BID 2024-103 Submittal Sheet Apparent Low.pdf

PDF 184 KB Posted

Attached to
BID# 2024-103 Monroe Street Improvements
Solicitation number
S-C01010-00011990
Issued by
Benton County, Mission CDP, Oregon

About this file

This is a bid submittal sheet from Clackamas County for BID #2024-103 SE Monroe Street Improvements project. Eight construction companies submitted bids by the deadline of December 4, 2024, at 2:00 PM PT. The bids were received between 12:51 PM and 1:57 PM on the submittal date, with all bidders providing required certification sheets and bid bonds.

Corpac Construction Company was identified as the apparent low bidder with a bid amount of $7,418,501.00, followed by Tapani, Inc. at $7,497,446.00. The remaining bids ranged from $7,992,000.00 to $8,586,401.00, submitted by Pacific Excavation, K&E Excavating, Goodfellow Bros, Kerr Contractors Oregon, Westech Construction, and Moore Excavation. All bidders met the basic submission requirements, including signed certification sheets and bid bonds, though none submitted first tier sub lists at the time of bid opening.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID #2024-103 - SE Monroe Street Improvements SUBMITTAL DEADLINE: December 4, 2024, 2:00 PM PT

Apparent Low Bidder: __Corpac Construction Company____ Bid Amount:__$7,418,501.00_________________________

Opened on _12/4/2024 at 2:00PM______________

Tralee Whitley, Contract Analyst

Signature Date

Name Date/Time Received BID Amount Certification Sheet Signed

Bid Bond Included

First Tier Sub List

1. Corpac Construction Company

12/4/24 at 12:51 $ 7,418,501.00 Yes No Yes No Yes No

2. Kerr Contractors Oregon

12/4/24 at 12:53 $ 8,540,095.00 Yes No Yes No Yes No

3. Westech Construction

12/4/24 at 13:19 $ 8,547,000.00 Yes No Yes No Yes No

4. Goodfellow Bros

12/4/24 at 13:21 $ 8,511,159.00 Yes No Yes No Yes No

5. Pacific Excavation

12/4/24 at 13:33 $ 7,992,000.00 Yes No Yes No Yes No

6. K&E Excavating

12/4/24 at 13:55 $ 8,141,175.00 Yes No Yes No Yes No

7. Tapani, Inc

12/4/24 at 13:56 $ 7,497,446.00 Yes No Yes No Yes No

8. Moore Excavation

12/4/24 at 13:57 $ 8,586,401.00 Yes No Yes No Yes No

12/4/2024

File details come from the government source that posted it. Updated .