This document provides the prevailing wage determination for a federal building construction project in Klamath County, Oregon. The wage determination specifies the required minimum hourly wages for various construction occupations such as electricians at $38.49, plumbers and pipefitters at $47.43, and truck drivers ranging from $29.33 to $30.24 depending on vehicle size. It also lists applicable fringe benefits for each occupation. The related federal contract opportunity is for structural deficiencies corrections and stabilization of a steel visitor center under solicitation number 140P2020R0158 issued by the National Park Service, Department of the Interior.
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
"General Decision Number: OR20210040 02/12/2021
Superseded General Decision Number: OR20200040
State: Oregon
Construction Type: Building
County: Klamath County in Oregon.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis‐Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above‐mentioned types of contracts entered into by the federal government that are subject to the Davis‐Bacon Act itself, but it does not apply to contracts subject only to the Davis‐Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)‐(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/01/2021 1 02/12/2021
BROR0001‐018 06/01/2020
Rates Fringes
BRICKLAYER.......................$ 41.20 22.39
TILE FINISHER....................$ 26.94 14.94
TILE SETTER......................$ 35.35 20.42
CARP0001‐032 06/01/2020
Rates Fringes
Carpenters:
Including Metal stud installation and form work..$ 41.75 18.30
CARP9001‐004 06/01/2020
Rates Fringes
Acoustical Ceiling Installer & Drywall Hanger.................$ 42.04 18.01
* ELEC0659‐012 01/01/2021
Rates Fringes
ELECTRICIAN......................$ 38.49 17.74
* ELEC0659‐016 01/01/2021
Rates Fringes
ELECTRICIAN
Low voltage for computers...$ 16.00 3%+10.65 Low Voltage Wiring for Alarms......................$ 31.06 14.23
ENGI0701‐027 01/01/2020
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 45.90 15.35
GROUP 1A....................$ 48.06 15.35
GROUP 1B....................$ 50.22 15.35
GROUP 2.....................$ 43.99 15.35
GROUP 3.....................$ 42.84 15.35
GROUP 4.....................$ 41.01 15.35
GROUP 5.....................$ 39.77 15.35
GROUP 6.....................$ 36.55 15.35
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: CRANE: Helicopter Operator, when used in erecting work; Whirley Operator, 90 ton and over; LATTICE BOOM CRANE: Operator 200 tons through 299 tons, and/or over 200 feet boom; HYDRAULIC CRANE: Hydraulic Crane Operator 90 tons through 199 tons with luffing or tower attachments
GROUP 1A: HYDRAULIC CRANE: Hydraulic Operator, 200 tons and over (with luffing or tower attachment); LATTICE BOOM CRANE: Operator, 200 tons through 299 tons, with over 200 feet boom;
GROUP 1B: LATTICE BOOM CRANE: Operator, 300 tons through 399 tons with over 200 feet boom; Operator 400 tons and over
GROUP 2: CRANE: Cableway Operator, 25 tons and over;
HYDRAULIC CRANE: Hydraulic crane operator 90 tons through 199 tons (without luffing or tower attachment);
TOWER/WHIRLEY OPERATOR: Tower Crane Operator; Whirley Operator, under 90 tons; LATTICE BOOM CRANE: 90 through 199 tons and/or 150 to 200 feet boom; HYDRAULIC CRANE:
Hydraulic crane operator, 50 tons through 89 tons (with luffing or tower attachment); BLADE: Auto Grader;Blade Operator‐Robotic; Bulldozer: Over 120,000 lbs and above;
Bulldozer: D‐10, D‐11 and similar type; Loader: 120,000 lbs and above; Excavator: over 130,000 lbs and above
GROUP 3: HYDRAULIC CRANE: Hydraulic crane operator, 50 tons through 89 tons (without luffing or tower attachment);
LATTICE BOOM CRANES: Lattice Boom Crane‐50 through 89 tons (and less than 150 feet boom); Bulldozer: over 70,000 lbs up to and including 120,000; Loader: 60,000 lbs and less than 120,000 lbs; Excavator: over 80,000 lbs through 130,000 lbs
GROUP 4: CRANE: Hydraulic Crane Operator, under 50 tons;
LATTICE BOOM CRANE OPERATOR: Lattice Boom Crane Operator, under 50 tons; TRACKHOE/BACKHOE‐ROBOTIC: up to and including 20,0000 lbs. with any or all attachments; BLADE:
Blade operator; Tractor operator with boom attachment;
DRILLING: Churm Drill and Earth Boring Machine Operator;
Directional Drill Operator over 20,000 lbs pullback; CRANE:
Chicago boom and similar types; Boom type lifting device, 5 ton capacity or less; Asphalt Paver; Mechanic; Bulldozer:
over 20,000 lbs and more than 100 horse and up to 70,000 lbs; Loader: 25,000 lbs and less than 60,000 lbs; Screed;
Excavator: over 20,000 lbs through 80,000 lbs.
