C250282_SOWV.pdf
PDF 247 KB Posted
- Solicitation number
- 250282
- Issued by
- Orange County, California
About this file
This is a Scope of Work Verification form submitted by the Orange County Transportation Authority (OCTA) in California for a Compressed Natural Gas (CNG) Fueling Facility Operation and Maintenance project. The project, identified as Requisition No. 001563, seeks qualified contractors to provide comprehensive operation and maintenance services for a CNG fueling station. The contract is structured as a three-year initial term with a total budget of $2,181,165.00. The scope of work verification was completed and signed by the Maintenance department on February 4, 2026, certifying that the solicitation documents were independently prepared to invite fair competition without bias toward any specific vendor or brand product.
The form confirms that the project will be funded through Federal Transit Administration (FTA) funds in accordance with FTA Circular 4220.1F regulations. The project manager's department verified that the scope of work provides clear and concise specifications identifying all characteristics and specific tasks required for the CNG fueling facility services, while allowing for evaluation of equivalent alternative proposals. The verification process ensures compliance with procurement standards that promote competitive bidding, efficient operations, and cost-effective service delivery by utilizing industry and government-recognized specifications and requirements.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK VERIFICATION
This Form Must Be Submitted with Scope of Work (SOW)
FA-CAMM-071.docm (05/16/16) Page 1 of 1
The following general rules shall apply when preparing scopes of work and specifications:
a) Provide a clear and concise Scope of Work (SOW) and not impose unreasonable requirements.
b) Specifications and Scopes of Work shall identify all characteristics and specific tasks and functions of the items or services to be procured, and meet the Authority’s requirements.
c) Whenever possible, the expected quality of services to be provided or the performance characteristics of the item shall be specified.
d) The requestor shall identify all optional items, and the solicitation documents shall set forth the expected needs and the manner in which the related bid prices will be considered.
e) Brand name specifications must be accompanied by an explanation that clearly indicates that the specification is not intended to be restrictive.
f) The salient characteristics represented by the brand names shall be identified to allow for evaluation of possible “or equal” material.
g) Because standard specifications and requirements allow for more efficient operations and result in lower prices, they shall be used wherever suitable.
h) Industry, federal, state and local government specifications and requirements can be used.
Consultants are prohibited from writing the Scope of Work or assisting in the development or writing the Scope of Work in which they may bid.
INSTRUCTIONS
Project Managers (PM) must select one of the following certifications and submit this form with the scope of work/specifications. This form must be signed by the Project Manager and one of the following: the PM’s Department Manager or Director or Executive Director.
Project Description: CNG Fueling Facility O&M Requisition No: 001563 o I certify that the attached SOW/specifications was independently prepared to invite competition;
does not include reference to a brand name, or include unreasonable restrictions or an intent to favor any specific vendor or brand product.
OR
o The SOW/specifications prepared includes a “brand name or equal” description because it was determined to be “impractical or uneconomical” (as referenced in FTA Circular 4220.1F -revised March 18, 2013) to write a clear and accurate description of the technical requirements of the goods or services to be acquired. However, the specific features or salient characteristics of the named brand which must be met by offerors of “an equal” proposal have been clearly stated, as required by Federal Transit Administration regulations. (FTA Circular 4220.1F – revised March 18, 2013)
Project Manager Signature Dept. Manager/Director/Executive Director Signature
Maintenance (MRM) 02/04/2026 Department Date