C250435_PS.doc

DOC document 48 KB Posted

Attached to
Public Outreach Services for the State Route 55 Improvement Project between Interstate 5 and State Route 91
Solicitation number
250435
Issued by
Orange County, California

About this file

This is a procurement schedule document from the Orange County Transportation Authority (OCTA) for RFP 250435, which solicits qualified consultants to provide public outreach services for the State Route 55 Improvement Project between Interstate 5 and State Route 91. The RFP was approved for release on July 27, 2026, and advertised on July 27 and August 3, 2026. A pre-proposal conference is scheduled for August 4, 2026, at 8:30 a.m., available in-person or virtually. Written questions from proposers are due by August 5, 2026, with OCTA's responses provided by August 11, 2026. Proposal submissions are due by 2:00 p.m. on August 25, 2026, followed by a pre-evaluation meeting at 4:00 p.m. the same day. Evaluation committee reviews are scheduled for September 8, 2026, from 1:00 p.m. to 3:00 p.m., with interviews on September 16, 2026, from 9:00 a.m. to 4:00 p.m. Board approval of the selected consultant is anticipated on November 9, 2027, with contract execution by December 1, 2027. The contract term is five years.

The budget for this public outreach services project is $2,359,750.00 for the five-year initial term. The procurement schedule indicates a comprehensive internal review process involving multiple staff reports and approvals through various OCTA departments and committees before final board approval and contract execution.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

June 26, 2026 To:

Angela Hui, Community Relations Specialist, Principal, Public Outreach

From:

Michael Cardozo, Senior Contract Administrator, CAMM Subject:

Procurement Schedule for Release, Selection and Award

RFP 250435 “State Route 55 Improvement Project

Between Interstate 5 and State Route 91 Public Outreach Consultant Support"

Please review the time schedule for the subject RFP. If you have a problem with any of the dates or timelines let me know as soon as possible.

June 23, 2026
Staff Report for Release to CAMM from Project Manager
July 7, 2026
Draft Staff Report to release to PM
July 13, 2026
To CEO from PM
July 27, 2026
Board Approval - Issue RFP

July 27 and August 3, 2026

Advertise

August 4, 2026
Pre-Proposal Conference (in-person/virtual) 8:30 a.m. – Room 08
August 5, 2026
Written Questions due from proposers
August 11, 2026
OCTA’s response to proposers

August 25, 2026

Offers submitted by 2:00 p.m.

August 25, 2026
Pre-Evaluation Meeting 4:00 p.m.

September 8, 2026

Evaluation Committee Reviews Proposals

1:00 p.m. – 3:00 p.m.

September 16, 2026
Interviews

9:00 a.m. – 4:00 p.m.

September 16, 2026
Staff Report to Project Manager, PM to write Procurement Approach

October 6, 2026

CAMM staff report review meeting (Thursday Meeting)

October 12, 2026
Staff Report to Executive Director
October 19, 2026
Staff Report to CEO
October 26, 2027
Staff Report to COB
November 2, 2027
RTPLegislative and Communications Committee
November 9, 2027
BOD Approves Selection
December 1 2027
Contract Executed

Project Manager Concurrence:

Angela Hui, Community Relations Specialist, Principal, Public Outreach

Date Revised: 3/20/2019