GROUP 5: TRACKHOE/BACKHOE‐HYDRAULIC: up to and including 20,000 lbs.; Open wheeled type; DRILLING: Churm Drill and Earth Boring Machine Operator; Directional Drill Operator less than 20,000 lbs pullback; Concrete Pumper; Concrete Paver; forlkift over 5 ton; Bulldozer: 20,000 lbs or less, or 100 horse or less; Loader: ruber tired type, less than
25,000 lbs; Roller
GROUP 6: LOADERS: (less than 1 cu yd.); Oiler; Crane oiler;
forklift; Broom; Roller (Non‐Asphalt)
Zone Differential (add to Zone 1 rates):
Zone 2 ‐ $3.00 Zone 3 ‐ $6.00
For the following metropolitan counties: MULTNOMAH;
CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA;
CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS
INDICATED:
All jobs or projects located in Multnomah, Clackamas and Marion Counties, West of the western boundary of Mt. Hood National Forest and West of Mile Post 30 on Interstate 84 and West of Mile Post 30 on State Highway 26 and West of Mile Post 30 on Highway 22 and all jobs or projects located in Yamhill County, Washington County and Columbia County and all jobs or porjects located in Clark & Cowlitz County, Washington except that portion of Cowlitz County in the Mt.
St. Helens ""Blast Zone"" shall receive Zone I pay for all classifications.
All jobs or projects located in the area outside the identified boundary above, but less than 50 miles from the Portland City Hall shall receive Zone II pay for all classifications.
All jobs or projects located more than 50 miles from the Portland City Hall, but outside the identified border above, shall receive Zone III pay for all classifications.
For the following cities: ALBANY; BEND; COOS BAY; EUGENE;
GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG
All jobs or projects located within 30 miles of the respective city hall of the above mentioned cities shall receive Zone I pay for all classifications.
All jobs or projects located more than 30 miles and less than 50 miles from the respective city hall of the above mentioned cities shall receive Zone II pay for all classifications.
All jobs or projects located more than 50 miles from the respective city hall of the above mentioned cities shall receive Zone III pay for all classifications.
IRON0029‐013 07/01/2020
Rates Fringes
IRONWORKER (Reinforcing and Structural)......................$ 39.10 29.75
LABO0737‐005 06/01/2019
Rates Fringes
Laborers: (Mason Tender‐Cement/Concrete)..........$ 31.56 14.60
LABO0737‐006 06/01/2019
Rates Fringes
Laborers: (Mason Tender‐Brick)...$ 31.56 14.60
LABO0737‐022 06/01/2019
Rates Fringes
Laborers:
GROUP 1.....................$ 30.82 14.57
GROUP 2.....................$ 31.97 14.57
GROUP 3.....................$ 26.72 14.57
LABORER CLASSIFICATIONS
GROUP 1: Form‐Stripping
GROUP 4: Grade Checker, Pipelayer
GROUP 5: Flagger
PAIN0055‐021 07/01/2019
Rates Fringes
DRYWALL FINISHER/TAPER...........$ 38.48 16.71
PAIN0055‐024 07/01/2020
Rates Fringes
Painters:
Brush, Roller and Spray.....$ 22.94 13.34
PLAS0555‐006 07/01/2020
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 35.52 19.42
PLUM0290‐008 04/01/2020
Rates Fringes
Plumbers and Pipefitters.........$ 47.43 31.74
SHEE0016‐017 07/01/2019
Rates Fringes
Sheet metal worker (Excluding metal roof)......................$ 28.43 18.53
TEAM0037‐008 06/01/2020
Rates Fringes
Truck drivers:
GROUP 1.....................$ 29.33 16.40
GROUP 2.....................$ 29.20 16.40
GROUP 3.....................$ 29.34 16.40
GROUP 4.....................$ 29.62 16.40
GROUP 5.....................$ 29.85 16.40
GROUP 6.....................$ 30.03 16.40
GROUP 7.....................$ 30.24 16.40
TRUCK DRIVERS CLASSIFICATIONS
GROUP 1: Dump trucks, side, end and bottom dumps: up to and including 10 cu. yds.
GROUP 2: Dump trcuks/articulated dumps 6 cu to 10 cu.;
GROUP 3: Dump trucks, side, end and bottom dumps: over 10
cu. yds. and including 30 cu. yds., includes articulated dump trucks
GROUP 4: Dump trucks, side, end and bottom dumps: over 30 cu.
yds. and including 50 cu. yds. and includes articulated dump trucks
GROUP 5: Dump trucks, side, end and bottom dumps: over 50
cu. yds. and including 60 cu. yds. and includes articulated dump trucks
GROUP 6: Dump trucks, side, end and bottom dumps: over 60
cu. yds. and including 80 cu. yds. and includes articulated dump trucks
GROUP 7: Dump trucks, side, end and bottom dumps: over 80
cu. yds. and including 100 cu. yds., includes articulated dump trucks
SUOR2009‐038 11/09/2009
Rates Fringes
LABORER: Common or General......$ 26.48 7.50
SHEET METAL WORKER (Metal Roofs Installation)..............$ 23.65 6.33
SPRINKLER FITTER (Fire Sprinklers)......................$ 25.00 8.29
WELDERS ‐ Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis‐Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health‐related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health‐related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198‐005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non‐union rates. Example: SULA2012‐007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG‐OH‐0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis‐Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"