This document outlines technical performance standards for maintenance, repair, and logistics support services required under the solicitation for Federal Contract Opportunity W519TC-23-R-0104 at Presidio of Monterey, CA. Key requirements include establishing and managing equipment repair shops to process lateral transfers and perform technical inspections per regulations. The contractor must perform repairs according to work requests and technical manuals, meeting minimum rejection rates of 97% for mechanical work and 98% for electrical work. Additional requirements involve tire maintenance and repair, wheel alignment support, physical security of arms rooms and sensitive items, shop supply services using automated Army supply systems, managing standard pricing items, operating a production control capability to manage the maintenance workload, and providing preventative, scheduled, and unscheduled repair services for food service equipment per technical manuals and manufacturer instructions. Response times for unscheduled food service equipment maintenance must be within 24 hours of notification.

View the file

Other files

File Type Posted
B08 Attachment 0030 Government Responses to Industry (19MAR2024) -Final.xlsx XLSX spreadsheet
W519TC23R0104-0002_Signed.pdf PDF
W519TC-23-R-0104 Conformed Copy.pdf PDF
W519TC23R0104-0001_SIGNED.pdf PDF
B08 Attachment 0030 Government Responses to Industry (8MAR24) -Final.xlsx XLSX spreadsheet
B08 Attachment 0011 - Contract References Spreadsheet (04MAR24).xlsx XLSX spreadsheet
B08 Attachment 0001 - EAGLE PPI 2.0 PWS POM (07MAR24).pdf PDF
B08 Attachment 0005 - Cost-Price Matrix (POM) (29FEB24).xlsx XLSX spreadsheet
B08 Exhibit B - Contract Data Requirements List (29Feb24) PoM.xlsx XLSX spreadsheet
B08 Exhibit K - SS-01 Supply and Services Report Format updated 19 Jan 24.xlsx XLSX spreadsheet
B08 Exhibit J - PM-12 KTR Accident Reporting Format.xlsx XLSX spreadsheet
B08 Attachment 0011 - Contract References Spreadsheet 04JAN2024.xlsx XLSX spreadsheet
B08 Attachment 0013 - Mission Essential EAGLE Contractor Services for Presidio of Monterey.pdf PDF
B08 Attachment 0025 - PWS-Annex D - Environmental Requirements.docx DOCX document
B08 Attachment 0026 - PWS-Annex E Definitions Acronyms and Abbreviations.docx DOCX document
B08 Attachment 0027 - PWS-Annex F - Publications and Forms.docx DOCX document
B08 Attachment 0023 - PWS-Annex B - Supply PRS-PoM (1).docx DOCX document
B08 Attachment 0005 - Cost-Price Matrix (POM).xlsx XLSX spreadsheet
B08_W519TC23R0104_Presidio RFP_Final _Signed.pdf PDF
B08 Attachment 0015 - Subcontractor Cost Information Submission 08JAN2024.pdf PDF
B08 Attachment 0001 - EAGLE PPI 2.0 PWS POM 6FEB24.pdf PDF
B08 Attachment 0003 - Performance Questionnaire_04JAN2024.pdf PDF
B08 Exhibit H - PM-09 Performance Management Review Format (version 5-01-23).pptx PPTX presentation
B08 Attachment 0002 - Staffing and Labor Mix PoM.xlsx XLSX spreadsheet
B08 Attachment 0014 -NOT APPLICABLE.pdf PDF
B08 Exhibit C - CD-02 Burn Rate Report Format (1).xlsx XLSX spreadsheet
B08 Exhibit D - ITD-01 Transportation Report Format.xlsx XLSX spreadsheet
B08 Exhibit A - DD1423-1 DTA for PoM.pdf PDF
B08 Exhibit B - CDRL Listing PoM.xlsx XLSX spreadsheet
B08 Attachment 0006 - Preaward Survey of Prospective Contractor Accounting System SF 1408.pdf PDF
B08 Attachment 0028 - PWS-Annex G - Government Property Incidental.docx DOCX document
B08 Attachment 0024 - PWS-Annex C - Transportation PRS-PoM (1).docx DOCX document
B08 Exhibit F - PM-01 Contractor Employee Information Format (1).xlsx XLSX spreadsheet
B08 Attachment 0004 - Letter of Consent 04JAN2024.docx DOCX document
B08 Exhibit G- PM-08 - PoM Scheduled Government Furnished Property (version 20240213).xlsx XLSX spreadsheet
B08 Attachment 0029 - Appendix A - Non-ASC Customer (DLIFLC).docx DOCX document
B08 Attachment 0007 - Department of Labor Wage (2015-5633).pdf PDF
B08 Attachment 0010 - Blocked File Extensions.pdf PDF
B08 Exhibit E - MMD-01 Maintenance Report Format (1).xlsx XLSX spreadsheet
B08 Attachment 0009 - Purchasing Invoicing Guide (PIG) 04JAN2024.docx DOCX document
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Annex A – Maintenance PRS

Task/Requirement
Standard
Sampling Method, Lot & Acceptable Quality Level (AQL)

MATERIEL MAINTENANCE – GENERAL

5.1.1 Establish, operate, and manage equipment repair shops, and supporting functions.

Quality: Lateral transfers processed IAW local directives, AR 710-2, DA PAM 710-2-1 and ISM Operating Manual.

