About this file

This is a Purchase Requisition document from the Orange County Transportation Authority (OCTA) for Public Outreach consultant services on the State Route 55 Improvement Project between Interstate 5 and State Route 91. The procurement seeks to onboard a consultant to provide public outreach services during the preconstruction and construction phases of the project. The contract includes an initial five-year term with a three-year option term. The requisition was entered on June 25, 2026, with a due date of December 1, 2026, and construction is slated to commence in February 2027. Angela Hui serves as the Project Manager for this procurement.

The total budget for the initial five-year term is $2,359,750.00, with annual allocations as follows: $2,359,750.00 for Fiscal Year 2026-27, $300,000 for FY 2027-28, $617,500 for FY 2028-29, $617,500 for FY 2029-30, $482,750 for FY 2030-31, $236,000 for FY 2031-32, and $106,000 for FY 2032-33. The option term is valued at $300,000. This procurement is not grant-funded and does not require Department IS involvement. The requisition has been authorized and is proceeding through OCTA's standard procurement process.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Is Dept Involved

Budget Year Fiscal Year Encumbered Grant Funded

Warehouse

IS INVOLVEMENT - NOT REQUIRED

GRANT FUNDED - NO

N Fiscal Year 26-27

Kathy HoR002288 CE 06/03/2026ANGELA HUI $2,359,750.00Veronica Garcia 06/04/2026

***** PURCHASE REQUISITION REPRINT *****

OCTA PRD

Run On: 2026/06/25 PR8001Report:

Michael CardozoRun. By: 1Page:

- - - - - -- - - - - - - - - - - - - - Authorized - - - - - - - - - - - - - -- - - - - -

TBD

Auth. By

V99999 Supplier:

Auth. ValueAuth.Date

Purchasing Question

FOB

Purchasing Instructions

Project Manager Date ReqdDate EnteredSec CdRequested ByReq No

Due Date: December 1, 2026 – Construction is slated for February 2027. Onboarding a consultant.

Actual PriceOrder NoDescriptionItem UOM Estimated PriceQty

$2,359,750.000001 EA Initiate a new procurement for Public Outreach consultant services for2,359,750.001 the SR-55 (I-5 to SR-91) project for the preconstruction and construction phases. Five (5)-year initial term with three

(3)-year option term.

Initial Term: $2,359,750

Option Term: $300,000

FY26-27 $300,000

FY27-28 $617,500

FY28-29 $617,500

FY29-30 $482,750

FY30-31 $236,000

FY31-32 $106,000

PM: Angela Hui ext 5648

%100.000017 7519 FF102 TYP

PR8001Jun 25,2026 R002288 Report:

Run. By: Michael Cardozo Req No Page: 1

Run On:

PR8001Jun 25,2026 R002288 Report:

Run. By: Michael Cardozo Req No Page: 2

Run On:

File details come from the government source that posted it. Updated .