About this file

This document is a Past Performance Questionnaire for a federal contract opportunity related to fire suppression installation at Fort Vancouver National Historic Site. The questionnaire is designed to capture detailed performance evaluations across multiple assessment areas including quality, schedule management, cost control, project management, small business subcontracting, and regulatory compliance. The document is part of Solicitation 140P8424R0013, with a return deadline of July 2, 2025, and is issued by the National Park Service - Point Reyes MABO.

The questionnaire provides a comprehensive evaluation framework with ratings ranging from Unsatisfactory to Exceptional, covering key performance dimensions such as workmanship quality, timely project milestone completion, cost management, subcontractor coordination, safety compliance, and adherence to labor standards. The document allows the reference contact to provide granular feedback on the contractor's performance, with specific rating categories for each evaluation area and opportunities for supplementary comments. The completed questionnaire will be used as source selection information for assessing the contractor's past performance capabilities for similar future contracts.

View the file

Other files for this federal contract opportunity

Other files attached to Fort Vancouver NHS INSTALL FIRE SUPPRESSION, newest first.
File Type Posted
Sol_140P8325R0013_Amd_0003.pdf PDF
B09_Questions_for_140P8325R0013_Forth_Vancouver_NHS_Install_Fire_Suppression_Install_0003.docx DOCX document
Building_Descriptions_FOVA_Fire_Sprinkler_Att_2-AMENDED_(2)_0003.docx DOCX document
Fort_Vancouver_-_Bldg_722_Administration-_INSP_2024_0003.pdf PDF
FAS_ITM_Bldg_733_Jan_2017_0003.pdf PDF
Fort_Vancouver_-_Bldg_721_Auditorium___Gym_-_INSP_2024_0003.pdf PDF
Fort_Vancouver_-_Bldg_704_Project_Office-_INSP_2024_0003.pdf PDF
Sol_140P8325R0013_Amd_0002.pdf PDF
Sol_140P8325R0013_Amd_0001.pdf PDF
A07_FOVA_Fire_Sprinkler_Att_2_Plans_attachment_4-AMENDED_0001.pdf PDF
_FOVA_Fire_Sprinkler_Att_2-AMENDED_0001.docx DOCX document
B11__Site_Walk_Attendance_0001.jpg JPG image
Sol_140P8325R0013.pdf PDF
A07_FOVA_Fire_Sprinkler_Att_2_Plans_attachment_4.pdf PDF
B03_WA20250120_05_23_2025_SAM_attacment_6.pdf PDF
A07_FOVA_Fire_Sprinkler_Att_1_Plans_attachment_3.pdf PDF
B08_Offeror_s_representations_and_certificates_to_be_provided_with_proposal_Attachment_11.pdf PDF
B08_Relevant_Project_Experience_Questionnaire_attachment_9.docx DOCX document
A06_FOVA_Fire_Sprinkler_Att_2_attachment_2.docx DOCX document
A03_-_Construction_Contract_Administration_attachment___7.docx DOCX document
B08_Limitations_on_Subcontracting_Worksheet_Attchment_10.xlsx XLSX spreadsheet
A04_FOVA_Fire_Sprinkler_SOW_attachment_1.docx DOCX document
B08_ContractPriceSchedule_attachment_5.xlsx XLSX spreadsheet
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation: 140P8424R0013 Offeror Company Name: _________________________________

PAST PERFORMANCE QUESTIONNAIRE

INSTRUCTIONS: Offeror to complete Sections A and B and transmit questionnaire to reference.

Reference to complete Sections C and D and transmit back to Contracting Officer listed in section E.

Notice to Contractor

Information provided in this questionnaire is intended for use as source selection information and as such is deemed Source Selection Sensitive. Statements or comments provided in the questionnaire do not signify an express or implied endorsement of any product, supply, service, or enterprise.

This information shall not be construed as an endorsement by the Government or its employee(s) of the contractor for advertising purposes or in a manner that implies the contractor, its products, or services, are approved, endorsed, or considered by the Government to be superior to other products or services.

The contractor shall not be permitted to use any information provided in this questionnaire to publicize, or otherwise circulate, promotional materials that state or imply Governmental, organizational, group, expert, or individual endorsement or consumer testimonial of a product, service, or position which the contractor represents.

A. CONTRACTOR INFORMATION (check one) ☐company listed above ☐ proposed sub for company listed above

Company Name
Company
Street Address
Address
City
City
State
State
Zip Code
XXXXX
UEI Number
XXXXXXX
Point of Contact
Name, Email, Phone

B. CONTRACT INFORMATION

Project Title
Title
Contract Number
XXXXXXXXXX
Contract Type
Firm Fixed Price / Time & Materials / Cost Reimbursable / Other
Awarded Contract Price
$X,XXX,XXX
Current / Final Price
$X,XXX,XXX
Contract Award Date
XX/XX/XXXX
Contract Completion Date
XX/XX/XXXX
Period of Performance
XX/XX/XXX – XX/XX/XXX
Project Location
Park or Street address, City, State
Client / Owner
Company
Brief description of the contract & work effort:
Scope of work description

C. REFERENCE:

Name
First, Last
Position / Title
Title
Organization
Agency or Company
Phone Number
XXX-XXX-XXXX
Email Address
Email
Signature
Signature
Date
XX/XX/XXXX

D. EVALUATION

Rating
Definition
Exceptional
Performance met contractual requirements and exceeded many to the owner’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance met contractual requirements and exceeded some to the owner’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance met contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance did not meet some contractual requirements. The element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Evaluation Area
Rating

Quality

Quality of workmanship (including subcontractors)?
Choose an item.
Quality of and adherence to quality control plan?
Choose an item.
Quality of informational and technical submittals?
Choose an item.
Overall Quality Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Schedule (& Time Management)

Met project schedule milestones?
Choose an item.
Responded to owner requests in a timely manner?
Choose an item.
Informational and technical submittals submitted timely?
Choose an item.
Promptly addressed scheduling issues?
Choose an item.
Overall Schedule (& Time Management) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Cost Control

Addressed differing & unforeseen site conditions so as to minimize additional costs?
Choose an item.
Provided fair and reasonable pricing for contract modifications?
Choose an item.
Submitted accurate and complete invoices?
Choose an item.
Promptly paid subcontractors and suppliers?
Choose an item.
Overall Cost Control Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Management

General oversight by project manager and superintendent?
Choose an item.
Coordination with and control of subcontractors?
Choose an item.
Avoidance of accidents & safety violations?
Choose an item.
Addressed location factors (especially remote locations)?
Choose an item.
Maintained good working relationship with owner representatives?
Choose an item.
Demonstrated flexibility, innovativeness and cooperation in resolving potential problems?
Choose an item.
Overall Management Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Small Business Subcontracting (& Labor Standards)

Met regulatory and contractual labor standards?
Choose an item.
Successfully contracted with small and socio-economically disadvantaged businesses?
Choose an item.
Quality and adherence to applicable subcontracting plans?
Choose an item.
Overall Small Business Subcontracting (& Labor Standards) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Regulatory Compliance

Met building and life safety codes?
Choose an item.
Overall Regulatory Compliance Rating
Choose an item.
Overall Recommendation:
Given what I know today about the contractor's ability to perform in accordance with the contract’s most significant requirements, I would recommend them for similar contracts:
Choose an item.
Overall Comments:

E. RETURN:

Return by
NOON p.m. Pacific Daylight Time on July 2,2025
Name
Geri Larsen
Title
Contracting Officer
Organization
National Park Service – Point Reyes MABO
Email
Geraldine_larsen@ps.gov