Random sampling (shop/activity scheduled periodically)

Lot: All in-process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL: 95%

5.1.4 Perform technical inspections in accordance with the maintenance request.

Quality: IAW AR 750-1, DA PAM 750-8, applicable LIS publications, installation policies and procedures, external and internal SOPs, and materiel maintenance (COR) guidance.

Random (shop/activity scheduled periodically)

Lot: All in-process and completed work orders, files, logs, and SOPs at time of surveillance.

MATERIEL MAINTENANCE – PROGRAMS/EFFORTS

5.2.1 Perform repairs IAW work request and applicable equipment TMs or equivalent publications.

Quality: Repairs will be IAW the maintenance request and to standards, to include estimated task times, as stated in current equipment Technical Manuals (TMs), Technical Bulletins (TBs), Modification Work Orders (MWOs), Safety of Use Messages (SOUMs), Special Technical Inspection and Repairs (STIRs), other applicable Government technical publications, or OEM equivalent publications when a Government technical publication is not available.

Random sampling

Lot: All in-process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

5.2.1 Ensure minimum rejection rates for mechanical and electrical repair work completed are met in order to meet first time pass rates.

Quality: IAW AR 750-1, Appendix B-11, paragraphs (a-d) Random (shop/activity scheduled periodically)

Lot: Equipment that has completed the repair cycle and has been deemed as ready for issue (RFI) back to the customer.

AQL: 97% for mechanical AQL: 98% for electrical

MATERIEL MAINTENANCE SUPPORT

5.3.8 Maintain, repair, and replace tires on rims.

Quality: IAW TM 9-2610-200-14 Random (shop/activity scheduled periodically)

Lot: The number of line items on receipts processed on the day of surveillance.

5.3.9 Provide wheel alignment support.

Quality: IAW applicable TMs and standards.

Random (shop/activity scheduled periodically)

Lot: All in process and completed work related to replacing front axle components (tie-rod/sway bar).

5.3.11 Maintain physical security of the Material Maintenance Arms room and sensitive items.

Timeliness: Notify the COR immediately of the discovery of a missing sensitive item or major administrative discrepancy.

Quality: IAW AR 190-11, AR 710-2, AR 750-1, DA PAM 750-8, and local SOPs.

Random (shop/activity scheduled periodically)

Lot: All in process and completed sensitive item work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL: 100%

REPAIR PARTS AND MATERIEL MANAGEMENT TASKS

5.5.1 Perform shop supply services; use the automated Army supply system as the primary means of attaining materiel.

Quality: IAW AR 750-1, AR 710-2, DA PAM 25-30, AR 725-50, DA PAM 710-2-2; AR 740-1; AR 735-5; AR 710-1; AR 710-3; DA Pam 710-7; AR 710-3, DA Pam 710-2-1; FEDLOG; and LIS user’s manual Random (shop/activity scheduled periodically)

Lot: All in-process and completed work orders, requisitions, requests, files, records, SOPs, and stockage at time of surveillance.

AQL: 95%

5.5.6 Manage Standard Pricing (SP) items.

Timeliness: Meet SP turn- in criteria for timeliness of turn-ins.

Quality: IAW DFAS-IN Reg 37-1 Chapter 13, finance & accounting policy, implementation, unserviceable turn-ins, and current army guidance.

Periodic

Lot: The numbers of SP items processed during the period at time of surveillance.

PRODUCTION CONTROL

5.6.1 Operate a production control capability that effectively manages the maintenance workload; provide personnel technically capable of performing all tasks found in the applicable maintenance LIS End User Manual. Operate multiple equipment receiving points; provide order statuses.

Timeliness: Work completed IAW time estimates given at work induction.

Quality: IAW work request, AR 750-1, DA PAM 750-1, DA PAM 750-8, applicable LIS publications, local policies and procedures.

Random

Lot: All in process and completed work as well as all existing logs and files at time of surveillance

AQL 95%

FOOD SERVICE EQUIPMENT

5.7.1 Provide preventive, scheduled, and unscheduled repair services.

Quality: IAW Density list Bi-Weekly

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL:90%

5.7.2 Perform inspections, services, and maintenance.

Quality: IAW applicable technical manual / manufacturer's instructions.

Random

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL: 90%

5.7.3 Provide unscheduled maintenance.

Timeliness: Unscheduled maintenance service calls are responded to within 24 hours or 1 business day of notification from DFAC maintenance POC.

Random

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

5.7.4 Utilizing ODCs to perform maintenance tasks.

Quality: ODCs approved by DFAC Manager are utilized when contractor does not possess a unique skillset needed to complete a repair/service.

Random

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.