This is an interoffice procurement schedule memorandum from the Orange County Transportation Authority (OCTA) to manage the release, selection, and award process for RFP 250131 regarding the Los Angeles 2028 Olympics Transportation Service Plan and Capital Needs Assessment. The RFP was issued on January 14, 2026, with advertisement occurring on January 13 and 20, 2026. A pre-proposal conference is scheduled for January 21, 2026, at 11:00 a.m. in both in-person and virtual formats. Written questions from proposers are due by January 28, 2026, with OCTA's responses provided by February 4, 2026. Proposal submissions are due by 2:00 p.m. on February 11, 2026, followed by a pre-evaluation meeting at 4:00 p.m. the same day. Proposal evaluation by the Evaluation Committee is scheduled for February 24, 2026, from 9:00 a.m. to 3:00 p.m., with interviews occurring on March 3, 2026, during the same hours. Best and Final Offers (BAFOs) are due by March 10, 2026, as needed. The contract is anticipated to be executed by May 1, 2026, following approval by the Board of Directors on April 13, 2026.
The project is funded through the Federal Transit Administration with a total budget of $950,000 for a twenty-month contract term. This procurement seeks qualified consultants to develop a comprehensive transportation framework, service plan, and capital needs assessment in preparation for the 2028 Summer Olympic and Paralympic Games in Los Angeles. The schedule includes multiple approval stages, including CAMM staff report review on March 19, 2026, staff reports to the CEO on March 23, 2026, and to the Chief Operating Officer on March 30, 2026, before Executive Committee consideration on April 6, 2026, and final Board of Directors approval on April 13, 2026.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised: 3/20/2019
INTEROFFICE MEMO
January 14, 2026
To: Charles Main, Section Manager III, Transit Service Planning
From: Gina Torres, Senior Contract Administrator, CAMM
Subject: Procurement Schedule for Release, Selection and Award
RFP 250131 "Los Angeles 2028 Olympics Transportation Service Plan and Capital Needs Assessment"
Please review the time schedule for the subject RFP. If you have a problem with any of the dates or timelines let me know as soon as possible.
January 14, 2026 Issue RFP
January 13 & 20, 2026
Advertise
January 21, 2026 Pre-Proposal Conference (in-person/virtual) 11:00 a.m. – Room 08 Tentative
January 28, 2026 Written Questions due from proposers
February 4, 2026 OCTA’s response to proposers
February 11, 2026
Offers submitted by 2:00 p.m.
February 11, 2026 Pre-Evaluation Meeting 4:00 p.m.
February 24, 2026
Evaluation Committee Reviews Proposals 9:00 a.m. – 3:00 p.m.
March 3, 2026 Interviews 9:00 a.m. – 3:00 p.m.
March 3, 2026 Staff Report to CAMM from Project Manager
March 10, 2026 BAFOs Due (as needed)
March 19, 2026
CAMM staff report review meeting (Thursday Meeting)
March 19, 2026 Staff Report with Procurement Approach to Project Manager
March 23, 2026 Staff Report to CEO
March 30, 2026 Staff Report to COB
April 6, 2026 Executive Committee
April 13, 2026 BOD Approves Selection
May 1, 2026 Contract Executed
Project Manager Concurrence:
Charles Main, Section Manager III, Transit Service Planning Date