CEP_Fire_Pump_Test_Method Of Procedure 06-02-16.pdf

PDF 393 KB Posted

Attached to
C1NZ--Design Build Project: 629-20-118 CFM - Redesign and Repair Fire and Jockey Pump Systems
Solicitation number
36C25621R0026
Issued by

View the file

Other files

File Type Posted
Sprinkler - CEP - 3 Standpipes.pdf PDF
CEP_L01_ALL_FP_NS_FAB.pdf PDF
CEP_L02_ALL_FP_NS_FAB.pdf PDF
Section 01 33 23.docx DOCX document
CEP_L03_ALL_FP_NS_FAB.pdf PDF
CEP_L02_ALL_FP_NS_FAB.pdf PDF
CEP_ 3 Standpipes_Sprinkler.pdf PDF
VA PUMP 2 FIELD TEST REPORT.pdf PDF
CEP_L04-5_ALL_FP_NS_FAB.pdf PDF
Section 01 00 00.docx DOCX document
Section 01 35 26.docx DOCX document
CEP_L04_ALL_FP_NS_FAB.pdf PDF
CEP_L01_ALL_FP_NS_FAB.pdf PDF
4. VA Master Specs Table of Contents.docx DOCX document
CEP_L03-5_ALL_FP_NS_FAB.pdf PDF
Section 01 32 16_15.docx DOCX document
015-7FX301.pdf PDF
016-7FX302.pdf PDF
36C25621R0026_1.docx DOCX document
VA PUMP 1 field test report.pdf PDF
Section 00 11 21.docx DOCX document
General Decision LA 20200041 10-09-2020.pdf PDF
EXHIBIT A CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY.pdf PDF
017-7FX501.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

V.A. N.O.

Method Of Procedure

Rev 1.0

Section 01 MOP Information

MOP Title: Fire Pump Test

Creation Date: 6/02/2016 MOP

Revision

Date:

6/02/2016 MOP

Author:

Bryan Haas

Section 02

Site information

Customer(Company)Name:

VA

Address:

Street Address:

City: State: Zip Code:

LOR Class:

Site Point of

Contact:

Name:

Bill Monahan Email:

william.monahan@clarkconstruction.com

Phone:

Contractor: Name: CMHP Email:bryan.haas@clarkconstruction.com Phone: (504)252-5893

Section 03

MOP Overview

Brief overview/

Work Area:

Systems Affected: Campus Fire Suppression / Standpipe

Systems

Equipment

Information:

Manufacturer:

METRON

Type:

Model #:

MP300-125-46-MTS

Name:

Equipment ID#:

FP#1 & FP#2 (Controllers)

Special Tools/Materials/Personnel

Required:

Section 04 MOP Effect

MOP Effect on Critical Facility

1) Electrical Utility Equipment: NO

2) Emergency Generator System: NO

3) Critical Cooling System: NO

4) Critical Power Distribution System: NO

5) Building Monitoring System: NO

6) Lockout/Tag out Required? NO

7) FIRE ALARM SYSTEM: YES

- F.A. SYS. Must be called into test prior to start of Fire Pump Test.

Section 05 MOP Documents

MOP Documents

1) List of references:

- FPP Field Pump Test Documents

- Certified Pump Curve sheets

- Fire Pump Isometric FP-02 Marked-Up to reflect Method of Procedure steps. Attached.

- Fire Alarm System TEST mode – Method of Procedure. Attached.

Rev 1.0

Section 06 MOP Safety

MOP Safety Requirements

1) Need 10ft. ladder to remain in Fire Pump room at all times. Ladder is required to reach Test Main Valve to

Level 1.

2) Ear protection should be worn during testing.

Section 07 MOP Risks &

Assumptions

Risks and Assumptions

Section 08

MOP Details Detailed Procedure

Initial Conditions:

1. Fire Pump controller is monitored by the Fire Alarm system which is monitored by the Remote Operations Center.

1a. Prior to the start of any Fire Pump TEST or Service the Fire Alarm system needs to be called into TEST mode. Please see attached M.O.P. for contact info for that procedure.

Expected /Nominal Performed

Operation

Test Procedure:

1. After receiving confirmation from the VA that the Fire Alarm system is in TEST mode, CLOSE the (2) OS&Y Gate Valves directly behind the Fire Pump

Controllers. This will isolate the CEP standpipes from the Fire Pump pressure during testing. See marked-up Isometric for reference.

2. OPEN Control Valves at the 8in. Main Return pipe to the Fire Water Tank. This will assure water returns to the Fire Water Tank during Fire Pump Testing. See attached Isometric drawing for reference.

No other valves need be cycled for testing.

3. To initiate Fire Pump test, press the “TEST” button on Fire Pump Controller

“FP-1” and allow timed test to complete.

Once complete, press the “TEST” button on Fire Pump Controller “FP-2” and allow timed test to complete.

TEST IS COMPLETE. MOVE ON TO BACK OUT PROCEDURE.

Rev 1.0

Back-out Procedure

1. CLOSE Control Valves at the 8in. Main Return pipe to the Fire Water Tank.

This will assure that after testing Fire Pump discharge water does NOT go to the tank.

Check

2. OPEN the (2) OS&Y Gate Valves directly behind the Fire Pump Controllers.

This will OPEN the CEP standpipes back up to the Fire Pump pressure after testing.

3. Call VA contact and report Fire Pump testing has completed and ask the Fire Alarm system be taken out of TEST mode.

NOTE: If the above described valves are NOT returned to their original positions the Fire Alarm system will immediately report a supervisory condition on the Tamper Switches related to those valves. So it is important to verify. There is a chain hung sign on each valve noting the original intended valve position.

End of Procedure brhaas Snapshot