitted to the contract manager and other RCP staff identified for their review and feedback.

� Deliverable: Draft report. List of AP and BP reviewers along with their feedback.

List of RCP reviewers with their feedback.

� Completion Date: 30 days after receiving all feedback from AP and BP managers

TASK 5

Final report document, incorporating feedback from AP, BP, and NERR managers that was received in Task 4 reviews. Final PDF document would need to be ADA compliant to DEP specifications

� Deliverable: Final report PDF document, in ADA compliant format

� Completion Date: One month after completion of Task 4

PROJECT COSTS AND DELIVERABLES

All deliverables will be digital and submitted in either Word or PDF format and are outlined in the Table below. The not to exceed project cost is $28,325.02 and is summarized by subtasks below. The task order is proposed on a lump sum basis and invoices will be prepared on a project percent complete basis. Attached is a breakdown of costs by labor hours and rates.

Table 1 Project Deliverables

Deliverable Due Date Cost Task 1: Coordination with

FCMP

1 month after NTP

3.5 months after NTPTask 2: Manager Interviews Task 3: Report Outline 4.5 months after NTP Task 4: Draft Report with Managers Reviews

1 month after receiving manager feedback

Task 5: Final Report 1 month following completion of Task 4 Total

PROJECT SCHEDULE

The schedule described in the request for proposal is based on time from contract award and will be between six and seven months, depending on AP and BP staff availability for interviews, report review and feedback. A tentative schedule is provided below assuming an October start date. The proposed scope of work will begin immediately upon notice to proceed.

Table 2 Proposed Project Schedule

We hope this scope and fee meets with your approval. Should you have any questions or require any additional information please do not hesitate to contact me at your earliest convenience at 850.580.7947 or lizbeth.childs@atkinsglobal.com.

Sincerely, Lizbeth Childs Project Manager, Coastal Engineering

Resource Distribution & Billing Schedule Scheduled Finish Period Oct'20 Nov'20 Dec'20 Jan'21 Feb'21 Mar'21 Apr'21

Task ID WBS/Task Name Labor Hrs Duration

1 2 3 4 5 6 7

01 Kick off meeting with client 1

02 Interveiws 3

03 Report outline 1

04 Draft report 1

05 Final Report 3

Total 10

$9,606.27

$ 9,206.45 $ 1,521.79

$ 1,747.64

$ 6,242.87

$28,325.02

9.0

37.0

9.0

51.5

52.5

159.0

9.0

6.00 25.00 6.00

9.00

51.50

10.00 33.00 9.50

33 9.551.502515 15

Staff

HRS.

Cost by

Pos & Act Staff HRS.

Cost by Pos &

Act Staff HRS.

Cost by Pos &

Act Staff HRS.

Cost by Pos &

Act Staff

HRS.

Cost by Pos &

Act Staff HRS.

Cost by Pos &

Act Staff HR

ACTIVITY

COST BY ACTIVITY

1 0.0 $0.00 1.5 $443.43 1.0 $266.00 3.0 $370.98 3.0 $602.49 0.5 $64.74 9.0 $1747.64

2 0.0 $0.00 2.0 $591.24 0.0 $0.00 16.0 $1978.56 17.0 $3414.11 2 $258.96 37.0 $6242.87

3 0.5 $147.37 0.5 $147.81 0.0 $0.00 4.0 $494.64 3.0 $602.49 1.0 $129.48 9.0 $1521.79

4 0.5 $147.37 6.0 $1,773.72 1.0 $266.00 18.0 $2,225.88 20.0 $4,016.60 6 $776.88 51.5 $9,206.45

5 1.0 $294.73 4.0 $1,182.48 0.5 $133.00 15.0 $1,854.90 28.0 $5,623.24 4 $517.92 52.5 $9,606.27

2.00 $589.47 14.0 $4,138.68 2.50 $665.00 56.0 $6,924.96 71.0 $14,258.93 13.50 $1,747.98 0.00 159.00 $28,325.02

$294.73

$295.62

$266.00

$123.66

$200.83

$129.48

Engineer II

Sr Scientist III

Sr Scientist I

Lump Sum Total

FDEP Contract Rates

Project Director

Sr Project Manager

Sr Engineer IV

Kick-Off Mtg

Interviews

Report outline

Draft report

Final Report

Table 1: Revised Fee Breakdown for Lump Sum Assignment

Florida Department of Environmental Protection (FDEP)

LUMP SUM FEE ESTIMATE BREAKDOWN

ACTIVITY DESCRIPTION Project Director Sr Project Manager Sr Engineer IV Engineer II Sr Scientist III Sr Scientist I Reimbursable

Expenses

TOTAL

TA2 AP Management Plans - SLR Generator Addition Initial Evaluation

Professional Services Contract - Contract No. BS136

Professional Services: "Engineering Services"

Change Order 1 - SLR
BS136 Task Assignment 2 - Revised Scope
Table 1 Revised Man hour estimate SLR - v2

File details come from the government source that posted it. Updated .