CEP_Fire_Pump_Test_Method Of Procedure 06-02-16.pdf
PDF 393 KB Posted
- Attached to
- C1NZ--Design Build Project: 629-20-118 CFM - Redesign and Repair Fire and Jockey Pump Systems
- Solicitation number
- 36C25621R0026
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sprinkler - CEP - 3 Standpipes.pdf | ||
| CEP_L01_ALL_FP_NS_FAB.pdf | ||
| CEP_L02_ALL_FP_NS_FAB.pdf | ||
| Section 01 33 23.docx | DOCX document | |
| CEP_L03_ALL_FP_NS_FAB.pdf | ||
| CEP_L02_ALL_FP_NS_FAB.pdf | ||
| CEP_ 3 Standpipes_Sprinkler.pdf | ||
| VA PUMP 2 FIELD TEST REPORT.pdf | ||
| CEP_L04-5_ALL_FP_NS_FAB.pdf | ||
| Section 01 00 00.docx | DOCX document | |
| Section 01 35 26.docx | DOCX document | |
| CEP_L04_ALL_FP_NS_FAB.pdf | ||
| CEP_L01_ALL_FP_NS_FAB.pdf | ||
| 4. VA Master Specs Table of Contents.docx | DOCX document | |
| CEP_L03-5_ALL_FP_NS_FAB.pdf | ||
| Section 01 32 16_15.docx | DOCX document | |
| 015-7FX301.pdf | ||
| 016-7FX302.pdf | ||
| 36C25621R0026_1.docx | DOCX document | |
| VA PUMP 1 field test report.pdf | ||
| Section 00 11 21.docx | DOCX document | |
| General Decision LA 20200041 10-09-2020.pdf | ||
| EXHIBIT A CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY.pdf | ||
| 017-7FX501.pdf |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
V.A. N.O.
Method Of Procedure
Rev 1.0
Section 01 MOP Information
MOP Title: Fire Pump Test
Creation Date: 6/02/2016 MOP
Revision
Date:
6/02/2016 MOP
Author:
Bryan Haas
Section 02
Site information
Customer(Company)Name:
VA
Address:
Street Address:
City: State: Zip Code:
LOR Class:
Site Point of
Contact:
Name:
Bill Monahan Email:
william.monahan@clarkconstruction.com
Phone:
Contractor: Name: CMHP Email:bryan.haas@clarkconstruction.com Phone: (504)252-5893
Section 03
MOP Overview
Brief overview/
Work Area:
Systems Affected: Campus Fire Suppression / Standpipe
Systems
Equipment
Information:
Manufacturer:
METRON
Type:
Model #:
MP300-125-46-MTS
Name:
Equipment ID#:
FP#1 & FP#2 (Controllers)
Special Tools/Materials/Personnel
Required:
Section 04 MOP Effect
MOP Effect on Critical Facility
1) Electrical Utility Equipment: NO
2) Emergency Generator System: NO
3) Critical Cooling System: NO
4) Critical Power Distribution System: NO
5) Building Monitoring System: NO
6) Lockout/Tag out Required? NO
7) FIRE ALARM SYSTEM: YES
- F.A. SYS. Must be called into test prior to start of Fire Pump Test.
Section 05 MOP Documents
MOP Documents
1) List of references:
- FPP Field Pump Test Documents
- Certified Pump Curve sheets
- Fire Pump Isometric FP-02 Marked-Up to reflect Method of Procedure steps. Attached.
- Fire Alarm System TEST mode – Method of Procedure. Attached.
Rev 1.0
Section 06 MOP Safety
MOP Safety Requirements
1) Need 10ft. ladder to remain in Fire Pump room at all times. Ladder is required to reach Test Main Valve to
Level 1.
2) Ear protection should be worn during testing.
Section 07 MOP Risks &
Assumptions
Risks and Assumptions
Section 08
MOP Details Detailed Procedure
Initial Conditions:
1. Fire Pump controller is monitored by the Fire Alarm system which is monitored by the Remote Operations Center.
1a. Prior to the start of any Fire Pump TEST or Service the Fire Alarm system needs to be called into TEST mode. Please see attached M.O.P. for contact info for that procedure.
Expected /Nominal Performed
Operation
Test Procedure:
1. After receiving confirmation from the VA that the Fire Alarm system is in TEST mode, CLOSE the (2) OS&Y Gate Valves directly behind the Fire Pump
Controllers. This will isolate the CEP standpipes from the Fire Pump pressure during testing. See marked-up Isometric for reference.
2. OPEN Control Valves at the 8in. Main Return pipe to the Fire Water Tank. This will assure water returns to the Fire Water Tank during Fire Pump Testing. See attached Isometric drawing for reference.
No other valves need be cycled for testing.
3. To initiate Fire Pump test, press the “TEST” button on Fire Pump Controller
“FP-1” and allow timed test to complete.
Once complete, press the “TEST” button on Fire Pump Controller “FP-2” and allow timed test to complete.
TEST IS COMPLETE. MOVE ON TO BACK OUT PROCEDURE.
Rev 1.0
Back-out Procedure
1. CLOSE Control Valves at the 8in. Main Return pipe to the Fire Water Tank.
This will assure that after testing Fire Pump discharge water does NOT go to the tank.
Check
2. OPEN the (2) OS&Y Gate Valves directly behind the Fire Pump Controllers.
This will OPEN the CEP standpipes back up to the Fire Pump pressure after testing.
3. Call VA contact and report Fire Pump testing has completed and ask the Fire Alarm system be taken out of TEST mode.
NOTE: If the above described valves are NOT returned to their original positions the Fire Alarm system will immediately report a supervisory condition on the Tamper Switches related to those valves. So it is important to verify. There is a chain hung sign on each valve noting the original intended valve position.
End of Procedure brhaas Snapshot
File details come from the government source that posted it. Updated .