Business_Case_-_North_ARFF_Kitchen_Rehabilitation.pdf
PDF 197 KB Posted
- Attached to
- North ARFF Station 2 Kitchen Remodel
- Solicitation number
- 26-043-ITB
- Issued by
- Bell County, Kentucky
About this file
This is a Business Case document and associated state and local contract opportunity for the Kenton County Airport Board (KCAB) in Kentucky involving the North ARFF Station 2 Kitchen Rehabilitation project. The project scope encompasses the complete redesign and remodeling of the kitchen and dining areas at North ARFF Station 2, including replacement of cabinets, appliances, plumbing, lighting, and painting, with associated mechanical, electrical, and plumbing (MEP) work to address deficiencies identified in the 2024 NARFF Facility Assessment. A pre-bid meeting and site visit will be held on Thursday, July 30, 2026 at 10:00 am at North ARFF Station 2, 81 Clay Drive, Hebron, Kentucky 41048. Questions must be submitted by 11:59 pm on Monday, August 10, 2026, with answers posted no later than Thursday, August 13, 2026 at 11:59 pm. Bids are due by Thursday, August 20, 2026 at 2:00 pm, with no bids accepted after that time unless extended by KCAB addendum. The project is scheduled for contract negotiation finalization and notice to proceed in Q1 2026, with design completion targeted for Q2 2026 and construction completion by May 26, 2026.
The total appropriations request for the project is $622,500.00, consisting of $500,000.00 for construction and installation, $50,000.00 for design, $55,000.00 for construction administration and inspection, $16,500.00 for contingency, and $1,000.00 for force labor. Design cost estimates are 80 percent certain based on comparable budgets for similar kitchen rehabilitation projects. The project is funded through CAPEX project funding and addresses critical infrastructure needs including the correction of an improperly sloped existing kitchen drain line that causes frequent backups and the removal of the garbage disposal. The primary business objective is to provide North ARFF firefighter occupants with a safe, comfortable, and clean space for mealtime activities while reducing future maintenance repairs and increasing kitchen functionality. The project will be executed through engagement with an on-call design provider for design and construction services.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Master Plan Alignment
Strategic Plan Alignment
Sustainability Benefits
$50,000.00
$500,000.00
Construction Admin & Construction Inspection (CA/CI) $0.00
$55,000.00
$16,500.00
$1,000.00
$622,500.00
January 28, 2026
Q1 2026
Q1 2026
May 26,2026
Q2 2026
Q2 2026
Contract Negotiation Finalized
Notice to Proceed (after contract is signed)
Known Risks & Limitations
None
Alternatives
Do nothing, and wait on a larger design project to address the issues at North ARFF
Total Appropriations Request:
Related Projects
The HVAC system is currently being repaired with a new coil and condenser to mitigate HVAC issues from the past few years
Fuel Performance via Operational Excellence: Ensure the safety and health of passengers and employees
Organizational Impact Justification
Cost
Design:
Construction/Installation:
Contingency (min 10%):
Force Labor:
Business Objectives: Provide North ARFF Firefighter occupants with a safe, comfortable, clean space to conduct mealtime activity
Project Value/ROI: Reduced maintenance repairs, and increased functionality of the kitchen at North ARFF
Organizational Impact
Project Approach
Work with our on-call design provider to redesign and construct the North ARFF kitchen, dining areas, lighting, painting, appliances, and associated MEP
Risk if Not Funded: North ARFF will continue to deteriorate and repairs will escalate
North ARFF Kitchen Rehabilitation PMWeb #
Current Situation/Background Information
The kitchen at North ARFF Station 2 requires a complete rehabilitation, including replacement of cabinets, appliances, and plumbing. The existing kitchen drain line is improperly sloped, resulting in frequent backups. Due to the misaligned drain line beneath the floor, the garbage disposal had to be removed. In addition, the kitchen and dining areas, lighting, and painting spaces should be redesigned and remodeled to address deficiencies.
Project Definition
Project Scope: Redesign and remodel the kitchen and dining areas, lighting, and painting spaces to correct deficiencies identified in the 2024 NARFF Facility
Assessment
Certainty of Cost Estimates
Design estimates are 80% based on a comparable budget to rehabilitate the kitchen area, cabinets and associated MEP
Design/Construction Completion
Project Schedule
Appropriations Approval
Procurement (Bid/Solicitation) Completion
Board Meeting
CAPEX
Project Funding
Miscellaneous:
ARFF Human Resources
Business Administration Information Technology
Capital Accounting Innovation
Commercial Management Operations
Customer Experience Planning & Development
Environmental, Social & Governance (ESG) Police Department
Facilities Procurement
Field Safety
Finance Terminal Modernization Program
Fleet Other ________________________________________________
Visuals
Approvals:
Larry Krauter
Chief Executive Officer
Dil Gruffydd
Chief Financial Officer
Executive Sponsor
Shannon Oldfield
Chief Operations Officer
Concurrence Leader
Steve Listerman
Vice President Public Safety, Security & Compliance
Engage with on-call to design and construct the rehabilitation of the North ARFF kitchen
Recommendation
Stakeholders
Business Unit Leader
Bill Siemer
Vice President Planning & Development
Sponsor/Originator
Eric Rysdon
Director Engineering Construction Management