About this file

This is a DD Form 1423-1, Contract Data Requirements List (CDRL), which specifies data deliverables required under a federal contract. The form documents a single data item (B002) for the BECS SETA for PSC contract with contractor TBD. The required deliverable is an Engineering Data Package containing System Design Documents, categorized as "OTHER" rather than a Technical Data Package or Technical Manual.

The data item is governed by authority DI-SESS-82166 and references BECS SETA for PSC PWS, Paragraph 6.1.2. The requiring office is PD BECS. The contractor must prepare System Design Documents in accordance with DI-SESS-82166 or the most recently approved version, ensuring technical soundness, logical organization, coherence, and freedom from typographical and grammatical errors. Content requirements reference PWS Paragraph 6.1.2, with several sections of DI-SESS-82166 deemed not applicable. The final electronic copy must include signature blocks for PD BECS. Distribution requires one copy each to PD BECS and PD BECS Cyber. Submissions include a draft electronic document due 60 days after approved Architectural Modernization Plan and a final electronic document due 90 days after approval. Draft and final copies are provided via DoD-SAFE. The form was prepared on 18 MAR 26. No pricing information or frequency of subsequent submissions is specified.

View the file

Other files

File Type Posted
B08 - W15P7T-27-R-A001 - Attachment 0006- Cost Price Proposal Workbook_Final.xlsx XLSX spreadsheet
Attachment 0007-RFP Industry- BECS Q_A Sheet_Rev16Sep26.xlsx XLSX spreadsheet
B08 - W15P7T-27-R-A001 - Attachment 0001 - PWS - SETA PSC _19Aug2026__Rev01.pdf PDF
W15P7T-27-R-A001- FINAL RFP - SETA PSC_20Aug2026_ Rev01.docx DOCX document
W15P7T-26-R-SETA - Attachment 0007-RFP Industry- BECS Q_A Sheet_04Sep2026.xlsx XLSX spreadsheet
B08 - W15P7T-27-R-A001 - Attachment 0001 - Draft PWS - SETA PSC _19Aug2026_Tracked_Rev01.docx DOCX document
W15P7T-27-R-A001- DRAFT RFP - SETA PSC_20Aug2026_ Rev01.docx DOCX document
B08 - W15P7T-27-R-A001 - Attachment 0005 - Corporate Experience Information Form_Rev01.docx DOCX document
B08 - W15P7T-27-R-A001 - Attachment 0001 - Draft PWS - SETA PSC _19Aug2026_Final..docx DOCX document
B08 - W15P7T-27-R-A001 - Attachment 0001 - Draft PWS - SETA PSC _19Aug2026_Final.pdf PDF
B08 - W15P7T-27-R-A001 - Attachment 0001 - Draft PWS - SETA PSC _19Aug2026_Final.docx DOCX document
B08 - W15P7T-27-R-A001 -Attachment 0001 -PWS - SETA PSC_19Aug2026_Final..pdf PDF
B08 - W15P7T-27-R-A001 - Attachment 0006- Cost Price Proposal Workbook_Final.xlsx XLSX spreadsheet
B08-CDRL G001_Contractor Travel_BECS SETA.pdf PDF
B08-CDRL E003 Asset Database Synchronization_SETA for PSC.pdf PDF
B08-CDRL B003 Architectural Modernization Plan_ SETA for PSC.pdf PDF
B08 - W15P7T-27-R-A001 - Attachment 0007- RFP Industry Question Sheet_Final.xlsx XLSX spreadsheet
B08 - W15P7T-27-R-A001 - Attachment 0002 - Quality Assurance Surveillance Plan_Final.pdf PDF
B08 - W15P7T-27-R-A001 - Attachment 0001 - PWS - SETA PSC _19Aug2026_Final.pdf PDF
A03-CDRL G002_Non-Disclosure Agreement (NDA)_BECS SETA.pdf PDF
B08-CDRL E001 Asset Database Entries_ BECS SETA.pdf PDF
B08-CDRL A002_POAMs_BECS SETA.pdf PDF
B08 - W15P7T-27-R-A001 - Attachment 0004 - Organizational Conflict of Interest (OCI)_Final.docx DOCX document
B08 - W15P7T-27-R-A001 - Attachment 0003 - Performance Assessment Questionnaire _Signature Page.pdf PDF
B08 - W15P7T-27-R-A001- DRAFT RFP - SETA PSC_20Aug2026_ Final.pdf PDF
B08-CDRL E002 Asset Database Updates_ BECS SETA.pdf PDF
B08 - W15P7T-27-R-A001 - Attachment 0003 - Performance Assessment Questionnaire _Final.docx DOCX document
B08-CDRL F001_Monthly Invoice_BECS SETA.pdf PDF
B08-CDRL D002 Cybersecurity Assessment Reports_BECS SETA.pdf PDF
B08-CDRL D001 Integration and Testing Plans_BECS SETA.pdf PDF
B08-CDRL B001 ECPs_SETA for PSC.pdf PDF
B08-CDRL A004_Quarterly Program Management Reviews (QPMRs)_BECS SETA.pdf PDF
B08-CDRL A003_Risk Management Plan (RMP)_BECS SETA.pdf PDF
B08-CDRL A001_Monthly Progress Report_SETA for PSC.pdf PDF
B08 - W15P7T-27-R-A001 - Attachment 0006- Cost Price Proposal Workbook_Final.xlsx XLSX spreadsheet
B08 - W15P7T-27-R-A001 - Attachment 0005 - Corporate Experience Information Form_Final.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

G. PREPARED BY

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER

Form Approved OMB No. 0704-0188

15. TOTAL

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

DIST

22202-4302.

