C250131_PS.pdf

PDF 132 KB Posted

Attached to
Los Angeles 2028 Olympics Transportation Service Plan and Capital Needs Assessment
Solicitation number
250131
Issued by
Orange County, California

About this file

This is an interoffice procurement schedule memorandum from the Orange County Transportation Authority (OCTA) to manage the release, selection, and award process for RFP 250131 regarding the Los Angeles 2028 Olympics Transportation Service Plan and Capital Needs Assessment. The RFP was issued on January 14, 2026, with advertisement occurring on January 13 and 20, 2026. A pre-proposal conference is scheduled for January 21, 2026, at 11:00 a.m. in both in-person and virtual formats. Written questions from proposers are due by January 28, 2026, with OCTA's responses provided by February 4, 2026. Proposal submissions are due by 2:00 p.m. on February 11, 2026, followed by a pre-evaluation meeting at 4:00 p.m. the same day. Proposal evaluation by the Evaluation Committee is scheduled for February 24, 2026, from 9:00 a.m. to 3:00 p.m., with interviews occurring on March 3, 2026, during the same hours. Best and Final Offers (BAFOs) are due by March 10, 2026, as needed. The contract is anticipated to be executed by May 1, 2026, following approval by the Board of Directors on April 13, 2026.

The project is funded through the Federal Transit Administration with a total budget of $950,000 for a twenty-month contract term. This procurement seeks qualified consultants to develop a comprehensive transportation framework, service plan, and capital needs assessment in preparation for the 2028 Summer Olympic and Paralympic Games in Los Angeles. The schedule includes multiple approval stages, including CAMM staff report review on March 19, 2026, staff reports to the CEO on March 23, 2026, and to the Chief Operating Officer on March 30, 2026, before Executive Committee consideration on April 6, 2026, and final Board of Directors approval on April 13, 2026.

View the file

Other files

File Type Posted
Los_Angeles_2028_Olympics_Transportation_Service_Plan_and_Capital_Needs_Assessment_(Addendum_#3_Revision).pdf PDF
C250131_PP-APPROVED.pdf PDF
C250131_Exhibit_C_Proposed_Agreement.pdf PDF
C250131_Exhibit_B_Price_Summary_Sheet.pdf PDF
C250131_Exhibit_C_Proposed_Agreement_GMEDITS.pdf PDF
C250131_PP-APPROVED_GMEDITS.pdf PDF
C250131_PP.pdf PDF
C250131_Exhibit_A_SOW.pdf PDF
C250131_Exhibit_B_Price_Summary_Sheet_gmedits.pdf PDF
C250131_Exhibit_A_SOW_gmedits.pdf PDF
los_angeles_2028_olympics_planning-2026-01-14-00-30-02_GMEDITS.docx DOCX document
C250131_Insurance_Approval_Response_12-29-25.pdf PDF
C250131_Email_PM_Federalized_12-30-25.pdf PDF
C250131_PS_idedits.doc DOC document
C250131_PP_idedits.docx DOCX document
C250131_Exhibit_D_Level_1_Safety_Specifications_Rev_8.pdf PDF
C250131_Insurance_Approval_Response_12-29-25_idedits.pdf PDF
[C]_C250131_Exhibit_C_Proposed_Agreement_idedits.docx DOCX document
[B]_C250131_Exhibit_B_Price_Summary_Sheet_idedits.docx DOCX document
[A]_C250131_Exhibit_A_SOW_idedits.docx DOCX document
C250131_Public_Notice_Proof.pdf PDF
C250131_Public_Notice.doc DOC document
C250131_SOW_Verification.pdf PDF
C250131_R000889.pdf PDF
C250131_ICE_R000889.pdf PDF
C250131_Form_700_Legal_Counsel_Response_12-16-25.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised: 3/20/2019

INTEROFFICE MEMO

January 14, 2026

To: Charles Main, Section Manager III, Transit Service Planning

From: Gina Torres, Senior Contract Administrator, CAMM

Subject: Procurement Schedule for Release, Selection and Award

RFP 250131 "Los Angeles 2028 Olympics Transportation Service Plan and Capital Needs Assessment"

Please review the time schedule for the subject RFP. If you have a problem with any of the dates or timelines let me know as soon as possible.

January 14, 2026 Issue RFP

January 13 & 20, 2026

Advertise

January 21, 2026 Pre-Proposal Conference (in-person/virtual) 11:00 a.m. – Room 08 Tentative

January 28, 2026 Written Questions due from proposers

February 4, 2026 OCTA’s response to proposers

February 11, 2026

Offers submitted by 2:00 p.m.

February 11, 2026 Pre-Evaluation Meeting 4:00 p.m.

February 24, 2026

Evaluation Committee Reviews Proposals 9:00 a.m. – 3:00 p.m.

March 3, 2026 Interviews 9:00 a.m. – 3:00 p.m.

March 3, 2026 Staff Report to CAMM from Project Manager

March 10, 2026 BAFOs Due (as needed)

March 19, 2026

CAMM staff report review meeting (Thursday Meeting)

March 19, 2026 Staff Report with Procurement Approach to Project Manager

March 23, 2026 Staff Report to CEO

March 30, 2026 Staff Report to COB

April 6, 2026 Executive Committee

April 13, 2026 BOD Approves Selection

May 1, 2026 Contract Executed

Project Manager Concurrence:

Charles Main, Section Manager III, Transit Service Planning Date