This is an Interoffice Memo from the Orange County Transportation Authority (OCTA) dated January 11, 2026, documenting the procurement plan for RFP 250131 regarding Los Angeles 2028 Olympics Planning. The RFP seeks qualified consultants to develop Olympic-related foundational strategy and planning for transit services in preparation for the 2028 Summer Olympic and Paralympic Games in Los Angeles. The procurement is structured as a Request for Proposals rather than an Invitation for Bids, as the selection requires evaluation criteria beyond price. The contract term is twenty (20) months with no renewal options indicated.

The contract is structured as a time-and-expense agreement with a total budget of $950,000, selected because firms will propose fully-burdened hourly rates and anticipated expenses rather than fixed prices due to the absence of a detailed Scope of Work. The evaluation criteria are weighted as follows: Qualifications of the Firm (20%), Staffing/Project Organization (25%), Work Plan (30%), and Cost (25%). The contract includes prevailing wage requirements and liquidated damages provisions. Funding sources include Local Measure M, STGB, STIP, and PPM, with a note that Federal Transit Administration funding may be applied during the agreement term. The evaluation team consists of five members: four internal evaluators from OCTA (Gina Torres, Charles Main, Greg Nord, Matt Ankley, and Laura Gillette) and one external evaluator (Rafael Cobian from the City of Anaheim). An independent cost estimate has been received, and requisition number R000889 has been assigned. A DBE goal applies to this procurement.

View the file

Other files

File Type Posted
Los_Angeles_2028_Olympics_Transportation_Service_Plan_and_Capital_Needs_Assessment_(Addendum_#3_Revision).pdf PDF
C250131_PP-APPROVED.pdf PDF
C250131_Exhibit_C_Proposed_Agreement.pdf PDF
C250131_Exhibit_B_Price_Summary_Sheet.pdf PDF
C250131_Exhibit_C_Proposed_Agreement_GMEDITS.pdf PDF
C250131_PS.pdf PDF
C250131_PP.pdf PDF
C250131_Exhibit_A_SOW.pdf PDF
C250131_Exhibit_B_Price_Summary_Sheet_gmedits.pdf PDF
C250131_Exhibit_A_SOW_gmedits.pdf PDF
los_angeles_2028_olympics_planning-2026-01-14-00-30-02_GMEDITS.docx DOCX document
C250131_Insurance_Approval_Response_12-29-25.pdf PDF
C250131_Email_PM_Federalized_12-30-25.pdf PDF
C250131_PS_idedits.doc DOC document
C250131_PP_idedits.docx DOCX document
C250131_Exhibit_D_Level_1_Safety_Specifications_Rev_8.pdf PDF
C250131_Insurance_Approval_Response_12-29-25_idedits.pdf PDF
[C]_C250131_Exhibit_C_Proposed_Agreement_idedits.docx DOCX document
[B]_C250131_Exhibit_B_Price_Summary_Sheet_idedits.docx DOCX document
[A]_C250131_Exhibit_A_SOW_idedits.docx DOCX document
C250131_Public_Notice_Proof.pdf PDF
C250131_Public_Notice.doc DOC document
C250131_SOW_Verification.pdf PDF
C250131_R000889.pdf PDF
C250131_ICE_R000889.pdf PDF
C250131_Form_700_Legal_Counsel_Response_12-16-25.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised: 07/20/2010

INTEROFFICE MEMO

Date: January 11, 2026

To: Charles Main, Section Manager III, Transit Service Planning

From: Gina Torres, Senior Contract Administrator, CAMM

Subject: Procurement Schedule for Release, Selection and Award RFP 250131 "Los Angeles 2028 Olympics Planning"

Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.

Procurement Type: RFP IFB

Justification (explain the rationale for using the particular procurement type):

A Request for Proposals (RFP) was issued as the nature of the procurement demands that evaluation criteria, in addition to price, be used to select a firm to provide Olympic-related foundational strategy and planning transit services.

Evaluation Criteria:

PROPOSAL WEIGHT

Qualifications of the Firm 20%

Staffing/Project Organization 25%

Work Plan 30%

Cost 25%

Justification: The standard 25 percent for each criterion was not used in this procurement. Several factors were considered in developing the weights.

Qualifications of the firm is weighted at 20 percent to ensure the firm has prior experience providing transportation services. Staffing and project organization is weighted at 25 percent to ensure the proposed staff have expertise in completing the work required. Staff proposed assigning the greatest importance to work plan as the firm must demonstrate its approach to planning, strategizing, and implementing Olympic-related transit services. Cost is weighted at 25 percent to ensure OCTA receives the best value for the service provided.

Contract Type: Time & Expense CTO-Based Firm Fixed Price

Justification (Explain the rationale for using the particular contract type): The contract type is time-and-expense because firms are requested to propose fully-burdened hourly rates and anticipated expenses for the work specified in the Scope of Work. The RFP does not have a specific Scope of Work detailing individual tasks.

Therefore, a firm-fixed price contract cannot be used.

Retention: Yes % No N/A

Georgia Martinez Comment on Text title needs to match title on scope of work

Procurement Plan, RFP 250131

Revised: 0720/2010

Prevailing Wages: Yes $ No N/A

Liquidated Damages: Yes $ No N/A

P.M. to provide support documentation identifying how the LD amount was established.

Procurement Schedule: Attached

Suggested Evaluation Team Members:

5 members are required over $500k

Internal Evaluators:

Gina Torres, Senior Contract Administrator, CAMM

Charles Main, Section Manager III, Transit Service Planning

Greg Nord, Department Manager, Planning & Analysis

Matt Ankley, Department Manager, Security & Emergency Prepardness

Laura Gillette, Schedule Analyst, Schedule and Bus Operations Support

External Evaluator:

Rafael Cobian, T.E., LEED GA, City Traffic Engineer, City of Anaheim

Contract Term: Twenty (20)-month term

Funding Source: Local Measure M STGB STIP PPM

Dollar Amount: Term $950,000

Independent Cost Estimate Received: Yes No

Requisition Received: Yes # R000889 No

DBE Goal: Yes No

Project Manager Concurrence:

Charles Main, Section Manager III, Transit Service Planning Date

CAMM Section/Department Manager Concurrence:

Iris Deneau, Section Manager, Procurement Date

1/12/26

Georgia Martinez Comment on Text You need to include FTA as a funding source with a note stating that per the pm there may be federal funding applied during the term of the agreement.

Georgia Martinez Comment on Text has this person taken the evaluation committee training?

gtorres Sticky Note She is working with Iris to complete evaluation training before evaluations are due.

File details come from the government source that posted it. Updated .