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page of Pages

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

DD FORM 1423-1, FEB 2001 Page of Pages

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package;

TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR GOVERNMENT PERSONNEL

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data. These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

FOR THE CONTRACTOR

DD FORM 1423-1 (BACK), FEB 2001

1_DATA_ITEM_NO: B002
2_TITLE_OF_DATA_ITEM: Engineering Data Package
3_SUBTITLE: System Design Documents
4_AUTHORITY_Data_Acquisit: DI-SESS-82166
5_CONTRACT_REFERENCE: BECS SETA for PSC PWS, Para. 6.1.2
6_REQUIRING_OFFICE: PD BECS
7_DID_250_REQ: N/A
8_APP_CODE: N/A
10_FREQUENCY: SEE ITEM 16
12_DATE_OF_FIRST_SUBMISSI: SEE ITEM 16
13_DATE_OF_SUBSEQUENT_SUB: SEE ITEM 16
DIST_STATEMENT: D
11_AS_OF_DATE: SEE ITEM 16
addressee1: PD BECS
draft1: 1
reg1: 1
repro1:
draft2: 1
addressee2: PD BECS Cyber
reg2: 1
repro2:
addressee3:
draft3:
reg3:
repro3:
addressee4:
draft4:
reg4:
repro4:
addressee5:
draft5:
reg5:
repro5:
addressee6:
draft6:
reg6:
repro6:
addressee7:
draft7:
reg7:
repro7:
addressee8:
draft8:
reg8:
repro8:
addressee9:
draft9:
reg9:
repro9:
addressee10:
draft10:
reg10:
repro10:
addressee11:
addressee12:
addressee13:
addressee14:
addressee15:
addressee16:
addressee17:
addressee18:
addressee19:
addressee20:
addressee29:
addressee30:
draft20:
draft19:
draft18:
draft17:
draft16:
draft15:
draft14:
draft13:
draft12:
draft11:
draft29:
draft30:
reg11:
reg12:
reg13:
reg14:
reg15:
reg16:
reg17:
reg18:
reg19:
reg20:
reg29:
reg30:
repro11:
repro12:
repro13:
repro14:
repro15:
repro16:
repro17:
repro18:
repro19:
repro20:
repro29:
repro30:
addressee21:
draft21:
reg21:
repro21:
addressee22:
draft22:
reg22:
repro22:
addressee23:
draft23:
reg23:
repro23:
addressee24:
draft24:
reg24:
repro24:
addressee25:
draft25:
reg25:
repro25:
addressee26:
draft26:
reg26:
repro26:
addressee27:
draft27:
reg27:
repro27:
addressee28:
draft28:
reg28:
repro28:
addressee31:
addressee32:
addressee33:
addressee34:
addressee35:
addressee36:
addressee37:
addressee38:
draft31:
reg31:
repro31:
draft32:
draft33:
draft34:
draft35:
draft36:
draft37:
reg32:
reg33:
reg34:
reg35:
reg36:
reg37:
repro32:
repro33:
repro34:
repro35:
repro36:
repro37:
draft38:
repro38:
total_draft: 2
total_repro: 0
16_REMARKS: The Contractor shall prepare System Design Documents in accordance with DI-SESS-82166 or the most recently approved version.

Content:

1. Provide System Design Documents that are technically sound, logically organized, coherent, and free of typographical and grammatical errors.

2. The Contractor shall refer to PWS Paragraph 6.1.2 for content to address in the appropriate sections of DI-SESS-82166.

3. DI-SESS-82166 Sections 3.b.2, 3.b.3, 3.b.6, 3.b.8, 3.b.11, and 3.b.14 are not applicable.

4. The final electronic copy will have a signature page with signature blocs for PD BECS.

Dist Statement Required:

"CUI"

Date of Submissions: (Blocks 12 and 13)

1. The Contractor shall submit a draft electronic System Design Document 60 days after approved Architectural Modernization Plan.

2. The Contractor shall submit a final electronic System Design Document 90 days after approved Architectural Modernization Plan.

Block 14:

1. Draft and final copies will be provided via DoD-SAFE.

A_CONTRACT_LINE_ITEM_NO: B002
B_EXHIBIT: B
TDP:
TM:
OTHER: X
DSYSTEMITEM: BECS SETA for PSC
E_CONTRACTPR_NO: TBD
FCONTRACTOR: TBD
16_REMARKS_Continued:
of_pages:
Reset:
Page2:
ADN:
send_to:
17_1:
17_b:
17_c:
17_d:
17_PRICE_GROUP:
ESTIMATED_TOTAL_PRICE:
H_DATE: 18 MAR 26
J_DATE:
Page:
reg38x:
reg38t: 2
title:

File details come from the government source that posted it. Updated .